Bid Schedule Design & Construct New Braking Pads - GRCA
RFP# P15PS01139
| Item # |
| Description |
| Quantity |
| Unit |
| Unit Total Cost |
| 1 |
| Hermit Road Interchange (does not include Option A) |
| 1 |
| LS |
| $ |
| 2 |
| Hermit Interchange (Option A) |
| 1 |
| LS |
| $ |
| 3 |
| Trail View Shuttle Stop (Option B) |
| 1 |
| LS |
| $ |
| 4 |
| Maricopa Point Shuttle Stop |
| 1 |
| LS |
| $ |
| 5 |
| Powell Point Shuttle Stop (does not include Option C) |
| 1 |
| LS |
| $ |
| 6 |
| Powell Point (Option C) |
| 1 |
| LS |
| $ |
| 7 |
| Hopi Point Shuttle Stop |
| 1 |
| LS |
| $ |
| 8 |
| Mohave Point Shuttle Stop (Option D) |
| 1 |
| LS |
| $ |
| 9 |
| The Abyss Shuttle Stop |
| 1 |
| LS |
| $ |
| 10 |
| Monument Creek Vista Shuttle Stop |
| 1 |
| LS |
| $ |
| 11 |
| Pima Point Shuttle Stop |
| 1 |
| LS |
| $ |
| 12 |
| Hermits Rest (Option E) |
| 1 |
| LS |
| $ |
| 13 |
| South Entrance Station: Lanes 2, 3, and 4 |
| 1 |
| LS |
| $ |
| 14 |
| Hermit Road Striping (Option F) |
| 1 |
| LS |
| $ |
| 15 |
| South Entrance Station Conc. Walk Improvements (Option G) |
*** Individual line item total costs must include any / all pricing elements, and must be the complete designed and installed cost for the particular braking pad ***