This document contains an amendment to a solicitation for commercial internet services in Somalia. The amendment revises the statement of work to allow equipment recovery within seventy-two hours prior to contract end anywhere in Somalia rather than just within the region. It also provides responses to contractor questions to clarify requirements and locations. Services are needed at Mogadishu International Airport, Baledogle Military Airfield, and Kismayo, utilizing fiber optic, satellite, or microwave solutions. The incumbent is Somtel Somalia Ltd under contract number N68171-21-P-4044. No extension to the proposal due date was granted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this SF-30 Amendment is to: (1) Revise Item No. 8 in the Statement of Work and (2) Respond to Contractors Request for Information (RFI).

All offerors must acknow ledge all Solicitation Amendments (SF-30) in accordance w ith the instructions in the solicitation.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6817122Q4026

X 9B. DATED (SEE ITEM 11)

21-Jun-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Jun-2022

CODE

NAVSUP FLC SIGONELLA SITE DJIBOUTI

PSC 831

BOX 0013

FPO AE 09902-0001

N68171 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6817122Q4026

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REVISED STATEMENT OF WORK

8. Work Area / Planning:

Remove:

b. “Contractor shall recover/repossess all contracted hardware/equipment within seventy-two

(72) hours prior to the end of the contract. The contractor shall provide set up / tear down instructions in the event that the team is relocated elsewhere in the region so the equipment can move with personnel.”

Replace with:

b. “Contractor shall recover/repossess all contracted hardware/equipment within seventy-two

(72) hours prior to the end of the contract. The contractor shall provide set up / tear down instructions in the event that the team is relocated elsewhere in the country of Somalia, so that the equipment can move with personnel.”

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

US GOVT RESPONSES TO RFI

Solicitation Amendment 0002

These are questions (Requests for Information (RFI)) that have come to the US Government by potential bidders on this competitive solicitation. The Government’s responses are indicated by “Response”.

Reminder:

(1) Each Solicitation Amendment must be acknowledged per the instructions in the solicitation.

(2) The Government will not accept any RFI submitted after the date indicated in the solicitation.

Question (Q1): Is this solicitation for a new requirement? If not, what company is the incumbent and what is the contract number and contract value?

Response (R1): This is not a new requirement. Incumbent Contractor is SOMTEL SOMALIA LTD, Contract No. N68171-21-P-4044; Contract value: $248,160.00.

Question (Q2): On page 4-Item 3- additional information is required for each site (i.e. GPS locations) for bidders to be able to supply compliant proposals. Please provide the GPS locations for each Solicitation site where services are to be provided.

Response (R2): For OPSEC (security) reasons, GPS locations/LAT/LOG information cannot be released by Government personnel for these locations. One can locate an approximate location info using open sources, i.e. Google.

Question (Q3): Please note the Page 4-Item 4 (c) and Page 5 (c) required on-site timeframes are in conflict with the Page 4-Item 6 Security requirements. Can the required on-site timeframes be modified to state that upon compliance with the Page 4-Item 6 Security requirements the required on-site timeframes would be applicable.

Response (R3): There is no conflict identified in Item 4 (c); Item 7 (c) and Item 6 Security. This is because Item 4(c) already gives the vendor 12 hours to address deficiencies and degradation of service.

Question (Q4): If the Solicitation cannot be modified as requested in Question 3 are bidders to include in their proposal provisions for on-site personnel to maintain the circuits?

Response (R4): Refer to (R3) and make your business decision on how best to perform the contract requirements.

Question (Q5): Please revise the Page 5-Item 7 (e) vaccination requirement to add that it is optional or that bidder personnel shall be required to follow local site mask rules as vaccinated personnel and verification of vaccinated personnel due to the remoteness of the sites, vaccine availability and religious reasons can be very hard to obtain at the requested sites

Response (R5): Please refer to Item 7 (e) where it states that “the contractor employee must request an exemption from the COVID-19 vaccination requirement in accordance with the requirements set forth by appropriate legal authority”.

Question (Q6): Please revise the equipment recovery within 72 hours prior to the end of the contract requirement, stated on Page 5-Item 8 (b), so that the requirement is either 72 hours after the termination of the contract or that bidders equipment is deemed abandoned if not removed as the bidder is required to provide services through the contract term and cannot recover equipment required to provide the services and still comply with the provision of the services.

Response (R6): Contractor is not allowed to abandon contractor-owned equipment upon termination or end of contracted requirement. Per the contract performance work statement: “Contractor shall recover/repossess all contracted hardware/equipment within seventy-two (72) hours prior to the end of the contract”. In the event US Government personnel are required to move to a different location, the contractor shall provide set up/tear down instructions to assist in seamless transfer of service elsewhere within Somalia.

Question (Q7): Please confirm that satellite service is not an acceptable technical solution for this Solicitation.

Response (R7): Satellite is acceptable at KIS and BMA Locations

Question (Q8): Please confirm that fiber optic and microwave services are acceptable technical solutions for this Solicitation.

Response (R8): Fiber Optic is acceptable at MOG Sites.

Question (Q9): Please provide the expected delivery timeframe, after award, for the services to be provided under this Solicitation.

Response (R9): Please see DELIVERY INFORMATION Sections (i.e. Period of Performance) in the Solicitation.

Question (Q10): Please provide the SLA required for the services to be provided under this Solicitation.

Response (R10): We do not know what is meant by your reference to “SLA.”

Question (Q11): Is there an exemption from Somalia taxes for the services and equipment to be provided under this Solicitation. If there is an exemption please provide the information needed to exempt the services and equipment from such taxes to the Somalia taxation authorities.

Response (R11): We do not have any exemption authority for Somalia Taxes provided to contractors. This is a business and legal decision for contractors to manage.

Question (Q12): The Government is respectfully requested to extend the proposal submittal date to two (2) weeks from the date on which the response to the Solicitation questions are released to bidders.

Response (R12): Extension of the proposal submittal due date is not granted.

Question (Q13): Who is the incumbent?

Response (R13): See Q1/R1 above

Question (Q14): How much was the total fixed price per year on each or any of the locations in Mogadishu?

Response (R14): See Q1/R1 above

Question (Q15): What was the most recent year that the contract was fulfilled and what price was it on all of any of the locations stated in the solicitation?

Response (R15): See Q1/R1 above

Question (Q16): How many of the locations have had connectivity prior this date?

Response (R16): See Q1/R1 above

Question (17): Can you please share the Lat/long of the following locations?

1. MOGADISHU INTERNATIONAL AIRPORT COMPOUND, MOGADISHU (2

locations within airport compound)

2. BALEDOGLE MILITARY AIRFIELD (BMA) BMA

3. KISMAYO

Response (R17): See Q2/R2 above.

(End of Summary of Changes)