Exhibit_A_CDRLs_-_191_Component_Parts_-_16_June_2014.pdf

PDF 353 KB Posted

Attached to
MHU-191A/M Munitions Transporter Component Parts
Solicitation number
N68335-14-R-0190
Issued by

About this file

MHU-191A/M Munitions Transporter Component Parts CDRLs

View the file

Other files

File Type Posted
N68335-14-R-0190-0002.doc DOC document
N68335-14-R-0190-0001.doc DOC document
Attachment_1_SOW_-_191_Component_Parts_-_16_June_2014.pdf PDF
14-R-0190_component_parts_RELEASED.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A, DD Form 1423, CDRLs 6/16/2014

CONTRACT DATA REQUIREMENTS LIST (CDRL)

(1 Data Item) Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0002 A TDP ____ TM _____ OTHER PROGRAM SCHEDULE

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A001 PROGRAM SCHEDULE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

SEE BLOCK 16 SOW PARA 3.1 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD 30 DAC

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

N/A SEE BLOCK 16 Reg Repro

16. REMARKS NAWCADLKE 4.8.6.5 1

BLOCK 4: REPORT SHALL BE IN CONTRACTOR FORMAT. MICROSOFT OFFICE PRODUCT

PREFERRED.

BLOCK 13: REVISON AS REQUIRED TO ADDRESS CHANGES TO THE PROGRAM SCHEDULE AND

UPDATED AT EACH GOVERNMENT/CONTRACTOR INTERCHANGE MEETING

NAWCADLKE 6.6.4.9 1

NAWCADLKE 131821 1

15. TOTAL ▬▬▬▬► 3

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of 8 Page

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0003 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A002 ACCEPTANCE INSPECTION PLAN

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

SEE BLOCK 16 SOW PARA 3.2 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD REQUIRED ONE/R 60 DAC

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

A N/A SEE BLOCK 16 Reg Repro

16. REMARKS NAWCADLKE 4.8.6.5 1

BLOCK 8: APPROVAL/DISAPPROVAL SHALL BE WITHIN 30 DAYS OF RECEIPT OF PLAN.

BLOCK 13: REVISION DUE 30 DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.

15. TOTAL ▬▬▬▬► 2

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 2 of 8 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0004 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A003 PILOT PRODUCTION INSPECTION REPORT

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

SEE BLOCK 16 SOW PARA 3.3.1 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD REQUIRED ONE/R SEE BLOCK 16

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

A N/A SEE BLOCK 16 Reg Repro

BLOCK 8: APPROVAL/DISAPPROVAL SHALL BE WITHIN 60 DAYS AFTER RECEIPT OF REPORT.

BLOCK 12: WITHIN 30 DAYS AFTER THE COMPLETION OF ALL INSPECTIONS

BLOCK 13: REVISION DUE 30 DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.

15. TOTAL ▬▬▬▬► 2

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 3 of 8 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0102, 0202, 0302, 0402 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A004 FULL RATE PRODUCTION INSPECTION REPORT

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

SEE BLOCK 16 SOW PARA 3.4.1 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD SEE BLOCK 16

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

N/A N/A SEE BLOCK 16 Reg Repro

BLOCKS 12 and 13: WITHIN 15 DAYS AFTER INSPECTION, ONE (1) OF EACH PART LISTED IN

APPENDIX A: PART A. MANUFACTURE PARTS AT A RATE OF ONE (1) OUT OF EVERY ONE

HUNDRED (100) MANUFACTURED.

- FAILURE/NON-COMPLIANCE SHALL RESULT IN ONE HUNDRED PERCENT (100%) INSPECTION

OF THE NEXT 50 UNITS OR REMAINDER OF THE DELIVERY ORDER (DO)

WHICHEVER COMES FIRST.

15. TOTAL ▬▬▬▬► 1

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 4 of 8 Page

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0005, 0103, 0203, 0303, 0403 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A005 ENGINEERING CHANGE PROPOSAL

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-CMAN-80639 SOW PARA 3.5.2 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD AS REQD

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

AS REQD AS REQUIRED Reg Repro

BLOCK 8: APPROVAL/DISAPPROVAL SHALL BE:

30 DAYS AFTER RECEIPT FOR NO COST ECP.

90 DAYS AFTER RECEIPT FOR COST IMPACT ECP.

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 5 of 8 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0006, 0104, 0204, 0304, 0404 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A006 REQUEST FOR DEVIATION

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-CMAN-80640 SOW PARA 3.5.2 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD AS REQD

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

BLOCK 8: APPROVAL/DISAPPROVAL SHALL BE 30 DAYS AFTER RECEIPT.

15. TOTAL ▬▬▬▬►

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 6 of 8 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0007, 0105, 0205, 0305, 0405 A TDP ____ TM _____ OTHER ENGINEERING DATA

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A007 REQUEST FOR WAIVER

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-SESS-81732 SOW PARA 3.5.2 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD AS REQD

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

BLOCK 8: APPROVAL/DISAPPROVAL SHALL BE 30 DAYS AFTER RECEIPT.

15. TOTAL ▬▬▬▬►

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 7 of 8 Pages

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

0008 A TDP ____ TM _____ OTHER MEETING MINUTES

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

MHU-191A/M COMPONENT PARTS

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A008 MEETING MINUTES

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

SEE BLOCK 16 SOW PARA 3.6 NAWCADLKE 4.8.6.5

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED AS REQD SEE BLOCK 16

a. ADDRESSEE

b. COPIES

8. APP CODE

C

11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.

Draft

Final

N/A Reg Repro

BLOCK 4: SHALL BE IN CONTRACTOR FORMAT. MICROSOFT OFFICE PRODUCT PREFERRED.

BLOCK 12: MINUTES SHALL BE SUBMITTED WITHIN 14 DAYS OF EACH MEETING.

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 8 of 8 Pages