Appendix A - Workload Estimate.pdf
PDF 5 MB Posted
- Attached to
- BASE OPERATIONS SUPPORT SERVICES (BOS), AVON PARK - AMENDMENT 02 Federal contract opportunity
- Solicitation number
- FA481421R0002
About this file
This is a solicitation for base operations support services at Avon Park Air Force Range in Florida. The Department of the Air Force is seeking proposals for a one-year base contract with six one-year options to provide range maintenance, target construction and maintenance, civil engineering, refuse collection, custodial services, and other support functions. The pre-proposal conference will be held on May 25, 2021, with questions due by June 2, 2021. The NAICS code is 561210 and the small business size standard is $41.5 million. The solicitation is fully set aside for 8(a) small businesses and will be awarded as a fixed-price contract.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX A – WORKLOAD ESTIMATES
Appendix A-1 Workload Estimate
Range Maintenance Workload 0BQuantity 1BFrequency
Roads & Grounds Maintenance
Heavy Equipment Support for EOD personnel 100 hrs Year North Target Complex (see Appendix B-1-1)
Shell Road R&M, as needed, 2.1 miles 2 Year Asphalt Road R&M, as needed, 1.6 miles 2 Year Culvert R&M, as needed, 16 total. 2 culverts Year Disking , 162 acres 2 Year Mowing, 34.7 acres 2 Year
South Target Complex (see Appendix B-1-2)
Shell Road R&M, as needed, 5.5 miles 2 Year Asphalt Road R&M, as needed, 1.6 miles 2 Year Dirt Road R&M, as needed, 1.3 miles 2 Year Culvert R&M, as needed, 62 total ea 2 culverts Year Disking , 239.8 acres 2 Year Mowing, 45.7 acres 2 Year
Maintain South Conventional Assault Strip (2799 ft. X 26 ft.)
2 Year
Oscar Target Complex (see Appendix B-1-3)
Shell Road R&M, as needed, 0.55 mile 1 Year Asphalt Road R&M, as needed, 0.83 mile 1 Year Culvert R&M, as needed, 11 ea. 1 culvert Year Disking , 12.8 acres 2 Year Mowing, 15.1 acres 2 Year
Target and Range Maintenance/Repairs
Replace strafe target pole(s), South Conventional 2 Year Replace strafe target pole(s), North Conventional 1 Year Rebuild strafe target berms, South Conventional 4 Year Rebuild strafe target berms, North Conventional 2 Year
Receive, unload, transport, store delivered target materials 100 deliveries Year Sanitize and place target vehicles 30 Year Prepare and place shipping containers 75 Year Place concrete construction blocks 175 Year Paint targets 100 gallons Year Sanitize existing targets on range 6 Year Oscar Range Target Complex
Maintain rail mover 1 Year Maintain rail track 1 Year Maintain 660 feet long x 8 feed wide protective berm, Oscar
1 Every 5 Years
Mow/Herbicide 660 feet long x 8 feet wide Berm 4 Year Maintain and update equipment inventory 1 Month Troubleshoot/maintain/repair electronic/manual gates and associated camera system within the cantonment, airfield & range complexes
13 automated 13 manual
8 camera systems
Quarter
Coordinate & schedule disposal & shipment of Low Level Radioactive Waste with other government agencies
1 Every 2 years
Inspect/maintain/repair/replace range complexes’boundary lights
30 ea Month
Special Projects w/heavy equip ops work 700 hrs Year
Appendix A-1-1 Range Target Descriptions
Range Maintenance
NORTH TACTICAL RANGE
Target # TARGET DESCRIPTIONS NT-1 Eight 20 ft containers. Ten 10ft concrete blocks. One 500 gallon tank. One fuel truck and two pick up trucks NT-2 None assigned NT-3 One F-4 aircraft. (Aircraft Holding short of runway) NT-4 One F-4 aircraft. (Aircraft on South end of runway) NT-5 Four Joint Modular Target Ground (JMTG) MIG aircraft, twenty six 20-foot containers, fourteen 20-foot ½ containers and six AAA guns. (Aircraft Parking Ramp) NT-6 Sixteen 20-foot containers, three AAA guns, and three large vehicles. (2 ½ ton truck). Field HQ &
VehicleParking) NT-7 Four 20-foot containers, one 40-foot container, two 20-foot ½ containers, two AAA guns, two vehicles
(car/pick-up) and one large vehicle. (Control Tower/Base Operations) NT-8 Four 20-foot containers and fourteen large vehicles. (Airfield Truck Park) NT-9 Twenty five 20-foot containers, two hundred seventy six 10-foot concrete construction blocks and forty two 5-foot concrete construction blocks. (Observation Post #5) NT-10 Two AAA guns, three large target vehicles and 6 HMMVEs. (Convoy)
NT-11 (Urban Village) 46 buildings constructed of 16 each forty foot shipping containers , 125 each twenty foot shipping containers, 40 each half size shipping containers, 1,189 each ten foot concrete construction blocks, 106 eacheight foot concrete construction blocks, 59 each six foot concrete construction blocks, 208 each five foot concrete construction blocks, 21 each three foot concrete construction blocks, 8 each two foot concrete construction blocks, twelve Large vehicles (two ½ ton or larger vehicle), seven small vehicles (pickup truck and smaller vehicles), one gas pump.
NT-12 (Mini Urban Village) Eight buildings, constructed of eleven 20 foot shipping containers, one hundred eighty four 10 foot concrete construction blocks, twenty six 5 foot concrete construction blocks and five smallvehicles.
NT-13 Six target vehicles and two F-4 aircraft.
NT-14 (SA-2 Site) 6 JMTG missiles mounted on six 10 foot concrete construction blocks, one Large vehicle and one radar trailer NT-15 (Helicopter Landing Zone) two UH-1s and two small vehicles NT-16 (Cave Complex) Two 20 foot shipping containers NT-17 JMTGs (Vehicles in tree line) six JMTGs NT-18 (Aircraft North end of Runway) One T-29 acft NT-19 (Aircraft North end of Runway) One F-4 NT-20 (Aircraft on Center of Runway) One A-4 NT-21 Not assigned NT-22 (Ammunition Storage Area) Four ½ shipping containers, two large vehicles NT-23 ( Reverted Vehicles) Four Armored Personnel Carriers, two AAA guns and Seventy 8 foot concrete constructionblocks NT-24 Not assigned NT-25 (Industrial Complex) Six ½ shipping containers, Ten 40 foot shipping containers, Fifty one 20 foot shipping containers, Two culverts 48’’ X 30’, Three 18 wheeler trailers, One Semi Tractor, Two small vehicles and 2 AAA guns
NT-26 (Aircraft South end of Taxiway) One F-4 DFP-E (Direct Fire Point 50 Cal and Below) DFP-F (Direct Fire Point 50 Cal and Below) DFP-G (Direct Fire Point 7.72 and Below) One Van and One shooting trailer OP-1 (Observation Tower)
Appendix A-1-1 Range Target Descriptions
Range Maintenance
NORTH CONVENTIONAL RANGE
Target # TARGET DESCRIPTIONS NC-1 (HE) APC HE Target) Four APC vehicles NC-2 (Right Bomb Circle “Dive-bomb”) One large vehicle NC-3 (Right Strafe Pits) NC-4 Left Bomb Circle (Helo brown-out) One large vehicle NC-5 (Left Strafe Pits) NC-6 (HE) Village “AC130 Target”) Five large vehicles and twenty six 20 foot shipping containers NC-7 (HE) Cave Complex) One 20 foot shipping container, four AAA and thirty eight 10 foot concrete constructionblocks NC-8 (HE) Mini Village “AC130 tune-up target) Seven large vehicles and thirteen 20 foot shipping containers NC-9 (HE) Hellfire Target) Six large vehicles DFP-H 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-H”
Sign material shall comply with Laser Requirements) DFP-I 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-I”
Sign material shall comply with Laser Requirements) DFP-J 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-J”
Sign material shall comply with Laser Requirements) DFP-K 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-K”
Sign material shall comply with Laser Requirements) DFP-L 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-L”
Sign material shall comply with Laser Requirements) DFP-M 50 cal and below Direct Fire Point (One 4 foot high post with a12x12 inch sign that reads “DFP-M”
Sign material shall comply with Laser Requirements)
SOUTH TACTICAL RANGE
Target # TARGET DESCRIPTIONS ST-1 (Eight Vehicle Convoy) 8 each Large Vehicles ST-2 (Command Bunker) Sixty 10 foot concrete construction blocks, four large vehicles, two AAA guns ST-3 (APC and Bridge) Three APCs, one bridge made up of three bridge section ST-4 (SA-3 Site) Five large vehicles (four with fake missiles attached), one radar van ST-5 (SA-2 Site) Six JMTGs, one large vehicle with radar dome, six 10 foot concrete construction blocks ST-6 (Aircraft on North end of Runway) One A-4 ST-7 (Aircraft on North end of Taxiway) One F-4 ST-8 (Aircraft on Center of Runway) One F-4 ST-9 (Urban Village) 260 eachtwenty foot shipping containers, 17 each½ size shipping containers, 14 each forty foot shipping containers, 8 eachlarge vehicles, 3 each small vehicles, 5 each AAA guns
ST-10 (AAA with Radar) One large vehicle with radar dome, three AAA guns ST-11 (Control Tower) two ½ shipping containers, one 40 foot shipping container, four 20 foot shipping containers, one UH-1, two AAA guns ST-12 (Fire Dept and Aircraft Parking Ramp) 5 each APCs, 6 each twenty foot containers, 2 each small vehicles ST-13 (West Truck Convoy) Six large vehicles ST-14 (Aircraft on South end of Runway) One F-100 ST-15 (POL Tank) One gallon tank ST-16 (Mini Village) Twenty four 20 foot shipping containers, six large vehicles ST-17 (HE) Eight extra-large vehicles, four 20 foot shipping containers ST-18 (South Reveted Aircraft) One A-4 ST-19 (North Reveted Aircraft) One A-4 ST-20 (Mini Village) Fifty three 20 foot shipping containers, 3 large vehicles, two small vehicles ST-21 (Vehicle Defense Perimeter) Four large vehicles ST-22 (Ammo Storage Area) Twenty 20 foot shipping containers, four ½ shipping containers, thirty nine 10 four concrete construction blocks, two large vehicles
ST-23 (Headquarters Bldg.) Twenty eight 20 foot shipping containers, thirteen ½ shipping containers ST-24 (Cave Complex) One 20 foot shipping container, twenty eight 10 foot concrete construction blocks, four AAA guns ST-25 (7 Vehicle Convoy) Four large vehicles ST-26 (Mortar Bunker) One 20 foot shipping container, one ½ shipping container, three AAA guns ST-27 (3 Vehicle Convoy) Three large vehicles ST-28 (4 APC Convoy) Four extra-large vehicles DFP-P 50 Cal and Below (Direct Fire Point) DFP-Q 7.62mm and Below (Direct Fire Point)
SOUTH CONVENTIONAL RANGE
Target # TARGET DESCRIPTIONS
SC-1 (Nuke Target) One Large Vehicle SC-2 (Right Bomb Circle “Dive”) One 20 foot shipping container SC-3 (Right Strafe Pits) SC-4 (Left Bomb Circle “Dive”) One 20 foot shipping container SC-5 (Left Strafe Pits) SC-6 (High Angle Strafe) One 20 foot shipping container DFP-N 50 Cal and Below (Direct Fire Point) DFP-O 50 Cal and Below (Direct Fire Point)
OSCAR RANGE TARGET COMPOSITION
Target # TARGET DESCRIPTIONS
N/A Moving target N/A Vehicles: two Small and one medium
Appendix A-1-2 Range Strafe Berms Description
Appendix A-2-1
Environmental Programs Support
Workload Quantity Frequency
Workload applicable to all environmental programs
Waste Management Program
Participate in Spill Response Exercises 1 Year Undergo RCRA inspection by Florida Department of Environmental Protection (FDEP)/EPA
1 Year
Provide data to update the Hazardous Waste Management Plan
1 Year
Provide data to update Spill Prevention Control and Countermeasure Plan
1 Year
Meet with RMFI HAZWASTE Manager 1 Week Cleanup of hazardous discharges 4 Year
ASBESTOS AND LEAD BASED PAINT
Schedule any workers with potential for exposure for training as required by EPA, nd FDEP
1 Annual
Draft FDEP Notification for proposed asbestos work 1 Annual Review and update Government provided Asbestos and Lead Based Paint Management Plans
1 Annual
Inspect existing facilities identified with asbestos containing materials (ACM) for potential exposure
2 Annual
Abate ACM 1 Annual Provide and maintain records of asbestos removal, transportation, and disposal
1 Annual
Report all ACM removal projects 1 Annual Review facility project documents for asbestos requirements
2 Annual
Identify unreported ACM locations discovered during maintenance activities
1 Month
Respond to customer concerns / complaints 1 Annual
CLEAN WATER
Inspect oil-water separators 1 Month Maintain, Clean Out, Remove Oil-Water Separators 1 Quarter
Update backflow prevention survey 1 Annual
Perform backflow device inspection 21 Annual
Maintain/install/replace backflow prevention devices 3 Annual
Inspect hose bib vacuum breakers 92 Annual
Inspect and Clean out Storm Water Traps 6 Annually
STORAGE TANKS
Perform AST inspection 1 Week Maintain Inventory/Issue Data 1 Daily
Provide data for EPA Report 1 Annual
Report release from tanks 1 Annual
POLLUTION PREVENTION & SOLID WASTE
Provide Data for base Pollution Prevention Management Plan
1 Annual
Provide Data for Solid Waste Management Plan 1 Annual
Report solid waste disposal quantities 1 Month
Maintain solid waste disposal weights/quantities records
1 Month
HAZARDOUS MATERIAL (HAZMAT) PROGRAM
Review and identify hazardous materials requirements and acquisitions and enter data in
ESOHMIS-HM
2 Year
ENVIRONMENTAL MANAGEMENT SYSTEM
Participate in EMS Cross-Functional Team Meetings 1 Quarterly
Attend initial and annual refresher training on EMS and Environmental Awareness
1 Annual
WASTE MANAGEMENT WORKLOAD
Activity Unit of Measure
Size Quantity Frequency
Manage, handle, label and maintain records for:
Wash Rack sludge Drum 55 gal 8 Annually Used paint/solvents Drum 30 gal 8 Annually Antifreeze Drum 55 gal 6 Annually Contaminated dirt/petroleum From spill/leak cleanups
Drum 55 gal 4 Annually
Used oil for energy recovery Drum 55 gal 24 Annually Unleaded Fuel Drum 55 gal 6 Annually Off spec diesel fuel Drum 55 gal 25 Annually Absorbent Material Drum 55 gal 8 Annually Freon Cylinder 20 lb 4 Annually Lead Batteries Pallet N/A 10 Annually Batteries, other Drum 5 Gal 10 Annually NICAD batteries Drum 10 gal 4 Annually Fluorescent lamp bulbs Container 36 bulbs/ container 16 Annually
Mercury containing devices Drum 8 gal 1 Annually
WASTE MANAGEMENT WORKLOAD
Activity Unit of
Measure Size Quantity Frequency
NICAD Batteries (target vehicles)
Pallet 1 ea 3 Annually
Used oil filters Drum 55 gal 6 Annually Parts washer Drum 55 gal 1 Annually Waste Grease Drum 55 gal 3 Anually
Coordinate pumping of waste oil from oil/water separator
Event N/A 2 Quarterly
Coordinate pumping of waste oil from used oil tank and UTES
Event N/A 1 Quarterly
Inspection of Satellite points Hours N/A 4 Quarterly Conferring with Hazardous Waste Manager Hours N/A 0.25 Weekly
Environmental Impact Analysis Process Workload Activity Quantity Frequency
Review and Process planned activities
AF Form 332-Civil engineering Work Requests 55 Annually AF Form 813-Request for Environmental Impact Analysis
50 Annually
AF Form 103-BCE Work Clearance Request 20 Annually
Assist with preparation/tracking of SHPO &USFWS Consultations
12 Annually
Appendix A-2-2 Workload Estimate for WBS 1.2.2
Civil Engineering – Facility & Infrastructure Operations & Maintenance & Management
Prepare budget inputs for all contractor CE areas 10 Year Inspect Bridges, 6ea
After severe storms, i.e., floods, hurricanes twice Year Work Orders/Job Orders (WO/JO)
Track WO/JOs 145 Month Initiate
Priority 1, Emergency 115 Year Priority 2, Preventive Maintenance & Plant Ops 900 Year Priority 3, Corrective Maintenance 650 Year Priority 4, Enhancement Work 50 Year
Initiate, coordinate and track AF Form 103, Base Civil Engineering Work Clearance Request
25 Year
Maintain the warranty/guaranty program for construction and equipment: Evaluate, make calls & schedule for warranty service work
1 Month
Participate in Commander’s staff meetings and other required meetings (WORB and Contract Evaluation)
3 Week
Test Fire Alarm Systems 27 Year Inspect & test (annual flow test) Sprinkler Systems 5 Year Service Hand held and Wheeled Fire Extinguishers 198 Year Barriers preventative/recurring maintenance - BAK-12 2 Barriers
Inspect and Test
Mon – Fri 1 Day Take down systems 15 Year Put back up systems 15 Year
Repair BAK 12 or E 5 systems 4 Year Inspect and repair generators and fuel tanks, 10 each installed & 1 spare
1 Week (Bi-weekly), Monthly/Quarterly/
Semi-annual/Annual)
Repair generators (hardwired to facilities & portables) 15 Year Prepare, setup and coordinate special events (Memorial Day, Veteran’s Day, Change of Command, Open House, etc)
5 Year
Participate in emergency/contingency actions
Hurricane 3 Year Exercises 6 Year Aircraft crash 1 Every 2 Years
Repair air conditioning systems (75 units) 60 Year Facility Maintenance
Painting, exterior touch up associated with M&R 1,500 Sq Feet Year Painting, interior touch up associated with M&R 2,500 Sq Feet Year Plumbing 55 Service Calls Year Locksmithing 110 Service Calls Year Interior electric job orders 135 Year Carpentry 60 Service Calls Year Bridges 6 Year
Airfield lighting, beacon, and power circuit job orders 50 Year Welding jobs for facilities and equipment,, , 15 Year Sheet metal/metal working job orders 5 Year
Appendix A-2-2 Workload Estimate for WBS 1.2.2
Civil Engineering – Facility & Infrastructure Operations & Maintenance & Management
Repair Airfield pavement 500 SF Year Repair Airfield pavements - Crack & spall 2,500 LF Year Maintain Airfield Assault Strip (3000 feet long x 50 feet wide)
6 Year
Concrete pad work 350 Sq Feet Year Pump the oil water separator , used oil tank, and the drums at UTES
4 Year
Inspect & repair Cathodic protection systems, ea. 4 Year Test & Maintain All Grounding Systems 1 Year Test & maintain aircraft engine thrust anchor system 1 Year Fill in pot holes on all roads maintained in contract per map
25 Year
Repair/replace culverts / headwalls 6 Year Sweep airfield pavements – runways, taxiways, & aprons 1,000 man-hours Year Install/maintain/replace and unobstruct view for road, building, fence, and installation & impact ranges boundary signs
50 Year
Repair chain link fencing 150 LF Year Inspect, maintain, repair, replace damaged installation perimeter & impact ranges boundary barbed wire/hog fabric & postfencing
500 LF
Year
Pressure wash exterior facilities 8 each Year Maintain and Repair ice-makers 4 Year Maintain, repair, and set-up portable Security Barriers, 2ea 4 Year Maintain, repair, and set-up portable loading ramps, 3ea 4 Year Maintain ASP & Armory security alarm systems 1 Qtr
Workload Relating to Environmental Flight Support, including operator
Activity Equipment Item Annual Frequency DURATION Annual Requirement (hours)
Clean/Remove cattle Guards
Backhoe 2 8 16
Spread shell Backhoe 1 8 8 Dig Burial pit Backhoe 3 8 24 Unload Supplies
Forklift 12 2 24
Load Scrap Forklift 1 8 8 Maintain Shell/dirt Roads
Grader
Load Shell Loader 1 8 8 Place Culverts Loader 4 8 32 Mowing Ag Tractor 5 40 20 Firebreak Disking mpact and non-impact areas
Ag Tractor w/Disk (needed when Gov Equip or personnel are not available)
2 40 80
Maintain Shell/dirt Roads
Dump truck
Transport Equipment
Tractor w/trailer 8 4 32
Appendix A-2-3 Workload Estimate for WBS 1.2.3
Civil Engineering – Project Programming and Engineering Services
Initiate AF Form 9, Purchase Request 20 Year Update active hardcopy ASPR/Q project files 130 files As changes occur Maintain current on-line data for ACES-PM project records, (active/inactive) project records As changes occur
Initiate and plan Sustainment, Restoration, and Modernization (SRM) Work Order projects to be accomplished by contract or in-house personnel.
12 Year
Develop, and prepare project planning & programming documents (i.e., DD1391, Gov’t Estimate, etc) for FSRM projects to be accomplished by contract which require MAJCOM project specific funding
12 Year
Design and/or coordinate and participate with design agent of FSRM projects to be accomplished by contract with MAJCOM project specific funding
12 Year
Provide construction inspection services for contractor accomplished FSRM projects. Construction projects will be accomplished through contracting vehicles from agencies such as but not limited to MacDill AFB and Moody AFB Contracting Squadrons, AFCESA; AFCEC;
and the Corps of Engineers
12 Year
Develop, and prepare all project planning, programming documents (i.e., DD Form 1391, Gov’t Estimate, cost benefit analysis, D3 sheets, , etc) for SRMC Projects greater than $5 Million
1 Year
Develop, and prepare all project planning, programming documents (i.e., DD Form 1391, Gov’t Estimate, cost benefit analysis, D3 sheets, , etc) for UMMC or MCP project
1 Every 5 Years
Maintain the warranty/guaranty program for construction and equipment: Evaluate, make calls & schedule for warranty service work
1 Month
Participate in Commander’s staff meetings and other required meetings (WORB & Contract Evaluation)
3 Week
GIS/Geo Base Workload
Maintain GIS/GeoBase data to meet SDSFIE standards
2 Daily
Provide paper maps from GIS/GeoBase data. 5 Week Update Mission Data Sets 3 Week Perform data quality control (data provided by data stewards)
2 Daily
Perform data storage and retrieval 1 Quarter Assist in preparation & maintenance of explosive siting packages for DoD Safety Board Approval
2 Year
Assist in preparation & maintenance of explosive siting packages to meet the requirements of AFMAN 91-201, Explosive Safety Standards
2 Year
Appendix A-2-4 Workload Estimate for WBS 1.2.4
Civil Engineering – Facility Operations: Refuse Collection
ITEM
NAME
ESTIMATED
QUANTITY
1 Annual Refuse Volume 250 Tons
2 Bulk Dumpster 1 Each
3 Distance To Disposal Site 60 Miles
REFUSE COLLECTION TASKS & FREQUENCY TABLES
Task Item
Number
SIZE
FREQUENCY
Dumpsters 10/*11 4 Cubic Yard Estimated at once a week
Dumpsters 3/*4 8 Cubic Yard Estimated at once a week
Dumpsters 1 8 Cubic Yard Every 2 weeks - Recyclables
Roll-off 1 20 Cubic Yard 8 Pulls a year (Reimbursable cost) Cleaning *14/16 4/8 Cubic Yard As Required
* NOTE: 14 (ea) dumpsters from 1 February through 30 September, and 16 (ea) dumpsters from 1 Oct through 31 January. One additional 8 CY dumpsters will be located at Morgan Hole Campground and one additional dumpster will be located at Willingham Campground during the period of 1 Oct through 31 January.
DUMPSTER LOCATIONS
BUILDING/FACILITY SIZE (CY) NUMBER of DUMPSTERS 102 4 1 236 4 1 236 8 1 475 4 1 600 4 1 2000-Willingham Camp Grounds 4 1 *(1) 28 4 1 29 4 1 29 8 1 44 4 1 43 4 1 77 8 1 2000-Morgan Hole Camp Grounds 8 1 *(1) COR designated 20 (roll-off) 1
* Increases by number shown from 1 Oct through 31 Jan
Appendix A-2-5 Workload Estimate for WBS 1.2.5
Civil Engineering – Facility Operations: Custodial Services
Air Force Custodial Standards – AFCOLS 3 Standard AF CUSTODIAL SERVICES: Level 2 Cleaning (Basic) TASK / SERVICE Level 2 Cleaning - Basic
General Administrative and Industrial Areas - Wing Staff Agencies, Admin Facilities/ Offices, Education Center Classrooms, PME Schools, Sq.
Command Sections, Hangars, Laboratories, Shops, Warehouses, Computer Rooms, Auditoriums, Break Rooms, Lobbies, Conference Rooms, etc…
SWEEP FLOORS 1 time every 2Weeks MOP FLOORS 1 time every 2 Weeks BUFF FLOORS As required for emergency spot cleaning MAINTAIN/STRIP FLOORS As required for emergency spot cleaning VACUUM CARPET 1 time every 2 Weeks SHAMPOO CARPET As required for emergency spot cleaning CLEAN WALK-OFF MATS 1 time every 2 Weeks TRASH COLLECTION/REMOVAL 1 x per Week @ central locations REST ROOMS (All tasks/services) 2 x per Week
- RESUPPLY REST ROOMS
- CLEAN DRINKING FOUNTAINS
- CLEAN WALLS/PARTITIONS
- SWEEP/DAMP MOP FLOORS
- CLEAN/DISINFECT REST ROOMS
- DESCALE TOILETS & URINALS
- REMOVE TRASH
Cleaning Level 2 - Basic
Facility No.
Address
Description
User/Agency
Restroo m SF
Carpet
SF
Hard Floor SF
Total Cleaned SF per Facility
24 South Blvd Wildland Fire Control Equipment Maintenance shop
AFCEC Natural Resources Wildland Firefighters
540 0 0 540
26 South Blvd Auditorium Various/598
RANS, 23 FG
0 0 2,342 2,342
29 South Blvd Administrative Offices
Commander & Support Staff/ 598
RANS, 23 FG
600 780 2,840 4220
44B South Blvd Hangar Rest Room
TDY Forces /598
RANS, 23 FG
420* 0 0 420
45 South Blvd Range Ops Ctr TDY Forces /598
RANS, 23 FG
286 450 590 1,326
65 South Blvd Target Maintenance & Fabrication Facility
Range Ops & TDY Forces/ 598
RANS, 23 FG
56* 0 0 56
77 South Blvd Warehouse TDY Forces /598
RANS, 23 FG
280* 0 0 280
236 South Blvd Deployed Unit Complex
TDY Forces /598
RANS, 23 FG
273 1,200 0 1,473
Civil Engineering – Facility Operations: Custodial Services Cleaning Level 2 - Basic Facility
No.
Address Description User/Agency Restroom
SF
Carpet
SF
Hard
Floor SF Total Cleaned
SF per Facility
424 South Blvd Administrative Offices & Armory
TDY Forces/ 598
RANS, 23 FG
168* 0 0 168
434 South Blvd Raquetba ll Court
TDY Forces/ 598
RANS, 23 FG
36 0 0 36
435 South Blvd Restroom Facility
TDY Forces/ 598
RANS, 23 FG
160* 0 0 160
439 South Blvd **Physical Fitness Exercise Facility
TDY Forces/ 598
RANS, 23 FG
470* 0 1,080 1,550
600 Frostproof Road
Environmental Admin Offices
Environmental/
598 RANS, 23 FG
80 0 0 80
Totals: 1,815 2,430 6,852 12,524
* Facilities are occupied by TDY forces conducting training at the range. When unoccupied the service level can be reduced to a weekly basis. When occupied the normal level of service would apply.
** This facility is not operated by a Services Squadron function. It is operated using 598 RANS, 23 FG unit funds and not occupied on a full-time basis. Permanent party and TDY forces utilize this facility
Civil Engineering - Facility Operations: Custodial Services
Workload Estimate for WBS 1.2.5 Civil Engineering - Facility Operations: Custodial Services
Services
Workload Estimate for WBS 1.2.5 Civil Engineering - Facility Operations: Custodial
Workload Estimate for WBS 1.2.5 Civil Engineering - Facility Operations: Custodial Services
Appendix A-2-6
Workload Estimate for WBS 1.2.6 Civil Engineering – Facility Operations: Grounds Maintenance and Landscaping
EDGING WORKLOAD
Below table depicts the historical linear footage of edging work to be done by either wheeled edger, trim -line trimmer, or herbicide.*. Method chosen by contractor will be at his discretion.
Facility Number
Linear Feet (LF) to be edged
NOTE
29 4,129 D, B, F, & PL
45 812 B, SW
236 6,063 SW, B, PL, RT
447 856 SW, C
600 1,057 B, C, AFLD fence 15,000 F Total LF 12,917
Notes:
B = Building C = Curb D = Ditch F = Fence
PL = Parking Lot RT = Running Track SW = Side walk
* Only when included in approved pest management plan
ITEM DESCRIPTION ESTIMATED
QUANTITIES
ESTIMATED WORKLOAD (#
TIMESANNUALLY)
Quantity Unit Growing Season Non-Growing Season
1 Mow Improved Grounds (3” – 4”) 80 Acres 30 11
2 Edging 12,061 Linear Feet 14 5
3 Trimming 1,200 Linear Feet 30-36 1-16
4 Irrigation 1 Acres 16 7
5 Debris Removal and Policing 1 Acres 25 27
6 Fertilizer and/or Lime 1 Acres 2 2
7 Renovate Lawns 2 Acres 1
8 Prune Shrubs and Other Plants 10 Each 6 2
Appendix A-2-6 Workload Estimate for WBS 1.2.6
Civil Engineering – Facility Operations: Grounds Maintenance and Landscaping
ITEM DESCRIPTION ESTIMATED
QUANTITIES
ESTIMATED WORKLOAD (#
TIMESANNUALLY)
Quantity Unit Growing Season Non-Growing
Season
9 Semi-improved Grounds (excluding BASH areas) (4” - 10”)
183 Acres 15 11
10 Semi-improved Grounds BASH area (7” – 14”)
678 Acres 15 11
11 Tree and Stump Removal 2 Each 1 1
12 Flower and Rock Beds and Related Areas
1000 Square Feet 7 3
13 Surface Drainage Ditches 26,572.57 Linear Feet 10 5
14 Tree Pruning 10 Each 1 1
Appendix A-2-7 Workload Estimate for WBS 1.2.7
Civil Engineering – Facility Operations: Pest Management
PEST MANAGEMENT WORKLOAD
ITEM NAME
ESTIMATED
QUANTITY UNIT
1 Pest Control Program Implementation & Management 12 Months
2 Total building area office space 256,000 Square feet
3 Total building area industrial space 52,240 Square feet
4 Total land area maintenance 5,145 Acres
5 UNIQUE PESTS TO BE CONTROLLED
Spiders, to include infestations
RATS
SNAKES
Occurrences/Year
PEST MANAGEMENT/HERBICIDING WORKLOAD
Work Description Quantity Frequency Herbicide runway & taxiway edges (exclude airfield lighting)
129,806 Sq Ft Minimum of Quarterly or as required due to growth
Herbicide Assault Strip 288,000 Sq Ft Minimum of Quarterly or as required due to growth
Herbicide Inactive (14/32) Runway 50,000 Sq Ft Minimum of Quarterly or as required due to growth
Herbicide Runway Distance Markers 334 Sq Ft Minimum of Quarterly or as required due to growth
Herbicide Bravo, Charlie, and Oscar Ranges
12.5 Acres Quarterly to semi-annually depending on
growth
Herbicide fence lines 40 miles Semi-annually Herbicide exotic invasive plant species
40 hours Month
Appendix A-3-1 Workload Estimate-for WBS 1.3.1
Support - Administration
Receives, processes, and submits quarterly/Annual Award packages
1/1 Qtr/Annual
Accomplishes preparation and tear down tasks for Commander’s Call
6 Year
Receives, coordinates, processes Drug Demand Reduction Testing notifications
12 Year
Monitors data and tracks suspense’s for military evaluations 4 Year Perform Organizational Defense Travel Administrator (ODTA) functions
3 Month
Initiate and process travel orders and amendments 5 Year Manages In-Processing of Government Travel Card (GTC) and Controlled spend Account (CSA)
6 Year
Monitors/Maintains GTC and CSA Program 1 Month Manages/Administers Unit in-Coming Member In-Processing 6 Year Manages/Administers Unit Out-Processing Program 6 Year Prepares, coordinates, and submits Requests for Personnel Actions (RPAs) into the civilian personnel action request system. Tracks and reports status of actions.
2 Month
Reviews, audits, manages and processes changes to Unit Manpower Document (UMD)
1 Month
Reviews, audits, manages and processes changes to Unit Manpower Personnel Roster (UMPR)
1 Month
Monitors/tracks military Vulnerable to Move List (ML) 1 Year Receives, coordinates, researches and responds to Freedom of Information Act (FOIA) requests
1 Quarter
Coordinates Functional Area Records Management-Records Custodian SAVs and consolidates corrective actions report
1 Year
News articles prepared. Receives requests, reviews, and drafts news article for approval
4 Year
Recurring report data collection/status for personnel, subsistence strength, public affairs, and copier(s)
1 Month
Coordinates and processes reports of investigations and/or inquiries.
2 Year
Receives, processes and prepares retention packages for Commander
1 Year
Monitor Government Travel Card (GTC) reports site and notify supervisor
1 Month
Process GTC application 2 Year Initiate and process AF Form 9, Purchase Request in DEAMS 50 Year Initiate and process AF Form 616, Fund Cite Authorization in
DEAMS
6 Year
Initiate and process DD Form 448, Military Interdepartmental Purchase Reques in DEAMS
1 Month
Initiate and process AF 4009 in DEAMS 3 Month Initiate and process MORD AF Form 406 in DEAMS 1 Month Perform file maintenance (RMD, RMFF, RMFI, RMFR, RMF, and Command Section)
File documents & correspondence 5 Day Research and make changes to file plans 2 Month Calendar year file change over and purge old documents 4 Year Prepare documents for staging area 1 Year
Address, post, sort, and distribute incoming and outgoing mail 1 Day
Appendix A-3-1 Workload Estimate-for WBS 1.3.1
Support - Administration
Apply government provided postage for outgoing official mail 15 Month Input civilian time sheet data into ATAAPS with corrections (40-50 sheets)
26 Year
Make up time sheets (40-50 sheets) 12 Year Assist employees and supervisors with time sheet entries 5 Bi-weekly Conducts and/or supports special studies (i.e., Civilian time accounting & training funds expenditures, TDY Expenditures, ABSS/DEAMS Reports, and Environmental Analysis, etc.)
Year
Operate office machines
Fax 5 Month Copier 150 Month Perform operational checks of office equipment 1 Day
Prepare slide presentations in final format 4 Month Research base, local, and National publications for historical information on range
1 Day
Type correspondence (i.e., appraisals, barments/warnings, staff summary sheet (SSS) packages, union memorandums, and other official memorandums, electronic forms) in final format
6 Week
Assign suspense’s and track progress 12 Month Prepare and schedule meeting rooms for conferences, Commander’s calls, and other events
8 Month
Download CSU Personnel Reports, 8 ea 1 Month Answer telephone, refer callers to appropriate party, and take messages
As Needed As Needed
Greet visitors, locates appropriate party, and directs visitor accordingly
2 Day
Checks, inventories and orders administrative supplies for common administrative area and special actions
1 Month
Check and update hard copy Publications Binders 1 Month Check and update forms and publications library as needed for civilian work force (i.e., insurance forms/information, workman’scompensation, etc.)
1 Month
Monitor Administration radio base station
Transmissions
Normal 5 Day Scan documents, correct OCR errors, and prepare in final format reports supporting local events
45 Month
Update EOD safety briefing log and distribute information to appropriate offices as required
3 Month
Post and update bulletin boards and other information boards 1 Week Prepare AF Form 428, Overtime Requests, and reconcile with time sheets.
15 Month
Update Org chart, recall roster, call sign and phone lists 1 Bi-annual Operate security camera monitoring equipment in Building 29, Rooms 151 and 152
Operational check 1 Day Initiate repair action for cameras, Bldgs. 26, 28 & 29 24 Year
Manages/monitors, forecasts, schedules and reports Ancillary training
1 Month
Appendix A-3-2 Workload Estimate for WBS 1.3.2
Support - Supply/Fuels
Task Quantity Frequency Purchase and issue supplies/services
CE 450 Year Vehicle Maintenance 350 Year Base Operating Support (BOS) 75 Year Communications 75 Year Range Operations 80 Year
Load/unload delivery trucks 80 Year Perform inventory of working stock 10 Year Perform inventory of shop tools 1 Year Issue office supply supplies for RO, CEIE, CE, RS, and Command Section (86 items in inventory)
358 Month
Process & log Chemical/ Hazardous Material Authorization Requests
6 Month
Inventory punctured aerosol cans 1 Week Inventory Bench Stock (80 inventory items) 1 Month
Determine equipment serviceability prior to turn-in to
DRMO
80 Year
Research and order non-standard/non stock listed parts 10 Year Prepare items for release to DRMO 80 Year Fuel Keys
Issue new key 35 Year Renew or reprogram key 8 Quarter
Gallons of Fuel Issued
Local
Diesel Fuel 30,000Gallons Year Unleaded 25,000 Gallons Year Propane (delivered) 400 Gallons Year
Remote (via diesel truck) 5,000 Gallons Year Issue fuel via fuel truck 10 Month
Percent of above number that are within 15 miles 98%
Percent of above number that are greater than 15 miles
2%
Set up account for exercising units to draw funds from for fuels/provide fuel keys, and make deliveries
8 Year
Process AF Form 1898, Fuels Issue/De-fuel Documents 1 Day Perform Daily Fuel System Inspection (AFTO Form 39) 1 Daily Perform Weekly Fuel System Inspection (AFTO Form 39)
1 Weekly
Perform Monthly Fuel System Inspection (AFTO Form 39)
1 Monthly
Inventory fuel levels and usage 1 Day Inventory fuel levels and usage 1 Week Receive and receipt fuels 4 Month Document all fuel transactions in FAS 1 Daily Inventory fuel levels and usage 1 Day Inventory fuel levels and usage 1 Week Receive and receipt fuels 2 Month Document all fuel transactions in FAS 1 Daily DOD FUELMASTER Maintenance
Appendix A-3-2 Workload Estimate for WBS 1.3.2
Support - Supply/Fuels
Task Quantity Frequency Initiate Help Line calls 5 Year Perform minor repairs 5 Year Facilitate contractor repair 3 Year
PMEL
Number of items (65 items)
Inspect, pack, and ship PMEL to MacDill 35 Year Prepare material for shipping 2 Month
Welding gases
Oxygen bottles received/issued 2 Year Acetylene bottles received/issued 2 Year Nitrogen bottles received /issued 2 Year Propane bottles received/issued 2 Year
Processes documentation, updates inventory records, and prepares items for turn-in of computer equipment to appropriate function, i.e., Comm Sq, DRMO, School donation program
35 Year
Appendix A-3-3
Workload Estimate for WBS 1.3.3 Support - Communications
Key Systems
Avaya CM7 Phone Switch 1
Avaya Digital/VOIP Telephones with multi-buttons in all buildings
Single line
FAX 21
Modem on PBX 8
STU III/STE (no phones) 3
Phone Voice Lines 275
Phone line pairs to be maintained or repaired
Copper (Bldg 236 & 53) 3100 pairs
Fiber 700 strands
Troubleshoot/repair/install/move telephones 2 Month Remove and test communications circuit (static in phone lines/PRI Switch
1 Month
Test and tag communications cable pairs 2 Week Install and retrieve communications lines for field exercises
2 Year
Provide communications support for contingencies and emergencies to include Exercises
2 Year
Maintain & Repair Land Mobile Radios (LMRs) & Air to Ground
Maintain/Repair/Program LMRs & Air to Ground Radios
3 Month
Issue/Install LMRs 12 Year Number of air-to-ground radios 34
Number of hand held radios 200
Number of consolettes 6
Number of vehicle mounted radios 75
Perform TCO duties
Training 1 Year Monitor, modified & oversee CSA contract 1 Every 2 Years Review phone bills 4 accounts Month Order and distribute phone books 1 Year Accreditation of 250 phones 1 Year Prepare, process, & submit requirements via Cyberspace Infrastructure Programming System
(CIPS)
1 Year
Manage and update the Telecom Monitoring & Assessment Program (TMAP)
1 Year
Troubleshoot Avaya CM7 1 Year Preventive maintenance - Avaya CM7 daily check 1 Day Backup Control Tower voice recorder 1 Month Troubleshoot, test, maintain, and repair Crash Network Sys 2 Year Test, Maintain,and repair ground to air radios, antennas, radio console controller and radio recorder equipment in Bldgs 41, 44, North, and South Range Towers.
4 Year
Maintain APAFR frequency list up to date 4 Year Maintain Callpilot Voice Mail Sys 2 Year Network access accounts for TDY users 30 year Troubleshoot, test, maintain, repair, and change Marquee 4 Year
Locate and mark communications lines in support of AF Form 103, Base Civil Engineering Work Clearance Request
25 Year
Repair cable cuts 1 Year Troubleshoot communications lines to/from runway weather equipment
1 Month
Repair/replace phone terminal boxes 2 Year Troubleshoot/repair security cameras (16 cameras) 2 Month Backup network servers (2 servers) 1 Week/Month
PCs/Laptops/Servers/Tablets 200
Network users 95
Install personal computers (PCs), peripherals, and network components, to Install/Troubleshoot/Maintain personal computers (PCs), peripherals, network components, Switches, and Routers
250 Year
Process new users accounts 38 Year
Establish accounts for non AF users 100 Year Exercise Support - Computers 6 Year Exercise Support p Radio & Frequencies 3 Year Media Support – photo, disk, camera, video, etc 3 Year Review Security Video 3 Year Perform network utilization studies 2 Year Operate help desk and resolve hardware and software problems
15 calls Week
Set up projection system 1 Month Provide Information Assurance Awareness training
Initial 10 Year Annual/recurring 90 Year
Conduct system accreditation/ risk analysis 1 Every 2 Years Promptly resolve security incidents 2 Year Provide basic hardware training to new users 12 Year Turn in PC (purge system, etc) 45 Year Track Work Orders 40 Month Develop and maintain APAFR web page on the AF Portal 2 Month Initiate and submit communications budget 2 Year Perform annual ITAM inventory IAW IPMS 1 Year Review/Approve ITAM Purchases IAW PWS Para 1.3.3 35 Year Notification to APAFR customers of system communications/information system outages
24 Year
Switch Systems/Dedicated Circuits (Bldg 236, phone switch)
Avaya CM7, Phone switch in Bldg 53
E-911 System -Trouble Shoot, Maintain, Install Patches 4 Year Avon Park Trunk Lines (Dialing out on 9) 4 DiD/4DoD
Multiplexed Promina 200 (Circuit 7RHM) (Bldg 53 computer for phone)
MacDill Trunk Lines (Bldg 236 to 53 phone lines) 10
LAN 1
Miami LINCS – Circuit LF3V NAP2 (Range Control Tower problems troubleshoot and coordinate for repair)
Install and Upgrade application software and patches 65 Year
Operating System Upgrades and patches 75 Year Coordinate, assist and monitor ITAM requirements/ projects with HHQs (Plans & Programs)
6 Year
ITAM project planning, support and oversight 6 Year Support & update CE Industrial Control Sys - Monaco 1 Year Troubleshoot & assist Government with DSL Bldgs 41 (AFLD Tower), 43 (Fire Dept), 44 Hangar Ofc), 236 (DUC), 238 (Troop Camp), 447 (VOQ), & 600 (Hunt/Rec)
Computer Assistance trip @ MacDill DUC 1 Month
Appendix A-3-4 Workload Estimate for WBS 1.3.4 Support - Transportation Services
Building 28 vehicle wash rack
Clean out sand trap and dispose of HAZWASTE 4 Year Steam clean walls and floors 1 Month
Collect and dispose of scrap metal 2 Year Perform vehicle repairs on GO/GFVGR
Remote maintenance 60 Year Percent of remote repairs within 15 miles of shop 98%
Percent of remote repairs beyond 15 miles of shop 2%
In shop maintenance 900 Year Minor Maintenance for GO/GFVGR
In shop minor maintenance 40 Year Mobile minor maintenance 30 Year
Repair shop equipment 25 Year Provide vehicle repair in support of in-transit off-site contingencies/emergencies.
2 Year
Restock oil and grease distribution system 8 Year Research required parts 250 Year Initiate SF Form 171, Request for Drivers Training and Addition to US Government License
20 Year
Initiate DD Form 1149, Request and Invoice Shipment Document 20 Year Maintain Technical Library 20 changes Year Number of Generators (Fire Department) 3 Year Number of FMIS Input 700 Month Number of Factory Recalls 6 Year Number of Driver Training Classes Provided to APAFR Customers
4 Year
Number of GO/GFVGR vehicles towed 6 Year Number of tires turned in for recycling 150 Year GO/GFVGR Vehicle Control Workload:
GO/GFVGR Vehicle Control Training (provided to APAFR customers)
2 Year
GO/GFVGR Vehicle Control Meetings on AFAFR 1 Year VCO notifications 1 Month
Total Fleet Data Workload Number GO/GFVGR Vehicle Assigned: 61 Vehicle In-Commission Rate (VIC): 91.5% Vehicle 24 Hour Turn Rate: 62.5% Average Age of Fleet: 15.2 years Total GO/GFVGR Vehicle Equivalents: 264.9 Total Cannibalizations: 3
Appendix A-3-4 Workload Estimate for WBS 1.3.4 Support - Transportation Services
Management of Vehicle Fleet Workload Quantity Frequency
Number of vehicles processed for shipment year: 1 Year
Vehicles Processed for depot repair 1 Year
Number of vehicles processed into the fleet per year: 2 Year
Number of vehicles processed for disposal per year: 2 Year
Number of accidents 5 Year
Perform Acceptance LTI to process vehicle into fleet 2 Year
Perform Shipment LTI to process vehicle for shipment or depot repair
2 Year
Perform Disposition LTI to process vehicle for disposition 2 Year
One-Time Repair Limit LTIs: 2 Year
Appendix A‐4 Historical Cost Data
HISTORICAL CE SUSTAINMENT COST DATA SUMMARY
DATE
VENDOR
ITEM/SERVICE
END ITEM
PRICE
Nov‐16
HOME DEPOT
MATERIAL
YELLOW PAINT FOR B‐776 ASP LINES
$ 21.97
QUICKSCREWS.COM
PLATED SCREWS TO INSTALL CABINETS
AT FIRE DEPT BLDG 43
$ 57.66
Nov‐16 MULBERRY MOTOR MATERIAL BATTERY FOR GENERATOR AT B‐53 $ 90.98
IRRAGATION REPAIR PARTS FOR BLDG
$ 35.74
PAINT AND PRIMER FOR DOORS AT
BLDG 236 & BLDG 29
$ 37.98
Nov‐16 SOUTHER SIGNS MATERIAL AIRFIELD SIGN REPLACEMENTS $ 70.00
Nov‐16 LOWES MATERIAL FAUCET REPAIR KIT FOR BLDG 43 $ 41.97
Nov‐16 CITY ELECTRIC MATERIAL FLOOD LIGHTS FOR BASE WIDE USE $ 139.90
Nov‐16 HOME DEPOT MATERIAL PVC CEMENT FOR CE USE ON BLDG 28 $ 7.20
FL IRRIGATION
IRRIGATION VALVES FOR REPAIR AT
BLDG 236
$ 223.00
PVC CEMENT FOR CE USE ON BLDG 28
$ 7.20
VALVE TO INTALL WATER COOLER AT
BLDG 29
$ 8.98
LOWES
HANDLES FOR ROLL UP DOOR AT
SUPPLY WINDOW BLDG 28
$ 7.34
Nov‐16 BAGWELL LUMBER MATERIAL PLYWOOD TO REPLACE FLOOR AT OP1 $ 234.50
ELETRICAL WHOLESALERS
BATTERIES FOR FIRE ALARM AT BLDG
$ 470.00
Dec‐16
ELECTRICAL
WHOLESALERS
MATERIAL
LIQUID TITE FOR CE STOCK USED BASE
WIDE
$ 48.89
WHOLESALERS
MATERIAL
EMERGENCY LIGHT REPLACEMENT FOR
FIRE DEPT
$ 322.00
Dec‐16 AMAZON.COM MATERIAL WATER COOLER FOR BLDG 475 $ 495.79
BAGWELL LUMBER
REPLACEMENT DOOR FOR
MECHANICAL ROOM AT BLDG 424
$ 1,108.45
ATLANTIC CULVERT CO
INC
MATERIAL
CULVERT REPLACEMENT FOR FROST
PROOF ROAD
$ 2,950.00
Dec‐16 INTERLIGHT.BIZ MATERIAL AIRFIELD LIGHTS FOR CE STOCK $ 313.32
SPRAYER AND BLEACH FOR PRESSURE
WASHING AT BLDG 28 AND 236
$ 18.94
REPAIR KIT FOR LEAKING TOILET AT
BLDG 447
$ 13.96
WINDTEK INC
AIRFIELD WINDSOCK REPLACEMENTS
FOR CE STOCK
$ 525.85
CABLETIESANDMORE.CO
M
MATERIAL
CABLE TIES FOR WINDSOCK
REPLACEMENTS
$ 25.09
Dec‐16 INTERLIGHT.BIZ MATERIAL AIRFIELD LIGHTS FOR CE STOCK $ 161.91
ULTIMATE WASHER
WALL MOUNT ELECTRIC PRESSURE
WASHER TO REPAIR WASH RACK
$ 2,856.80
CITY ELECTRIC
TOGGLE BOLTS FOR LIGHT FIXTURES AT
BLDG 77
$ 17.97
SHERWIN‐WILLIAMS
PAINT TO REPAINT FOR BLDG 28 RM
$ 54.50
FOAM SEALANT FOR BARRIER SHEDS
ROOF
$ 15.36
Jan‐17
1000BULBS.COM
PHOTO CONTROL FOR CE BASE USE
STOCK
$ 118.68
SEA COAST FIRE
REPLACEMENT PARTS NEEDED FOR
RANGE HOODS AT B‐236
$ 184.40
Jan‐17 FLORIDA COOLING MATERIAL COIL CLEANER FOR AC PMI'S $ 35.58
WHOLESALERS
MATERIAL
EMERGENCY LIGHTS FOR CE STOCK
BASE WIDE
$ 105.00
BATTERIES FOR EMERGENCY LIGHTS
USE BASE WIDE
$ 45.05
AMAZON.COM
CONCRETE JOINT SEALANT FOR POLY
PADS ON RUNWAY
$ 184.48
BOLT AND MOUNTING KIT TO INSTALL
SADLE ANTENNA ON B‐41
$ 48.16
PUMPCATALOG.COM
ARO PUMP ‐ INSTALLED WAST OIL
PUMP REPLACEMENT
$ 752.30
WEBOOST.COM
LIGHTNING SURGE PROTECTOR FOR
WIRELESS BOOSTER AT BLDG 29
$ 116.95
WHOLESALERS
MATERIAL
HARDWARE TO INSTALL SURGE
PROTECTION FROM LPS SURVEY
$ 70.28
Feb‐17
ULTIMATE WASHER
WALL MOUNT ELECTRIC PRESSURE
WASHER TO REPAIR WASH RACK
$ 351.70
GRAINGER.COM
NON DRIP NOZZLES FOR OIL
DISPENSING SYSTEM
$ 312.84
CABLE ADAPTER COUPLER TIES FOR
SADLE ANTENNA INSTALL AT B‐41
$ 43.80
SHOWMECABLES.COM
F‐TYPE ADAPTER FOR SADLE ANTENNA
INXTALL AT B‐41
$ 15.37
PALMER ELECTRIC/ACE
HARDWARE
TOILET WAX RING W/BOLTS FOR BLDG
$ 29.96
Feb‐17 HOME DEPOT MATERIAL FLANGE REPAIR KIT FOR BLDG 24 $ 17.98
SOMERS IRRIGARION
DWV PLAIN END PIPE FOR B‐44 SEPTIC
REPAIR
$ 38.40
PVCFITTINGSONLINE.CO
M
MATERIAL
COUPLING AND ADAPTER W/PLUG FOR
B44 SEPTIC REPAIR
$ 50.30
GLASS TO REPAIR WINDOW AT BLDG
236 CHOW HALL
$ 13.99
SUPERIOR HARDWARE
PROCUCTS
MATERIAL
LOCKS AND KEYPAD REPLACEMENTS
FOR BLDG 41 & 43
$ 1,455.34
PULL ELBOW TO REPAIR LIGHTS AT
BLDG 26
$ 10.61
LIGHT BULBS FOR ENTRANCE LIGHTS AT
BLED 29
$ 87.68
ZORO.COM
RED MARKING FLAGS FOR BASEWIDE
USE
$ 34.10
FAUCET REPAIR KIT FOR FOR BASEWIDE
$ 36.25
PROVANTAGE.COM
CABLE ADAPTER AND SPLITTERS FOR
SADL KEYBOARD, MOUSE, MONITOR
SETUP
$ 43.02
ALUMINUN THRESHOLD REPLACEMENT
FOR BLDG 41
$ 9.99
Mar‐17 LA ORNAMENTAL MATERIAL GATE 3 PARTS TO REPAIR OPENER $ 438.16
Mar‐17 DIGIKEY.COM MATERIAL CIRCUIT BOARD POWER CONNECTORS $ 11.63
Mar‐17
SIGNSDIRECT.COM
HAZARD MARKER REPLACEMENT FOR
LITTLE BRIDGE
$ 42.35
GLOBALINDUSTIRAL.COM
BARRIER REFLECTOR REPLACEMENTS
FOR ALL BRIDGES
$ 212.50
Mar‐17 HOME DEPOT MATERIAL PAINT FOR DOORS AT BLDG 424 $ 75.96
FLEXIBLE COUPLER FOR REPAIR BEHIND
B‐44 BATHROOMS
$15.32
Mar‐17 LA ORNAMENTAL MATERIAL GATE 3 PARTS TO REPAIR OPENER $23.60
SHOWMECABLES.COM
ADAPTER AND CONNECTORS FOR
WIRELESS BOOSTER AT BLDG 29
$17.04
FIRE EXTINGUISHER COVERS FOR BLDG
46 & 1058
$29.42
CAULK AND SILICONE SEALANT FOR
BASE WIDE USE
$47.79
LUMBER REPLACEMENT FOR
WILLINGHAM BRIDGE 1091
$60.00
Mar‐17 ZORO.COM MATERIAL DC POWER SUPPLY FOR BLDG 41 $131.71
FLORIDA COOLING
DIGITAL LARGE THERMOSTAT FOR
$48.12
PASSAGE LEVER/LOCK FOR BLDG 101
$13.97
Mar‐17 LA ORNAMENTAL MATERIAL CONTROL BOARD FOR GATE 3 $401.38
ALLDATARESOURCE.COM
ALARM MOTION DETECTOR FOR ASP‐
$679.05
WHOLESALERS
MATERIAL
SURGE PROTECTION PARTS FOR BASE
WIDE USE PER URS SURVEY
$515.76
Mar‐17 HOME DEPOT MATERIAL TOILET REPLACEMENT FOR BLDG 24 $149.00
PASSAGE LEVER/LOCK FOR BLDG 101
$27.94
HEATER HOSE TO REPAIR PRESSURE
WASHER
$16.99
HOSE FITTING FOR PRESSURE WASHER
REPAIR
$40.75
Mar‐17 MULBERRY MOTOR MATERIAL FILTER FOR DS2 DISPENSING PUMP $13.21
Mar‐17 GLOBALINDUSTIRAL.COM MATERIAL TOILET REPLACEMENT FOR BLDG 29 $159.95
ON‐SITE POWER
SERVICES
MATERIAL
CONTROLLER TO REPAIR GENERATOR
AT BLDG 41
$1,150.00
BUTWELL STONE AND
SOIL INC
MATERIAL
RIVER ROCK TO REPLACE MULCH AT
$600.00
SIGNSDIRECT.COM
HAZARD MARKERS FOR BASE WIDE
CULVERTS
$238.48
Apr‐17
SHERWIN WILLIAMS
PAINT TO REPAINT FOR BLDG 28 RM
$29.47
GLOBALINDUSTIRAL.COM
TOILET REPLACEMENT FOR BLDG 29
MEN'S ROOM
$159.95
LAMP/BULB REPLACEMENTS FOR
PARKING LOT AT BLDG 28
$97.50
CABLE SPLICE FOR GENERATOR LOAD
BANK TEST
$53.79
WHOLESALERS
MATERIAL
PLASTIC SOLUTIONS TO REPAIR HALL
LIGHT AT BLDG 238
$92.00
WHOLESALERS
MATERIAL
LAMPS AND PHOTOCONTROLS FOR CE
SUPPLY USED BASE WIDE
$130.28
WHOLESALERS
MATERIAL
RECEPTACLE PLATE REPLACEMENTS
FOR BLDG 68
$3.39
WHOLESALERS
DIFFUSER FOR FIRE DEPT VEHICLE BAY
$105.00
GROUT TO REPAIR TOILET B‐29 MENS
ROOM
$9.42
PARTSFORTECHS.COM
VOLTAGE REGULATOR FOR GENERATOR
AT BLDG 236
$139.59
WHOLESALERS
MATERIAL
12V 7AH BATTERIES FOR CE USED BASE
$460.00
Apr‐17 HOME DEPOT MATERIAL BAR OIL FOR CE BASE WIDE USE $23.98
AIRDELIGHTS.COM
FLUSHOMETERS USED ON TOILETS AND
URINALS FOR CE BASE WIDE USE
$112.90
EMERGENCYLIGHTING.C
OM
MATERIAL
BATTERY REPLACEMENTS FOR EXIT
LIGHTS AT BLDG 29
$65.03
TILE ADHESIVE AND GROUT FOR B424
LADIES ROOM REPAIRS
$27.84
May‐17
PKSUPPLIES.COM
SILICONE CONCRETE JOINT FOR POLY
PAD ‐ RUNWAY
$1,736.60
PUTTY & FAUCET SUPPLY LINE ROR
REPAIRS AT B‐424 AND B‐439
$69.08
May‐17 HOME DEPOT MATERIAL TOILET SEATS FOR USE BASE WIDE $71.94
WASHERS TO REPAIR URINAL IN MENS
ROOM BLDG 424
$12.48
VALVE TO REPAIR FAUCET B‐600 BACK
PORCH
$8.76
HOMEDEPOT.COM
FAUCETS REPLACEMENTS FOR BLDG
424 AND BLDG 439
$423.10
WHOLESALERS
MATERIAL
SURGE PROTECTORS FOR GATE
OPENERS
$307.52
FAUCETS REPLACEMENTS FOR BLDG
424 AND BLDG 439
$253.86
May‐17 HOMEDEPOT.COM MATERIAL FAUCET FOR BACK PORCH SINK B‐600 $78.29
May‐17 ZORO.COM MATERIAL FAN MOTOR FOR B‐77 BAY AREA $268.23
May‐17 CITY ELECTRIC MATERIAL FUSE FOR B‐77 BAY AREA $230.20
AMERICANLOCKSETS.CO
M
MATERIAL
FLAT DROP BRACKET FOR DOOR
CLOSER AT BLDG 236
$19.23
May‐17 MYSAFETYSIGN.COM MATERIAL FIRE EXTINGUISHER ARROW SIGN $44.50
PATCHING COMPOUND POWDER FOR
DRYWALL REPAIR BLDG 28
$7.98
GREE A/C SYSTEM FOR BLDG 28 RM
$2,105.92
May‐17 MULBERRY MOTOR MATERIAL BATTERY FOR GENERATOR AT B‐236 $95.91
PARTS TO REPAIR SINK SRAINS AT BLDG
$46.70
CERAMIC TILE FOR BLDG 424 LADIES
ROOM REPAIR
$0.67
PLASTIC P‐TRAP FOR FAUCET REPAIR AT
BLDG 439 & 424
$9.12
TAILPIECE TUBE AND WASHERS FOR
FAUCET REPAIR AT BLDG 439 & 424
$28.44
FLAT SPLINE AND SCREEN TO REPAIR
BLDG 236 BACK PORCH
$68.91
HARDWARE TO REPAIR LEAK IN FILL
VALVE AT BLDG 25
$46.95
WHOLESALERS
MATERIAL
EMERGENCY LIGHT BATTERIES FOR
$87.00
PVC TAILPIECE EXTENSION AND SLIP
JOINT TO REPAIR SINK DRAINS AT B‐600
$6.99
GASKET AND SEALS FOR TOILET REPAIR
MENS ROOM BLDG 29
$32.88
SUSTAINABLESUPPLY.CO
M
MATERIAL
LIQUID SOAP DISPENSERS FOR BLDG 44
AND BLDG 28 MENS ROOM
$102.60
May‐17 THE BULB BIN MATERIAL CEILING FAN FOR BLDG 49 $127.00
WHOLESALERS
MATERIAL
WFI HOTSPOT RECEPTACLES FOR BLDG
$10.43
Jun‐17
PLUMBINGSUPPLY.COM
ABS CLEANOUT PLUG FOR BLDG 28
WOMEN BATHROOM
$20.58
Jun‐17 INTERLIGHT.BIZ MATERIAL AIRFIELD LIGHT FOR CE STOCK $319.80
SOMERS IRRIGARION
CULVERT PIPE FOR BASE WIDE
SUSTAINMENT WORK
$6,000.00
INDUSTRIAL MOTOR
SERVICE
MATERIAL
MOTOR FOR AIR COMPRESSOR AT
BLDG 28
$1,286.61
CONTACTORS TO REPAIR WALK‐IN
FREEZER AT B‐236
$63.90
KHINDUSTRIES.COM
CORD REELS FOR VEHICLE CHARGING
AT BLDG 43
$864.57
WHOLESALERS
MATERIAL
PARTS TO INSTALL CORD REELS AT
BLDG 43
$1,679.70
REPLACE KEYPAD ON EMERGENCY
PHONE AT FUEL STATION
$118.34
EXCAVATION POINT
BULLROCK FOR WASHOUTS AND
CULVERT ENDS BASE WIDE
$5,800.00
WHOLESALERS
MATERIAL
RELAY HEATER ELEMENT FOR AIR
COMPRESSOR AT BLDG 28
$70.00
REPUBLIC SERVICES
MONTHLY BASIC RECYCLE AND ROLL
OFF 07/01/17‐07/31/2017
$529.25
AFFOREABLEOPENERS.CO
M
MATERIAL
PLUG‐IN LOOP DETECTORS FOR CE
STOCK ‐ BASE USE
$412.88
GROUND RODS AND CLAMPS FOR CE
$104.93
PANEL BOARD LOCK KIT FOR CE STOCK ‐
BASE USE
$154.05
Jul‐17
MULBERRY MOTOR
BATTERY REPLACEMENT FOR BLDG
1058 GENERATOR
$95.91
DANGER‐SAFETY HARNESS SIGNS FOR