This is a project specification document for the Nebraska Water Reclamation Facility (NE WRF) Influent Building Floor Repair project located in Florida. The scope of work encompasses the demolition of existing grating over channels in the influent headworks building through the splitter box and the installation of new grating to replace it. The contractor must provide all labor, materials, equipment, tools, services, and incidentals necessary to complete the work in full compliance with Contract Documents. All work must be completed in place and ready for continuous service, including any repairs, testing, permits, cleanup, replacements, and restoration required due to construction-related damages. The project has a construction timeline of 365 days and requires the contractor to comply with all applicable local, State, and Federal codes.
The contractor is responsible for furnishing all materials, equipment, skills, tools, and labor reasonably and properly necessary for substantial completion of the work without additional compensation, whether explicitly stated in the Contract Documents or not. No specific pricing terms, set-asides, or funding source information is detailed in this project specification document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL MEMORANDUM
To: Alyana Talaroc, E.I.
From: Michelle Widick, P.E.
Date: June 15, 2026
RE: NE WRF Influent Building Floor Repairs
A. Recommended Contract Time
The proposed repairs of the influent building floor generally consists of the following and has the approximate lead times as shown below after approval of shop drawings for construction/fabrication:
• FRP Grating – 2-3 months
• Access Hatches with Fall Protection – 3 months
• Aluminum Railing and Steel Framing – 3 months
Based on our discussion with the various vendors on the lead times for the above, the recommended
Contract Times are as follows:
• Notice to Proceed (NTP): 1 day
• Shop Drawings: 2 months
• Material Fabrication/Delivery: 3 months
• Demolition & Installation of Framing, Grating, Hatches, and Railing: 4 months
• Coating and Restoration: 1 month
• Total Time = 11 months
Therefore, the recommended Contract Time is as follows:
Substantial Completion: 11 months (335 calendar days from NTP)
Final Completion: 12 months (365 calendar days from NTP)