Text version

NNK16571085R – Combined Synopsis/Solicitation Questions and Answers

Amendment 03

Question #7: “Is the table supposed to have a formula that adds up all of the option periods and gives a sum of services, as for this task it gives an inaccurate value/total for what we would actually charge in order to do the project.”

Answer #7: The tables are formulated to calculate the sum of all five contract periods (Base Period through Option Period 04) for evaluation purposes only. The proposed price for all five BPA periods need to be evaluated; therefore, the sum of all five periods is used in the total evaluated price. The

Government understands that the total evaluated price is not the total price that an offeror would propose for the sample task.

File details come from the government source that posted it. Updated .