Attachment 2 - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Remove and Replace B4820 125KVA Uninterruptable Power Supply, newest first.
File Type Posted
Q A-2.pdf PDF
Amendment_05.pdf PDF
Q A-1.pdf PDF
Amendment_04.pdf PDF
Revised_SOW_R2.pdf PDF
Revised_SOW.pdf PDF
Questions_and_Answers.pdf PDF
Amendment_03.pdf PDF
Amendment_02.pdf PDF
SF1442.pdf PDF
Site_Visit_Presentation.pptx PPTX presentation
Amendment_01.pdf PDF
Sign-in_Sheet.pdf PDF
Attachment_4_-_General_Decision_Number_CA160031.pdf PDF
NND16571098E_Solicitation_Document.pdf PDF
Attachment_5_-_AFRC_form_10735 _Visit_Request_-_U.S._Citizens.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_3_-_Floor_Plan_and_Pictures.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

01/08

PART 1 GENERAL

1.1 SUMMARY

The work to be performed under this project consists of providing the labor, equipment, and materials to perform the removal and replacement of the B4820

125KVA Uninterruptable Power Supply (UPS) for the National Aeronautics and

Space Administration at the Armstrong Flight Research Center (NASA/AFRC), Edwards, California 93523.

a. The electrical scope includes the removal of the existing failing 125

KVA Uninterruptable Power Supply (UPS) and replace with new 125 KVA

UPS. NOTE: The existing UPS shall remain in place until the new UPS has been delivered on site.

1.2 CONSTRUCTION SCHEDULE AND PERIOD OF PERFORMANCE

Within the contract period of performance of 120 days, the Contractor shall commence and complete the work including all required submittals.

Task Calendar Days

NTP-Mobilize Site 21

Construction (No Phases) 99

Total 120

1.3 WORK HOURS

All Construction work under this contract shall be performed during normal duty hours from 6:00 a.m. to 5:30 p.m. Weekends and Government holidays are restricted for work unless otherwise directed by Contracting Officer.

The Contractor shall allow for a maximum of ten (10) days per year where construction activity is not permitted because NASA facilities are closed.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

Section 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

07/07

1.1 SUBMITTALS

The following shall be submitted in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Contact List of Key Personnel; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Contractor personnel employed on the Activity shall become familiar with and obey Activity regulations including safety, fire, traffic and security regulations according to Section 01 35 14.11 40 "AFRC Safety Requirements."

Contractor personnel shall keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (Peak traffic hours are 6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting

Officer. Contractor personnel shall not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.2.1.1 MATERIAL AND EQUIPMENT

Shipments shall be addressed to the Contractor who shall be responsible for their receipt, unloading, handling, and storage at the site. The Government will not accept deliveries on behalf of the Contractor or Subcontractors or assume responsibility for security of materials, equipment, or supplies delivered to the site. The Contractor shall not have any material or equipment deliveries made to the AFRC shipping and receiving warehouse. The

Contractor shall use the following address:

Name of Contractor's firm or company

P.O.C. (Name of Contractor's superintendent or other employee)

Repair B4820 UPS System

NASA Armstrong Flight Research Center

Edwards, CA 93524

The Contractor shall protect and preserve materials, supplies, and equipment of every description, including property which may be Government-furnished or

Government-owned. Material to be salvaged and reinstalled by the Contractor shall be protected during removal and stored to prevent damage. Only material and construction equipment designated for performance of contract work may be stored at the construction site or located in Government-controlled areas.

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2033%2000.doc ../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2035%2014.11%2040.doc

Section 01 14 00 Page 2

Materials and equipment to be provided under this contract shall be standard catalogue products of manufacturers regularly engaged in the manufacture of the products. Material and equipment shall be installed in accordance with the requirements of the contract drawings and approved recommendations of the manufacturers.

1.2.1.2 Subcontractors and Personnel Contacts

Contractor shall furnish a contact list of key personnel including e-mail addresses and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.3 Identification Badges

Identification badges will be furnished without charge. Application for and use of badges will be as directed. Contractor shall submit for approval on

NASA Form DFRC-735 or DFRC-736, at least 15 days prior to the desired date of entry, a list of personnel who require entry into Government property to perform work on the project. Furnish a completed EMPLOYMENT ELIGIBILITY

VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/sites/default/files/files/form/i-

9.pdf. Immediately report instances of lost or stolen badges to the

Contracting Officer.

1.2.1.4 Personnel Entry Approval

Failure to obtain entry approval will not affect the contract price or time of completion.

1.2.1.5 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installations under the cognizance of NASA except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The

Contracting Officer will identify designated smoking areas.

1.2.2 NORMAL DUTY HOURS

Normal duty hours are from 6:00 am to 5:30 pm Monday through Friday the first week, and then from 6:00 am to 5:30 pm Monday through Thursday the second week, excluding federal holidays. Armstrong Flight Research Center is currently operating under this flexible work schedule, permitting employees to work 80 hours in 9 days (known as a 9/80 schedule) and have a nonwork day every other Friday. The Center is closed every other Friday. The contractor's work shifts shall take place as described in Section 01 11 00, except as requested and approved per paragraph "Work Outside Normal Duty

Hours" below.

1.2.2.1 Work Outside Normal Duty Hours

Work outside normal duty hours requires Contracting Officer approval. Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2011%2000.doc

Section 01 14 00 Page 3 number and project title. Based on the justification provided, the

Contracting Officer may approve work outside normal duty hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

1.2.3 OCCUPANCY OF PREMISES DURING CONSTRUCTION

The buildings will be occupied during performance of work under this

Contract. Before work is started, the Contractor shall arrange with the

Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. Government personnel will be allowed in the construction area to perform routine or emergency maintenance on building systems and equipment.

This includes communication, electrical, mechanical, and fire protection systems.

1.3 ENVIRONMENTAL CONSIDERATIONS

[The Edwards AFB property, which NASA shares, is on the National Priorities

List (NPL, or Superfund) due to known areas of soil and groundwater contamination. Known contamination in soil has been cleaned up, and known contamination in shallow groundwater is under treatment but not yet cleaned

up. ]The Contractor shall be aware that all intrusive activities that require a dig permit (greater than 6" deep) may also require vapor monitoring and use of Personal Protective Equipment (PPE) when work is occurring within these areas, unless waived by the Contracting Officer.

Not Used

Section 01 20 00.00 20 Page 1

SECTION 01 20 00.00 20

PRICE AND PAYMENT PROCEDURES

02/10

Schedule of Values; G

SD-11 Closeout Submittals

Contractor's Invoice shall be submitted in accordance with Paragraph

"CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT"

1.2 SCHEDULE OF VALUES

1.2.1 Data Required

Within 15 calendar days after Notice of Award, the Contractor shall prepare and deliver to the Contracting Officer a schedule of values for approval.

The Schedule of Values shall consist of a detailed breakdown of each contract activity. The value of each activity shall be identified as a percentage of the total contract value, and shall correlate with the activities in the

Project Schedule.

Contracting Officer will determine whether items in the Schedule of Values are appropriate. Progress payments shall be based on the approved Schedule of Values.

1.2.2 Schedule Instructions

Payments will not be made until the Schedule of Values has been submitted to and accepted by the Contracting Officer.

1.3 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.3.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause

FAR 52.232-27. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. Requests for payment in accordance with the terms of the contract shall consist of:

a. The Contractor's invoice on the form furnished by the Contracting Officer for this purpose, shall show in summary form the basis for arriving at the amount of the invoice.

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2033%2000.doc

Section 01 20 00.00 20 Page 2

b. The contract performance statement on the form furnished by the

Contractor for this purpose and consistent with the approved Schedule of

Values, shall show in detail the estimated percentage of completion for each Definable Feature of Work (DFOW). The format, content, and number of copies required will be prescribed by the Contracting Officer and will be subject to his/her approval.

c. Furnish a certificate to the CO with each payment request attesting that the work for which payment is requested, including stored material, is in compliance with contract requirements.

d. The Estimate for Voucher, showing in detail the percentage of completion for each of the construction activities listed on the Schedule of Values.

e. Updated Project Schedule and any reports required by the contract.

g. Contractor Safety Self-Evaluation Checklist

h. Weekly Certified Payroll Report

i. Solid Waste Disposal Report

j. Other supporting documents as requested

k. For Final Payment: All closeout submittals must be received prior to final payment. A final invoice and the Contractor's Final Release is the

Contractor's request for final payment, including completed As-Built

Drawings. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary or official designee shall certify the Final

Release.

No separate payments will be made for protection efforts necessitated by the safety provisions.

1.4 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

Section 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

02/10

Electronic Mail (E-Mail) Address; G

View location map; G

Progress and completion pictures; G

1.2 VIEW LOCATION MAP

Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take regular digital photographs throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice one set of digital photographs on a CD-R, cumulative of all photos to date.

Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.

1.4 SUPERVISION

Provide at least one (1) qualified on-site Project Superintendent. The

Project Superintendent must have a minimum of 10 years' experience as a

Superintendent on projects similar in size and complexity.

In addition to the above experience requirements, the on-site Project

Superintendent shall complete the U.S. Army Corps of Engineers course entitled "Construction Quality Management for Contractors" prior to the start of construction.

The Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2033%2000.doc

Section 01 30 00 Page 2 failure to manage the project to ensure timely completion. Furthermore, the

Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.

Approval of on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed on-site Project

Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed on-site Project Superintendent at any time in order to verify the submitted qualifications.

1.5 PROJECT MEETINGS

1.5.1 Preconstruction Conference

The Contractor shall attend a preconstruction conference scheduled by the

Contracting Officer. Work shall not commence prior to the conference.

Discussion shall address project orientation, personnel contact, safety issues, permits, deficiencies, quality control and the location of the

Contractor's office.

1.5.2 Weekly Project Meetings

The Contractor shall attend weekly project meetings scheduled by the

Government. Discussion shall address at a minimum: safety issues, quality control, submittals, progress schedule, schedule of submittals, as-built drawings, deficiencies, material delivery, permits, equipment delivery, invoices, potential factors of delay, request for information (RFIs), changes, and functional tests.

1.6 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from NASA, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.7 INFORMAL PARTNERING

The Contractor will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session could be a part of the Pre-Construction

Meeting. Partnering sessions will be held at a location agreed to by the

Contracting Officer and the Contractor (typically a conference room provided by NASA or the Contractor).

Section 01 30 00 Page 3

The Partners will determine the frequency of the follow-on sessions.

1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft Office, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting

Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the

Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email addresses will NOT be allowed.

It is the Contractor's responsibility to make timely distribution of all

Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting

Officer, in writing, of any changes to this email address.

Section 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/08

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ECB 2005-10 (2005) Scheduling Requirements for Testing of

Mechanical Systems in Construction Contracts

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

Project Schedule; G

1.3 QUALIFICATIONS OF PROJECT SCHEDULER

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to the

Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of construction is the responsibility of the

Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule.

Provide a schedule that is a forward planning as well as a project monitoring tool.

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2033%2000.doc

Section 01 32 01.00 10 Page 2

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. The schedule shall be cost loaded and activity coded. The schedule will provide the basis for all progress payments. The project schedule shall be capable of showing percent complete for each activity.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If the

Contracting Officer determines that the Contractor has fallen behind the approved schedule, the Contracting Officer may require the Contractor to take steps necessary to improve its progress without additional cost to the

Government.

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project

Schedule shall be capable of meeting all requirements of this specification.

3.2.1 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting

Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.2.1.1 PROGRESS SCHEDULE REQUIREMENTS

The Contractor shall prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the major salient features of the work, including acquiring materials and equipment. The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. The Contractor shall:

a. Submit the progress chart in one reproducible format and three copies to the Contracting Officer for approval no later than 15 days after notice to proceed.

b. Prepare the progress chart in the form of a bar chart utilizing a form "Construction Progress Chart" or comparable format acceptable to the

c. Include no less than the following information on the progress chart:

1. Break out by major headings for each primary work activity.

2. A line item break-out under each major heading sufficient to track the progress of the work.

Section 01 32 01.00 10 Page 3

3. A line item showing contract finalization tasks which include punch list, clean-up, O&M data, and As-Built drawings. These activities are to show no associated costs.

4. The estimated percentage weight of total contract value for each line item on the chart. This shall be consistent with the Schedule

5. Separate line items for submittal preparation and reviews. These shall be consistent with the "Schedule of Submittals" required in

Section 01 45 00.10 40, "CONTRACTOR QUALITY CONTROL". Submittal preparation and reviews are to show no associated costs.

6. Separate line items for mobilization and demobilization.

d. Update the progress schedule in 3 copies every 30 days throughout the contract performance period. The updated schedule shall be submitted with the monthly payment request.

3.2.1.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have durations greater than

20 work days or 30 calendar days. Procurement activities are defined herein.

3.2.1.3 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.2.1.4 Mandatory Tasks

The following tasks must be included and properly scheduled if in scope:

b. Submission of mechanical/electrical/information systems layout drawings.

c. Submission and approval of O & M manuals.

d. Submission and approval of as-built drawings.

e. Submission and approval of NASA Form NF1046 "Transfer and/or

Notification of Acceptance of Accountability of Real Property" data.

f. Submission and approval of testing and air balance (TAB).

g. Submission of TAB specialist design review report.

h. Submission and approval of fire protection specialist.

i. Submission and approval of testing and balancing of HVAC plus commissioning plans and data. Develop the schedule logic associated with

../../AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/Word/01%2045%2000.10%2040.doc

Section 01 32 01.00 10 Page 4 testing and commissioning of mechanical systems to a level of detail consistent with ECB 2005-10.

j. Air and water balancing.

k. HVAC commissioning.

l. Controls testing plan submission.

m. Controls testing.

n. Performance Verification testing.

o. Other systems testing, if required.

p. Submission and approval of installed equipment lists.

q. Final inspection.

3.2.1.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed

(NTP) for phasing requirements.

3.2.2 Scheduled Project Completion and Activity Calendars

The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7-day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the

Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Note as Weather Sensitive

Installation those activities that are weather sensitive. Durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.

3.2.2.1 Project Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project" (or NTP) with a start date equal to the date that the NTP was acknowledged, and a zero day duration.

3.2.2.2 Schedule Constraints and Open Ended Logic

Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the

Section 01 32 01.00 10 Page 5 contract completion date. Include as the last activity in the project schedule an activity called "End Project" with an end date equal to the contract completion date for the project, and with a zero day duration. The schedule shall have no constrained dates other than those specified in the contract.

3.2.2.3 Early Project Completion

In the event the Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The

Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.

3.2.3 Milestones

The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for construction;

foundation/substructure construction complete; superstructure construction complete; building dry-in or enclosure complete to allow the initiation of finish activities; permanent power complete; and building systems commissioning complete.

3.3 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data Compact Disk (CD), reports, and schedules required for each submission are contained in paragraph SUBMISSION REQUIREMENTS.

3.3.1 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within 5 calendar days after

NTP. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Initial Schedule shall be at a reasonable level of detail as determined by the Contracting Officer.

3.3.2 Periodic Schedule Updates

Based on the result of the meeting, specified in PERIODIC SCHEDULE UPDATE

MEETINGS, submit periodic schedule updates. These submissions will enable the Contracting Officer to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgment of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.

3.4 SUBMISSION REQUIREMENTS

Submit the following items for the Initial Schedule and every Periodic

Schedule Update throughout the life of the project:

Section 01 32 01.00 10 Page 6

3.4.1 Data Delivery

Provide digital files containing the project schedule in the original scheduling software format, and PDF format. Each delivery shall also contain all previous update schedules. File medium shall be CD or other digital media approved by Contracting Officer. Label each CD indicating the type of schedule (Initial or Periodic Update), full contract number, Data Date and project title. Each schedule shall have a unique file name as determined by the Contractor.

3.4.2 Narrative Report

Provide a Narrative Report with the Initial and each Periodic Update of the project schedule, as the basis of the progress payment request. The

Narrative Report shall include: a description of activities along the 2 most critical paths where the total float is less than or equal to 20 work days, a description of current and anticipated problem areas or delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. The narrative report is expected to communicate to the Government, the Contractor's thorough analysis of the schedule output and its plans to compensate for any problems, either current or potential, which are revealed through that analysis. Identify and explain why any activities that, based on their planned dates, should have either started or finished during the update period but did not.

3.4.3 Approved Changes Verification

Include only those project schedule changes in the schedule submission that have been previously approved by the Contracting Officer. The Narrative

Report shall specifically reference, on an activity by activity basis, all changes made since the previous period and relate each change to documented, approved schedule changes.

3.4.4 Schedule Reports

The format, filtering, organizing and sorting for each schedule report shall be as directed by the Contracting Officer. Typically reports shall contain:

Activity Numbers, Activity Description, Original Duration, Remaining

Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish

Date, Total Float, Actual Start Date, Actual Finish Date, and Percent

Complete. The following lists typical reports that will be requested. One or all of these reports may be requested for each schedule submission.

3.4.4.1 Activity Report

A list of all activities sorted according to activity number.

3.4.4.2 Logic Report

A list of detailed predecessor and successor activities for every activity in ascending order by activity number.

3.4.4.3 Total Float Report

A list of all incomplete activities sorted in ascending order of total float.

List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

Section 01 32 01.00 10 Page 7

3.4.4.4 Earnings Report by Activity

A compilation of the Contractor's Total Earnings on the project from the NTP to the data date. This report shall reflect the earnings of specific activities based on the agreements made in the schedule update meeting defined herein. Provided that the Contractor has furnished a complete schedule update, this report shall serve as the basis of determining progress payments. Group activities by activity number. This report shall: sum all activities and provide a percent complete. The printed report shall contain, for each activity: the Activity Number, Activity Description, and Percent

Complete (based on total contract value).

3.4.5 Network Diagram

The network diagram is required for the Initial and Periodic Updates. The network diagram shall depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The

Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:

3.4.5.1 Continuous Flow

Diagrams shall show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated percent complete on the diagram.

3.4.5.2 Project Milestone Dates

Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.4.5.3 Critical Path

Clearly show the critical path.

3.4.5.4 Banding

Organize activities as directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by category of work, work area and/or responsibility.

3.5 PERIODIC SCHEDULE UPDATE MEETINGS

Conduct periodic schedule update meetings for the purposes of reviewing the

Contractor's proposed out of sequence corrections, determining causes for delay, correcting logic, maintaining schedule accuracy and determining percent complete. Meetings shall occur at least monthly within five days of the proposed schedule data date and after the Contractor has updated the schedule with Government concurrence respecting actual start dates, actual finish dates, remaining durations and percent complete for each activity it intends to status. Provide a computer with the scheduling software loaded and a projector during the meeting which allows all meeting participants to view the proposed schedule update during the meeting.

Section 01 32 01.00 10 Page 8

3.5.1 Update Submission Following Progress Meeting

Submit a complete update of the project schedule containing all approved progress, revisions, and adjustments, pursuant to paragraph SUBMISSION

REQUIREMENTS not later than 4 working days after the periodic schedule update meeting, reflecting only those changes made during the previous update

3.5.2 Status of Activities

Update information, including Actual Start Dates (AS), Actual Finish Dates

(AF), Remaining Durations (RD), and Percent Complete shall be subject to the approval of the Government prior to the meeting. As a minimum, address the following items on an activity by activity basis during each progress

3.5.2.1 Start and Finish Dates

Accurately show the status of the AS and/or AF dates for each activity currently in-progress or completed since the last update. The Government may allow an AF date to be assigned with the percent complete less than 100% to account for the value of work remaining but not restraining successor activities. Only assign AS dates when actual progress occurs on an activity.

3.5.2.2 Remaining Duration

Update the estimated RD for all incomplete activities independent of Percent

Complete. Remaining Durations may exceed the activity OD or may exceed the activity's prior update RD if the Government considers the current OD or RD to be understated based on current progress, insufficient work crews actually manning the job, unrealistic OD or deficiencies that must be corrected that restrain successor activities.

3.5.2.3 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete. To allow for proper schedule management, cost load the correction of punch list from Government final inspection not less than 1 percent of the total contract value, which activity(ies) may be declared 100 percent complete upon completion and correction of all punch list work identified during Government final inspection.

3.6 WEEKLY PROGRESS MEETINGS

a. Meet weekly with the Government (or as otherwise mutually agreed to) between the meetings described in paragraph PERIODIC SCHEDULE UPDATE

MEETINGS for the purpose of jointly reviewing the actual progress of the project as compared to the planned progress and to review planned activities for the upcoming two weeks. The then-current and approved schedule update shall be used for the purposes of this meeting and for the production and review of reports. The Contractor's Project Manager and the Authorized Representative of the Contracting Officer shall attend. The weekly progress meeting will address the status of RFI's, RFP's and Submittals.

Section 01 32 01.00 10 Page 9

b. Provide a bar chart showing Total Float and Sorted by Early Start

Date, with a two week "look-ahead" schedule by filtering all schedule activities to show only current ongoing activities and activities schedule to start during the upcoming two weeks, organized by responsible party and sorted by Early Start Date.

c. The Government and the Contractor shall jointly review the reports.

If it appears that activities on the longest path(s) which are currently driving the calculated completion date, are not progressing satisfactorily and therefore could jeopardize timely project completion, corrective action must be taken immediately.

3.7 OWNERSHIP OF FLOAT

Float available in the schedule, at any time, shall not be considered for the exclusive use of either the Government or the Contractor.

Section 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

06/10

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

Submittals which are required prior to the start of construction work on-site, such as:

List of proposed products

Construction Progress Schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of Values

Accident Prevention Plan

Activity Hazard Analysis for Mobilization

Quality Control (QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Section 01 33 00 Page 2

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or un-fabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with specified requirements.

Report which includes findings of a test required to be performed by the

Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or

Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

SD-08 Manufacturer's Instructions

Section 01 33 00 Page 3

Preprinted material describing installation of a product, system or material, including special notices and Safety Data Sheet (SDS) concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to operate and maintain equipment.

This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual, database, or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract.

For example, Record Drawings, warranty certificates, training records, asset / equipment list with cost breakdown, and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.1.2 Approving Authority

Office or designated person authorized to approve submittal.

1.1.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with this section.

Updated Submittal Register; G

Section 01 33 00 Page 4

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.3.1 Contractor QC Approved (Submittals without a "G" designation)

Contractor shall review all construction submittals for quality control.

When Government approval is not required, Contractor shall be held responsible for submittal approval and construction per contract documents.

1.3.2 Government Approved (Submittals with a "G" designation)

Government approval is required for critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer.

1.4 PREPARATION

1.4.1 Transmittal Form

Transmit each submittal, except sample installations and sample panels to the

Contracting Officer. Transmit submittals with transmittal form prescribed by

Contracting Officer and standard for project. On the transmittal form identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled, "Identifying Submittals," of this section.

1.4.2 Identifying Submittals

When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review, and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.

Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:

a. Project title and location.

b. Construction contract number.

c. Date of the drawings and revisions.

d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other subcontractor associated with the submittal.

e. Section number of the specification section and applicable drawing numbers by which submittal is required.

f. Submittal description (SD) number of each component of submittal.

g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.

Section 01 33 00 Page 5

1.4.2.1 Digital Submittals

In addition to providing the required quantity of hard copies of administrative, informational, material, O&M, and as-built drawing submittals, the contractor shall also include one electronic copy of each submittal. The electronic copy shall be in both an original editable file format (when created by the Contractor) and PDF format and submitted on non-rewritable optical media (CD or DVD) at the same time as the hard copy submittal. If material is copyrighted, written permission from the copyright holder for digital replication of O&M Manuals shall also be included. Red-lined as-built drawings shall be scanned to PDF in the same paper size as the original.

1.4.3 Format for SD-02 Shop Drawings

Shop drawings are not to be less than 8 1/2 by 11 inches nor more than 30 by

42 inches, except for full size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless other form is required. Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.

Present A4 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.

Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled, "Identifying Submittals," of this section.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the

Government contract number in the margin, immediately below the title block, for each drawing.

Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.

Include the nameplate data, size and capacity on drawings. Also include applicable federal, military, industry and technical society publication references.

1.4.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions

Present product data submittals for each section as a complete, bound volume.

Include table of contents, listing page and catalog item numbers for product data.

Indicate, by prominent notation, each product which is being submitted;

indicate specification section number and paragraph number to which it pertains.

Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.

Section 01 33 00 Page 6

Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates.

Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American

National Standards Institute (ANSI), ASTM International (ASTM), National

Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable…