N68335-17-R-0054-0004_Solicitation_Amendment.docx
DOCX document 35 KB Posted
- Attached to
- Jet Blast Deflectors
- Solicitation number
- N68335-17-R-0054
About this file
Solicitation amendment to provide questions and answers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N68335-17-R-0054-0003_Solicitation_Amendment.docx | DOCX document | |
| N68335-17-R-0054-0002_Solicitation_Amendment.docx | DOCX document | |
| N68335-17-R-0054-0001_Solicitation_Amendment.docx | DOCX document | |
| Attachment_1_-_CDRLs.docx | DOCX document | |
| N68335-17-R-0054_Solicitation_FINAL.docx | DOCX document | |
| N68335-17-R-0054_Section_L_Attachment_1_Past_Performance_Evaluation_Data.docx | DOCX document | |
| N68335-17-R-0054_Section_L_Attachment_2_Past_Performance_Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N68335-17-R-0054
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
AMENDMENT 0004
The purpose of this amendment is to provide questions and answers, as follows:
Q1) Are each of the CLIN(s) to have a pre-production First Article Test representative item?
1. No, there is only 1 FAT unit as referenced in Section B of the Solicitation.
Q2) If question (1) is in the affirmative, what is the level and scope of the First Article Test to be performed (i.e., component and/or assembly functional configuration audit (FCA))?
1. FAT unit will be checked against what is called out in the drawing package and technical data requirements (such as dimensional, material specs, welder qualifications, welding, paint and finish, hydrostatic tests, etc) see drawing package, as well as CDRLs, for this information.
Q3) If a pre-production First Article Test FCA is required either at the assembly or component level, will a FCA acceptance test plan or test requirements be provided to the vendors?
1. No test plan will be provided. All test requirements are documented in the drawing package and the technical data requirements.
Q4) Are there manufacturing flatness tolerances that must be followed either at the assembly or component level?
1. Yes, flatness tolerances must be followed in accordance with the drawing package and the technical data requirements.
(End of Summary of Changes) image1.wmf