Performance Work Statement for Bldg 10427 Demo.pdf
PDF 850 KB Posted
- Attached to
- Demolition of Bldg 53 and Bldg 10427
- Solicitation number
- FA500020Q0033
About this file
This performance work statement outlines the requirements for the demolition of two buildings at Joint Base Elmendorf Richardson in Alaska. The contractor will be responsible for demolishing Building 10427 and Building 53, disposing of all debris, and restoring both sites according to specifications. Hazardous materials assessments and abatement are required before demolition begins. Utilities must be properly disconnected and terminated. The contractor will coordinate all utility work with the relevant base organizations. The statement provides detailed instructions on fencing, backfilling, seeding, stormwater protection and other site restoration requirements. The contractor must appoint a project manager and submit daily reports documenting work completed and inspections. The performance objective is to fully demolish both facilities and remove all materials in compliance with environmental regulations, with the government inspecting to ensure standards are met.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FXSB 11-1001
Demolition of Building 10427
PERFORMANCE WORK STATEMENT (PWS)
FOR
DEMOLITION OF BUILDING 10427
AT
JOINT BASE ELMENDORF-RICHARDSON, AK
15 Jan 2020
Solicitation # FA5000-20-Q-0033
PROJECT NUMBER: FXSB 11-1001
1.1 GENERAL REQUIREMENTS: Provide all labor, materials, and equipment, necessary to complete the work for the demolition, removal and disposal of the 3 story Concrete building in accordance with the PWS, and the attached specifications and drawings. The Contractor shall comply with all applicable Federal, State, and Local regulations. Please see attached drawings for approximate dimensions and locations. Contractors shall not rely on drawings and are responsible for field verifying all measurements and locations of utilities to be demolished prior to work start. Locates of utilities shall be done by the Contractor through the dig permit process. Information shown on government provided reference drawings may not be accurate and requires verification of dimensions/locations.
All utilities for this facility are owned by the government except for the natural gas which is owned by Enstar. The contractor will make arrangements with government inspector and Enstar for the proper disconnect and removal of utilities.
1.2 PROJECT LOCATION: All work under this project will be performed on Joint Base Elmendorf-Richardson (JBER), Alaska. This building is located at 10427 19th street on JBER Elmendorf.
1.3 PERFORMANCE WORK STATEMENT: This Performance Work Statement (PWS) is intended to outline the Contractor’s general work items. Incidental work may be required to accomplish the intent of the contract. It is the Contractor’s responsibility to ensure all incidental work required to complete the demolition, disposal and finish work is included in their proposal for all areas of work outlined by the Performance Work Statement.
1.3.1. Work areas include: Building 10427, including related items that may not be attached to the structure such as sewer lines back to the main, water service lines back to the mains, sidewalks, gas lines back to the main, electrical lines underground or overhead, landscaping, etc. All work indicated shall be accomplished for the original proposal price, including special work times required for utility outages, and repair of damages to the site, by the Contractor. The building is a concrete structure with a concrete foundation. The contractor will remove all portions of the building and not leave any structure in the ground. At the completion of the project the contractor will leave a level area that is top soiled and seeded.
1.3.2. Provide a complete hazardous materials and hazardous waste survey for building 10427 including testing, test reports and identification of all hazardous containing materials and lead containing materials that exist. This structure is anticipated to have asbestos material used in its construction such as 9x9 floor tiles and possible pipe insulation remaining. This should not alleviate the contractor from sampling any material that they believe contains asbestos. A complete survey shall be submitted no later than 30 days prior to beginning of any work.
Hazardous materials and hazardous waste that may be expected to be encountered by the Contractor include: asbestos, lead including lead based paint (LBP), glycol, light bulbs, ballasts, thermostats and PCB’s. Other hazardous waste and hazardous materials containers may be encountered as determined through the required hazardous waste testing performed by the Contractor.
The contractor is required to attend a site visit prior to submitting a proposal and determine as much hazardous material as possible which will be included in the bid.
1.3.3. Fencing: Provide temporary fence for security around the demolition site prior to beginning abatement, and maintain through project completion. Temporary fence s h a l l be chain link, minimum 6’- 0” high, and shall be continuous and secure around site, free from gaps or breaks. Appropriate signage shall be conspicuously posted on fence, around construction site, including but not limited to Danger – Keep Out!
1.3.4. After all hazardous materials (if any) are removed by the Contractor. The contractor will compiled a list to indicate the quantities of materials removed and supply the information to the 673 CES/CEANV office. Contractor shall abide by all Environmental Provisions.
1.3.5. Remove and properly dispose of all hazardous materials and hazardous waste, including but not limited to, asbestos and lead-containing materials, light bulbs, ballasts, glycol, thermostats and other reportable materials in accordance with the attached Environmental Provisions and local, state, and federal regulations. Salvage, reuse, or recycle metals (i.e., conduit, piping, wiring, etc.) to the greatest extent possible.
1.3.6. Building demolition limits extend to 75 feet around perimeter of building or to the main utility lines if required.
1.3.7. Completely remove slab on grade, foundation, foundation supports, foundation walls and utilities within the construction site. Termination of utilities shall be as outlined in section 1.4.
1.3.8. Disposal of all solid waste shall be off base.
1.3.9. Disposal of asphalt and clean concrete will be on JBER at the main gravel pit located near the east end of the 06/24 runway off Richardson drive. Coordinate with the project inspector for proper disposal location of asphalt and clean concrete.
1.3.10. Backfill material will be made available to the contractor from the main gravel location off of Richardson drive. The exact location of borrow material will be determined at the time of need. The contractor will be responsible for loading and excavation of pit material. There is no processed material available at the pit for use by this contract.
Any processed material needed by the contractor will be purchased off installation and hauled on by the contractor at his expense. Top soil is not available on base and will be purchased and hauled by the contractor.
1.3.11. Building has an existing parking lot which will remain. The sidewalks that directly access the building will be removed back to the main public sidewalks. Parking lot and sidewalks to remain will be protected to the maximum extent possible. Contractor will take care not to damage existing parking lot/sidewalks, any damage will be repaired by the contractor at no additional cost.
1.3.12. Any grassed area disturbed by demolition activity will be left level and seeded. Provide approved seed, or hydro-seed, lawn material over all areas not getting asphalt or concrete. Install top soil & hydro seed for all grass areas disturbed and sidewalks, drives & utilities that have been removed. Fill top 6" with topsoil compacted to 85% of maximum density and prepare surface for seeding.
1.3.13. Work shall be performed in such a way as required to protect storm water runoff from pollution (erosion, sediment, or waste) entering waterways in compliance with all Federal, State and local regulations. Completed work in areas where site is to be left natural, (no pavements), shall be revegetated in accordance with the best management practices of the Clean Water Act and shall encourage groundwater infiltration.
1.4 UTILITIES WORK: The Contractor shall provide a work schedule for the disconnection and demolition of utilities for approval by the Contracting Officer. Contractor shall submit details; including sketches, materials to be used, and descriptions of the termination work for all utilities terminations for approval by the Contracting Officer prior to performing the work. Contractor will provide a work start notice prior to any work start and shall provide a minimum 3 weeks’ notice for approval for any work that will require a shutdown of utilities affecting other facilities. “JBER-Elmendorf domestic water/fire suppression services, electrical services, sanitary sewer collection services are owned and operated by 773 CES. Ownership of natural gas services is Enstar Gas Company. Demolition contractor will coordinate disconnect and removal of utilities from site with 773 CES and Enstar prior to start of any demolition activities.” The Contractor’s responsibilities related to existing utilities include the following:
1.4.1 Water: Where water service connects directly to a water main, Contractor shall disconnect from the main, and valve and repair coupling shall be placed on main.
The service pipe shall be abandoned in place. Where water service connects to a manhole, Contractor shall plug the service line at the manhole with a proper water plug for the service line type and size, provided no other service lines from other buildings are connected to the same service line.
1.4.2 Sewer: Where Sewer lateral drops into main. Main will have to be repaired after removal of lateral. Because of the age of this pipe the contractor may need to replace a section and not just plug the pipe. The lateral will be abandoned in place. Where sewer service connects to a manhole, Contractor shall plug the service line at the manhole with a proper sewer plug for the service line type and size, provided no other service lines from other buildings are connected to the same service line.
1.4.3 Electrical: The Contractor shall be responsible for coordinating use of on-site power with the 773d CES exterior electric shop through the project inspector and shall provide any temporary electrical connection components required, or shall provide their own independent power prior to beginning the abatement phase of the work. The Contractor shall notify the Contracting Officer 14 days prior to beginning work on building 10427. All interior electrical equipment within the building limits shall be the property of the Contractor to salvage or dispose of as required.
Final termination shall be coordinated with the government and shall be made at the transformer serving the building by the 773d Exterior electric shop. Additionally, the contractor will remove the meter base/disconnect, remove electrical conductors, plug open end of conduit at electrical vault and at open end at demo excavation limits. Abandoned in place conduit needs to be tracked in GIS.
1.4.4 Communications: The Contractor shall be responsible for notifying the 673rd Communications Squadron (673 CS), Maintenance Support, minimum 10 business days prior to beginning any communications demolition. Contractor shall be responsible for complying with Attachment #6, JBER Telecommunications Installation Standards, applicable to the termination. Contractor shall be responsible for providing a six (6) inch pre- formed stainless steel splice case. Final termination shall be made within the area shown on the contract drawings at the location determined by 673 CS. Communication conduit shall be removed back to vault/manhole and capped and sealed at exterior of vault/manhole. Communication cables to be removed and recapture splicing cables back to supply case at vault/manhole. Upon completion of splicing any communication, or data cables, the Contractor shall backfill the dig area in preparation for asphalt.
1.4.5 Natural Gas: Disconnect service lateral at main. Disconnect assumed to within building 10427, and properly remove and dispose of any hazardous material and hazardous waste from any equipment prior to disposal.
1.4.8. Fire Alarm Panel: The contractor shall notify the 773 alarm shop prior to demolition to give shop personnel an opportunity to remove the Fire Alarm Panel and antenna mast from the building prior to demolition.
1.5 ENVIRONMENTAL COORDINATION: All work shall be performed in accordance with the JBER Environmental Requirements.
1.5.1 Hazardous materials/ hazardous waste abatement: Hazardous materials and hazardous waste that should be expected to be encountered and removed by the Contractor include: Asbestos (ACM), lead including lead based paint (LBP), glycol, light bulbs, ballasts, and PCB’s. Other hazardous waste and hazardous materials containers may be encountered as determined through the required hazardous waste testing performed by the Contractor. All required sampling, testing, documentation and disposal shall be by the Contractor as a part of the resulting be performed by Enstar for the distribution system. The Demo contractor must coordinate this disconnect with Enstar. The service line will be abandoned in place. Abandoned in place line will be tracked in governments GIS information.
The contractor will ensure that this information is transferred to the government for inclusion. All costs for termination work shall be the responsible of the contractor.
1.4.7. Mechanical: The Contractor shall remove and dispose of all mechanical equipment
AT&T and GCI communications. The contractor will verify that these utilities are contacted and if part of the building demolition will remove as required by those utility agencies.
1.4.6. Other utilities: other utilities that may be part of this contract could include contract work.
1.5.2 Contractor is responsible for abatement of all hazardous materials and hazardous waste from the facilities identified for demolition. Competent Persons shall perform all abatement. The Competent Persons shall be trained, knowledgeable, and qualified in the techniques of abatement, handling and disposal of hazardous materials and the subsequent cleaning of contaminated areas. The Contractor and his personnel shall comply with all applicable Federal, State and Local regulations to perform the work of this contract.
1.6 CONTRACTOR PROJECT MANAGERS: The Contractor shall appoint a project manager to serve as the single point-of-contact and liaison between the Contractor and the Contracting Officer or his representative for all work under the contract. Upon receipt of the Notice to Proceed (NTP), the Contractor shall immediately provide the name of the designated individual and contact information to the Contracting Officer, in writing. The Project Manager will be responsible for the complete coordination of all work under the contract.
1.6.1 Daily Reports: All Contractor daily inspections and tests will be reported on a contractor-approved form. The Contractor's verification must be contained in the Contractor's report. When completed by the quality control inspector or contractor project manager, this report must contain sufficient information and details to provide complete documentation of all daily work, inspections and tests. These reports, including a record of deficiencies and corrective action taken, should be submitted to the Government daily no later than 1200 hours the first working day following the date which the report covers.
1.7 SERVICES SUMMARY (SS):
Performance Objective
Performance Threshold
Method of Surveillance Deficiency Resolution
SS 1:
Demolish Facility
Facility demolished All materials removed from the site in compliance (100%) with the PWS and applicable environmental laws and regulations
Government inspection (100%)
Contractor re-performance and payment of Contractor caused fines
SS 2:
Remove debris off deconstruction site
All material removed from the site of the existing facility and waste disposed of properly
Government inspection (100%)
Contractor re-performance and payment of Contractor caused fines
SS 3:
Inventory debris
Furnish the government with an accurate inventory of debris to include type, volume, and location
Government inspection (100%)
Contractor re-performance
SS 4:
Restore site
Perform all site restoration work as described in the PWS
Government inspection (100%)
Contractor re-performance
PWS Attachments:
Attachment #1: Project Asbuilt Drawings Attachment #2: Existing Condition Pictures Attachment #3: AF66
-END OF SECTION-