Attachment_2_PBP_Milestones.pdf
PDF 7 KB Posted
- Attached to
- TR-338D Transducers
- Solicitation number
- N66604-17-R-0642
About this file
PBP Milestones
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N66604-17-R-0642-0005.pdf | ||
| N66604-17-R-0642-0004.pdf | ||
| N66604-17-R-0642-0003.pdf | ||
| N66604-17-R-0642-0002.pdf | ||
| N66604-17-R-0642-0001.pdf | ||
| Attachment_4_Exhibit_A_CDRLs.pdf | ||
| Attachment_1_DD254.pdf | ||
| Attachment_3_Exhibit_B_CDRL.pdf | ||
| N66604-17-R-0642_TR-338D_Solicitation.pdf | ||
| Attach__2_-_PR1300608611_TR-338D_SOW_Ver2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN 0001 Milestones Severable/Cumulative Percent CLIN 0001 Price Milestone Completion Verification Method
1. Preliminary Configuration Review (PCR) Completion
Severable 20%
PCR is conducted IAW the SOW. COR receives, reviews, and accepts contractor-submitted PCR presentation package and supporting technical documentation.
2. Final Configuration Review (FCR) Completion Cumulative - based on milestone #1
20%
FCR is conducted IAW the SOW. COR receives, reviews, and accepts contractor-submitted FCR presentation package and supporting technical documentation.
3. First Article material received Cumulative - based on milestones #1 and #2.
20% Contractor provides internal report to COR which provides proof of purchased material receipt (receipt report and date received)
4. Delivery of First Article transducers Cumulative - based on milestones #1, #2, and #3.
20% Contractor delivers First Article transducers and the Government receives them.
TOTAL: 80%
CLIN 0002 Milestones Severable/Cumulative Percent CLIN 0002 Price Milestone Completion Verification Method
1. Final Configuration Review (FCR) Completion Severable 50%
IAW CDRL A005, contractor submits draft copy of complete drawing package prior to FCR. COR reviews and accepts noting any discrepancies identified during the FCR
2. First Article-Physical Configuration Audit (FA- PCA) completion
Cumulative - based on milestone #1
10%
IAW CDRL A005, contractor submits complete drawing package prior to FA-PCA. COR reviews and accepts noting any discrepancies identified during the FA-PCA.
3. Functional Configuration Audit/Physical Configuration Audit (FCA/PCA) completion
Cumulative - based on milestones #1 and #2
20%
IAW CDRL A005, contractor submits complete drawing package prior to FCA/PCA. COR reviews and accepts noting any discrepancies identified during the FCA/PCA
TOTAL: 80%
Solicitation N66604-17-R-0642 for TR-338D Transducers Performance Based Payments Milestone Plan