About this file
This document provides details for a federal contract solicitation to perform asphalt seal coating work on the National Interagency Fire Center campus in Boise, Idaho. The work includes seal coating approximately 64,800 square yards of asphalt concrete across the campus and repainting all striping. The period of performance is 90 calendar days, and work must be conducted during regular office hours from 7:00 am to 4:30 pm Monday through Saturday, with exceptions possible for holidays. The site will remain occupied, and the contractor must coordinate work that disrupts parking lots or roadways with the Contracting Officer Representative at least one week in advance to ensure government vehicles can be moved. The contractor must provide a list of personnel to the COR before starting work and notify them of any changes one day in advance for security clearance. A staging area will be designated, and the contractor must supply portable toilet facilities. The pre-bid meeting date and time are provided in the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
BUREAU OF LAND MANAGEMENT
Fire and Aviation 3833 S Development Ave
Boise, Idaho 83705-5354
July 24, 2023
PROLOGUE
NIFC Campus Asphalt Seal Coat
Work effort includes seal coating all asphalt and painting all striping across campus, which is approximately 64,800 SY of asphalt concrete (AC). All other work is as shown within the contract documents. The work to be performed on the National Interagency Fire Center (NIFC) campus at 3833 S Development Ave Boise, ID 83705.
General information about the project is provided below.
1. Period of Performance: This project has a 90-calendar day period of performance, in which material application parameters within the specifications regarding temperature, etc. will be taken into consideration upon award.
2. Building Occupancy: All buildings across campus will be occupied during this construction project. Contractor shall coordinate with Contracting Officer Representative (COR) a minimum of one week ahead of any work that requires disruption of parking lots or roadways. Contractor will coordinate with COR to ensure government vehicles and equipment are moved.
3. Site Safety: Contractor shall provide all safety barriers required for contractor and occupant safety.
4. Security: NIFC is a secure campus site with a controlled security entrance.
a. Prior to commencing work, the contractor shall provide a list to the COR containing names for all contractor personnel who will work on the NIFC campus. Any changes to the list shall be provided to the COR a minimum of one day prior to arrival.
b. All contractors’ personnel shall present an official US Government or State Government issued photo identification at the security gate. ID’s will be compared to the contractor’s personnel list. Identification shall adhere to REAL ID standards upon effective date of federal requirement.
c. All the contractors’ personnel shall wear NIFC furnished visitor badges in a visible location at all times while on the campus and return the badge at the end of each day, or at the completion of the project. Badge turn-in is at the discretion of the NIFC Security Manager.
d. Contractor personnel shall not enter the site more than 30 minutes prior to the start of the scheduled workday and must leave the campus within 30 minutes of the scheduled workday completion.
5. Contractor Staging Area: A lay-down, staging, and contractor-provided portable toilet area will be designated for the project. The physical size of the area required will be coordinated with the government upon award. Contractor shall provide sanitary facilities during the construction period for their employees and subcontractors.
6. Work Hours: Construction work shall be conducted during regular office hours which are 7:00 am to 4:30 pm, Monday through Saturday (due to parking lot availability) with exceptions for holidays. Contractor requested work during holidays, early mornings, evenings, nights, and weekends will be considered by the government COR on a case-by-case basis.
7. Pre-Bid Construction Meeting: Refer to solicitation for date, time, & location of the pre-bid meeting.
--end---