This Task Group Instruction (TGI) details a maintenance project for cleaning and repairing Fuel Oil Service Tank No. 1A on the USS Blue Ridge (LCC-19). The work is scheduled to start on 7/21/2026 and complete by 11/19/2027, involving comprehensive tank maintenance including cleaning, welding repairs, and surface treatments. Specific tasks include vee-out and welding one linear foot of deteriorated welds, base metal weld buildup of 60 square inches, removing and installing 10 square feet of deteriorated plate, and 4 linear feet of defective stiffener.

The project requires Level II general cleaning, nondestructive testing, and application of yellow top coat paint to various tank components. The work involves multiple service areas including Fuel Oil Service Tank No. 1A, Fuel Oil Service Tank No. 1B, and the Ship Service Diesel Generator. Special requirements include SURFMEPP cleanliness standards and fabrication of a non-flammable closure due to work affecting a fire zone boundary. The tank has a capacity of 1,279 gallons, and the instruction specifies detailed procedures for surface preparation, welding, inspection, and finishing of tank components.

View the file

Other files

File Type Posted
EXHIBIT - Contract Data Requirements List (CDRL)_R2.pdf PDF
N6264925RA024-0003.pdf PDF
TGI_3819P12349_A01_c0v0_FY26.pdf PDF
TGI_3819P12351A01_c0v0_FY26.pdf PDF
TGI_3819P12347_A01_c0v0_FY26.pdf PDF
TGI_3819P12334A01_c0v0_FY26.pdf PDF
TGI_3819P12315A01_c0v0_FY26.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
TGI_3819P12331A01_c1v1_FY26.pdf PDF
TGI_3819P26201A01_c0v0_FY26.pdf PDF
Attachment II Price Proposal Form N6264925RA024(R1).xlsx XLSX spreadsheet
TGI_3819P12322_A01_c2v1_FY26.pdf PDF
TGI_3819P12313A01_c0v0_FY26.pdf PDF
TGI_3819P22102_A01_c0v0_FY26.pdf PDF
TGI_3819P14205A01_c2v2_FY26.pdf PDF
TGI_3819P25502_A01_c0v0_FY26.pdf PDF
TGI_3819P13505A01_c0v0_FY26.pdf PDF
TGI_3819P12352A01_c1v0_FY26.pdf PDF
TGI_3819P12345_A01_c1v3_FY26.pdf PDF
TGI_3819P12330A01_c1v1_FY26.pdf PDF
TGI_3819P65425A02_c0v0_FY26.pdf PDF
TGI_3819P14208A01_c1v1_FY26.pdf PDF
TGI_3819P12328A01_c1v1_FY26.pdf PDF
TGI_3819P14113A01_c0v0_FY26.pdf PDF
TGI_3819P51403A01_c0v0_FY26.pdf PDF
TGI_3819P12302A01_c2v2_FY26.pdf PDF
TGI_3819P14121A01_c0v0_FY26.pdf PDF
TGI_3819P16719A02_c0v0_FY26.pdf PDF
TGI_3819P12348_A01_c0v0_FY26.pdf PDF
TGI_3819P14207_A01_c1v2_FY26.pdf PDF
TGI_3819P13411A01_c1v1_FY26.pdf PDF
TGI_3819P12329A01_c1v1_FY26.pdf PDF
TGI_3819P14204A01_c0v0_FY26.pdf PDF
TGI_3819P12389A01_c0v0_FY26.pdf PDF
TGI_3819P12350A01_c0v0_FY26.pdf PDF
TGI_3819P14114A01_c0v0_FY26.pdf PDF
TGI_3819P12343A01_c1v1_FY26.pdf PDF
TGI_3819P12307A01_c0v0_FY26.pdf PDF
TGI_3819P22101_A01_c0v0_FY26.pdf PDF
TGI_3819P13339A01_c0v0_FY26.pdf PDF
TGI_3819P26202_A01_c0v0_FY26.pdf PDF
TGI_3819P25604A01_c1v1_FY26.pdf PDF
TGI_3819P14116A01_c0v0_FY26.pdf PDF
TGI_3819P12346_A01_c0v0_FY26.pdf PDF
TGI_3819P12325_A01_c0v01_FY26.pdf PDF
TGI_3819P12326_A01_c1v0_FY26.pdf PDF
TGI_3819P22103A01_c0v0_FY26.pdf PDF
TGI_3819P12309A01_c1v0_FY26.pdf PDF
TGI_3819P12308A01_c0v0_FY26.pdf PDF
TGI_3819P13507A01_c0v0_FY26.pdf PDF
Show 40 more

Latest 50 of 162 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: FO SERVICE TK NO. 1A AY A 0 0

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE:

F/O - CLEAN AND REPAIR FUEL OIL SERVICE TANK NO. 1A (5-122-1-F)

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

YUUICHI YOSHIHARA 231B. 315-243-9984 22-DEC-2023

APPROVED BY: CODE PHONE DATE

RYOUTA TAKAGI 231B. 315-243-4502 22-DEC-2023

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

CHANGE INSTRUCTIONS:

SPECIAL REQUIREMENTS:

SURFMEPP

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II

This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: FO SERVICE TK NO. 1A AY A 0

FOUO

SHIP: LCC-19 CHG/VER: 0/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-6 J-1 M-1

1. SCOPE/PURPOSE

1.1 Title: Fuel Oil Service Tank No. 1A (5-122-1-F); clean and repair

1.2 Location of Work:

1.2.1 Fuel Oil Service Tank No. 1A (5-122-1-F)

1.2.2 Fuel Oil Service Tank No. 1B (5-123-1-F)

1.2.3 Ship Service Diesel Generator (SSDG) No. One (5-121-1-E)

1.3 Identification:

1.3.1 Quantity (One EA), Fuel Oil Service Tank No. 1A

Tank No.: 5-122-1-F Capacity: 1,279 Gallons

1.3.2 Quantity (One EA), Fuel Oil Service Tank No. 1B

Tank No.: 5-123-1-F Capacity: 1,279 Gallons

1.3.3 Quantity (One EA), Manhole Cover Plate(s) for 5-122-1-F

Manhole No(s).: Not Assigned Size: 15 Inches x 23 Inches Material: Steel

1.3.4 Quantity (One EA), Bolting Ring for Manhole Cover Plate(s) for 5-122-1-F

Manhole No(s).: Not Assigned Material: Steel

1.3.5 Quantity (One EA), Manhole Cover Plate(s) for 5-123-1-F

Manhole No(s).: Not Assigned Size: 15 Inches x 23 Inches Material: Steel

1.3.6 Quantity (One EA), Bolting Ring for Manhole Cover Plate(s) for 5-123-1-F

Manhole No(s).: Not Assigned Material: Steel

1.4 Security Classification: None.

FOUO

SHIP: LCC-19 CHG/VER: 0/0

1.5 Initial Condition:

1.5.1 Potential Lead Hazard

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM S9086-

CJ-STM-

010/CH-075

Fasteners 7 N

4 DWG 210-

7542615

FUEL OIL & LUBE OIL SERVICE

TANKS FOR SHIPS SERVICE

DIESEL GENERATOR

A Y AL

L

3. APPENDICES:

3.1 Appendix “J” TGI Job Summary Information Sheet

3.2 Appendix "M" TGI Material List

3.3 Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1 and 1.3.2.

5.1.1 Accomplish the requirements of 009-107 of 2.1.

5.1.1.1 Accomplish the requirements of 009-09 of 2.1.

5.1.1.2 Ensure General Cleaning must be Level II.

5.1.2 Accomplish installation of each manhole cover for each tank listed in 1.3.1 and 1.3.2 in accordance with Figure 075-4-1 of 2.3.

5.2 Repair each tank listed in 1.3.1, based on the CCIMS assessment report as designated by the SUPERVISOR, using 2.4 for guidance. See 5.9.4 through 5.9.6.

5.2.1 Vee-out and weld a total of one linear foot of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, shell plating, and overhead.

5.2.2 Chip and grind each surface flush in way of each repair.

5.2.3 Base metal weld buildup a total of 60 square inches of each plate defect in the tank.

5.2.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.

7/21/2026

11/19/2027

FOUO

SHIP: LCC-19 CHG/VER: 0/0

5.2.3.2 Surface must be ground to sound metal prior to base metal weld buildup.

5.2.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.

5.2.3.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.

5.2.4 Remove existing, fabricate and install new a total of 10 square feet of deteriorated plate.

5.2.5 Remove existing, fabricate and install new a total of 4 linear feet of defective stiffener.

5.2.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A, Lines One through 7.

5.2.6.1 Accomplish nondestructive testing in accordance with Line 11.

5.2.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.

5.3 Accomplish the requirements of 009-32 of 2.1 for interior surface of each tank listed in 1.3.1 where new material is installed and disturbed by hot work repaired in 5.2.

5.3.1 Power tool clean for interior surface of each tank to remove all rust and corrosion.

5.3.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.8.

5.4 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 12, for machinery space side surface of each cover plate listed in 1.3.3.

5.4.1 Apply one top coat of yellow, color No. 13538 (SAE-AMS-STD-595), conforming to MIL-PRF-24635, Type V, at 4 to 7 mils Dry Film Thickness (DFT) to machinery space side surface of each cover plate.

5.4.2 Power tool clean for tank side surface of each cover plate to remove all existing coating, rust, and corrosion.

5.4.2.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.8.

5.5 Accomplish the requirements of 009-32 of 2.1 for machinery space side surface of each bolting ring listed in 1.3.4.

5.5.1 Apply one top coat of yellow, color No. 13538 (SAE-AMS-STD-595), conforming to MIL-PRF-24635, Type V, at 4 to 7 mils Dry Film Thickness (DFT) to machinery space side surface of each bolting ring.

5.5.2 Power tool clean for tank side surface of each bolting ring to remove all existing coating, rust, and corrosion.

5.5.2.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.8.

5.6 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 12, for machinery space side surface of each cover plate listed in 1.3.5.

5.6.1 Apply one top coat of yellow, color No. 13538 (SAE-AMS-STD-595), conforming to MIL-PRF-24635, Type V, at 4 to 7 mils Dry Film Thickness (DFT) to machinery space side surface of each cover plate.

5.6.2 Power tool clean for tank side surface of each cover plate to remove all rust and corrosion.

5.6.2.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.8.

FOUO

SHIP: LCC-19 CHG/VER: 0/0

5.7 Accomplish the requirements of 009-32 of 2.1 for machinery space side surface of each bolting ring listed in 1.3.6.

5.7.1 Apply one top coat of yellow, color No. 13538 (SAE-AMS-STD-595), conforming to MIL-PRF-24635, Type V, at 4 to 7 mils Dry Film Thickness (DFT) to machinery space side surface of each bolting ring.

5.7.2 Power tool clean for tank side surface of each bolting ring to remove all rust and corrosion.

5.7.2.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.8.

5.8 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.9 Notes:

5.9.1 Planner: Code 231B Y. Yoshihara, 243-9984

Engineer: Code 250 S. Fujita, 243-4307 Engineer: Code 250 J. Igarashi, 243-4230

5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.9.3 This TGI meets the intent of DDG CSWT File Nos. 123-133 and 123-142.

5.9.4 CCIMS assessment of each tank listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No. 3819P12301I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.

5.9.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.9.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.9.7 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.9.8 Ship’s Force will provide system fluid for contractor when requested by Code 333 Work Integration Manager

(WIM).

5.9.9 JCNs ER01-ZAM0, ER01-ZAK2, and EA02-ZAA9 are related to this TGI.

5.10 Government Furnished Material (GFM): None.

5.11 SRF-JRMC will provide the following service work: (TGI No. 3819P12301S02).

5.11.1 [C740] Crane and crane rigging service.

5.11.2 [X99E] Utility service, electrical.

5.11.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

5.11.4 [C106.1] Safety inspection for SRF-JRMC employees.

FOUO

SHIP: LCC-19 CHG/VER: 0/0

5.11.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.11.6 [C133] QA inspection for (G) symbol(s).

5.11.7 [C135] QA inspection for (G) symbol(s).

5.11.8 [C250] Technical support.

FOUO

J-1

SHIP: LCC-19 CHG/VER: 0/0

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

FO SERVICE TK NO. 1A AY A 0 0

CU PHASE TITLE:

F/O - CLEAN AND REPAIR FUEL OIL SERVICE TANK NO. 1A (5-122-1-F)

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

FO SVC 5-123-1-F TK FO SVC 5-122-1-F TK

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA ,TAKEHIDE

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

3819P12301 A01

TOTAL MAT’L COST TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to clean and repair fuel oil service tank No. 1A (5-122-1-F)

Location of Work:

Fuel Oil Service Tank No. 1A (5-122-1-F) Fuel Oil Service Tank No. 1B (5-123-1-F) Ship Service Diesel Generator (SSDG) No. One (5-121-1-E)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

5.1 LBR QA HRs 22 KE PC

5.2 SFTR HRs, WELD HRs, CARP HRs, PNTR HRs, QA HRs 22 KE PC

5.3 PNTR HRs, QA HRs 22 KE PC

5.4 PNTR HRs, QA HRs 22 KE PC

5.5 PNTR HRs, QA HRs 22 KE PC

5.6 PNTR HRs, QA HRs 22 KE PC

5.7 PNTR HRs, QA HRs 22 KE PC

5.8 PNTR HRs, QA HRs 22 KE PC

Dewatering and Cleaning Work CFM: $ for marine chemist, gaskets, fasteners, tank watch cost, and MISC.

22 MQ CS

Structural Work CFM: $ for all paints, thinner, grit including disposal cost, fire watch and tank watch cost, MT inspection cost, lead sampling/analysis cost, air compressor rental cost and fuel oil cost for air hose test, and MISC such as electrode, gases, temporary closure/covering material, and other consumable.

22 MQ CS

Process Funding Document 10 CT OM

FOUO

M-1

SHIP: LCC-19 CHG/VER: 0/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

FO SERVICE TK NO. 1A AY A 0 0

CU PHASE TITLE:

F/O - CLEAN AND REPAIR FUEL OIL SERVICE TANK NO. 1A (5-122-1-F)

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

3819P12301 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 FO SERVICE TK NO. 1A AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

3819P12301 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 FO SERVICE TK NO. 1A AY A 0