Attachment 1 Work Specification Package
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RSC_007.pdf | ||
| Answers_to_Request_for_Specification_Clarification_no._001-006.pdf | ||
| DD254-Rev1.pdf | ||
| 5_Way_Breakdown-Rev_1.xlsx | XLSX spreadsheet | |
| N4523A-17-R-0001_FY_17_Stennis_Preservation_Solicitation.pdf | ||
| Attachment_3._5_Way_Breakdown.xlsx | XLSX spreadsheet | |
| Attachment_4._Request_for_Specification_Clarifications.docx | DOCX document | |
| Attachment_2._CDRLs_and_DiDs.pdf | ||
| Attachment_5._DD254 _Contract_Security_Classification_Specification.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
INCLUDES ALL CHANGES THROUGH 9/3/2016
PUGET SOUND NAVAL SHIPYARD AND INTERMEDIATE
MAINTENANCE FACILITY
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
USS JOHN C. STENNIS (CVN-74)
SPECIFICATION NUMBER: NWRMC-502-16
FY-17 PLANNED INCREMENTAL AVAILABILITY (PIA)
INDEX
SHIP: USS JOHN C. STENNIS (CVN 74) NWRMC-502-16
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-17 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE DATE
009-01 General Criteria; accomplish 07/30/2015
009-01 General Criteria; accomplish 07/18/2014
009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 07/18/2014
009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 07/18/2014
009-03 Toxic and Hazardous Substances; control 07/18/2014
009-03 Toxic and Hazardous Substances; control 07/18/2014
009-04 Quality Management System; provide 05/12/2016
009-04 Quality Management System; provide 07/18/2014
009-05 Temporary Accesses; provide 07/30/2015
009-05 Temporary Accesses; provide 07/18/2014
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
07/18/2014
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
07/30/2015
009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 07/30/2015
009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 07/18/2014
009-08 Fire Protection at Contractor's Facility; accomplish 07/30/2015
009-08 Fire Protection at Contractor's Facility; accomplish 07/18/2014
009-10 Shipboard Asbestos-Containing Material (ACM); control 07/18/2014
009-10 Shipboard Asbestos-Containing Material (ACM); control 07/18/2014
009-18 Magnetic Material; control 07/18/2014
009-18 Magnetic Material; control 07/18/2014
009-19 Provisioning Technical Documentation (PTD); provide 07/18/2014
009-19 Provisioning Technical Documentation (PTD); provide 07/30/2015
009-20 Government Property; control 07/18/2014
009-20 Government Property; control 07/18/2014
009-21 Logistics and Technical Data; provide 07/18/2014
009-21 Logistics and Technical Data; provide 07/18/2014
009-23 Interferences; remove and install 07/30/2015
009-23 Interferences; remove and install 07/18/2014
009-24 Shipboard Authorization, Control, Isolation, Blanking,Tagging, and Cleanliness Requirements; accomplish
07/30/2015
009-24 Shipboard Authorization, Control, Isolation, Blanking, and Tagging Requirements;
accomplish
07/10/2015
009-28 Fire Prevention Requirements; accomplish 07/30/2015
009-28 Fire Prevention Requirements; accomplish 06/10/2014
009-29 Asbestos-Free Pipe Hanger Liner Material; install 07/29/2004
009-29 Asbestos-Free Pipe Hanger Liner Material; install 07/29/2004
009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/17/2013
Page 1 of 6 EXECUTING WORK
ITEM_NO. TITLE DATE
009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/17/2013
009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish
07/30/2015
009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish
07/18/2014
009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component; provide
07/30/2015
009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component; provide
07/19/2007
009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish
07/18/2014
009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish
07/18/2014
009-59 Organotin Antifouling Material; control 07/29/2011
009-59 Organotin Antifouling Material; control 07/29/2011
009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;
provide and manage
09/01/2015
009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;
provide and manage
09/01/2015
009-61 Shipboard Use of Fluorocarbons; control 07/18/2014
009-61 Shipboard Use of Fluorocarbons; control 07/18/2014
009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 07/18/2014
009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 07/18/2014
009-65 Polychlorinated Biphenyls (PCBs); control 07/29/2011
009-65 Polychlorinated Biphenyls (PCBs); control 07/29/2011
009-67 Integrated Total Ship Testing; manage 07/18/2014
009-67 Integrated Total Ship Testing; manage 07/18/2014
009-69 Heavy Weather/Mooring Plan; provide 07/30/2015
009-69 Heavy Weather/Mooring Plan; provide 07/18/2014
009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish
07/18/2014
009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish
07/30/2015
009-72 Physical Security at Private Contractor's Facility; accomplish 07/18/2014
009-72 Physical Security at Private Contractor's Facility; accomplish 07/18/2014
009-73 Shipboard Electrical/Electronic Cable; remove, relocate, repair, and install 07/30/2015
009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install 07/18/2014
009-74 Occupational, Safety and Health Requirements; accomplish 07/30/2015
009-74 Occupational, Safety and Health Requirements; accomplish 07/10/2015
009-77 Cofferdam Requirements; accomplish 07/18/2014
009-77 Cofferdam Requirements; accomplish 07/18/2014
009-79 Government Owned Material (GOM); status reporting 07/18/2014
009-79 Government Owned Material (GOM); status reporting 07/18/2014
009-80 Ship's Facilities; provide 07/18/2014
009-80 Ship's Facilities; provide 07/18/2014
009-81 Compartment Closeout; accomplish 07/18/2014
009-81 Compartment Closeout; accomplish 07/30/2015
Page 2 of 6 EXECUTING WORK
ITEM_NO. TITLE DATE
009-82 Data Requirements When Installing an Equal Component Vice Specified Component;
provide 07/29/2011
009-82 Data Requirements When Installing an Equal Component Vice Specified Component;
provide
07/29/2011
009-83 Wire Rope Fitting Verfication; provide 01/17/2013
009-83 Wire Rope Fitting Verfication; provide 01/17/2013
009-84 Accountability of Temporary Fasteners; provide 07/18/2014
009-84 Accountability of Temporary Fasteners; provide 07/18/2014
009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish
08/01/2008
009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish
08/01/2008
009-87 Chemical disinfection Procedures; accomplish 07/18/2014
009-87 Chemical disinfection Procedures; accomplish 07/18/2014
009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify
07/18/2014
009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify
07/18/2014
009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;
accomplish
07/29/2011
009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;
accomplish
07/29/2011
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide
07/18/2014
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide
07/18/2014
009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/17/2013
009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/17/2013
009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 07/18/2014
009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 07/18/2014
009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide
01/17/2013
009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide
01/17/2013
009-99 Ship Departure Report; provide 07/18/2014
009-99 Ship Departure Report; provide 07/18/2014
009-100 Ship's Stability Process Control Procedure (PCP); maintain 07/18/2014
009-100 Ship's Stability Process Control Procedure (PCP); maintain 07/18/2014
009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish 07/18/2014
009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish 07/18/2014
009-102 Alteration Verification; provide 07/29/2011
009-102 Alteration Verification; provide 07/29/2011
009-103 Weight and Moment Change Data; provide 07/18/2014
009-103 Weight and Moment Change Data; provide 07/18/2014
009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/06/2014
009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/06/2014
009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish
07/18/2014
009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish
07/18/2014
Page 3 of 6 EXECUTING WORK
ITEM_NO. TITLE DATE
009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;
accomplish 07/18/2014
009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;
accomplish
07/18/2014
009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 07/18/2014
009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 07/18/2014
009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration;
provide and manage
07/18/2014
009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration;
provide and manage
07/30/2015
009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 07/18/2014
009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 07/18/2014
009-118 CG Deck Loading; accomplish 07/18/2014
009-118 CG Deck Loading; accomplish 07/18/2014
009-120 Fact Finding and Critique of Unplanned Events; manage 07/18/2014
009-120 Fact Finding and Critique of Unplanned Events; manage 07/30/2015
009-121 Ship Assessment/Inspection Requirements; provide 07/18/2014
009-121 Ship Assessment/Inspection Requirements; provide 07/18/2014
009-122 Temporary Padeye; install and remove 07/30/2015
099-02NW General Contractor Environmental Protection Requirements for Bremerton Naval Complex (BNC).
07/01/2016
Page 4 of 6 EXECUTING WORK
DATETITLEITEM NO.
CATEGORY II. FY-17 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER
009-32 Cleaning and Painting Requirements; accomplish 07/10/2015
009-32 Cleaning and Painting Requirements; accomplish 07/10/2015
009-32 Cleaning and Painting Requirements; accomplish 05/12/2016
Page 5 of 6 EXECUTING WORK shane.ferreira Cross-Out shane.ferreira Cross-Out shane.ferreira Cross-Out
ITEM NO. TITLE
Workplace Requirements; accomplish042-01-001
Scheduling, Progressing, and Associated Reports; provide042-11-001
Hazardous Waste Produced on Naval Vessels; control077-01-001
Water Brake Tank Catapult Number 2, preserve587-21-001
Water Brake Tank Catapult Number 1, preserve587-21-002
Catapult No. 3 Wing Voids Preservation; accomplish631-13-002
Vent Inlet 01-156-3-Q; preserve631-13-005
Vent Inlet 01-156-5-Q; preserve631-13-006
Catapult Piping Space 1-165-4-Q; preserve631-13-007
Vent Plenum 02-16-2-Q; preserve631-13-008
Vent Plenum 02-21-4-Q; preserve631-13-010
Vent Plenum 01-68-2-Q; preserve631-13-011
Vent Plenum 02-77-2-Q; preserve631-13-012
Vent Plenum 02-78-2-Q; preserve631-13-013
Vent Plenum 02-94-1-Q; preserve631-13-014
Vent Plenum 02-95-1-Q; preserve631-13-015
Vent Plenum 01-143-6-Q; preserve631-13-016
Vent Inlet (01-172-1-Q) and Supply System Trunk (S-03-172-1); preserve631-13-017
Vent Plenum 03-175-18-Q; preserve631-13-019
Vent Plenum 01-66-1-Q; preserve631-13-020
Vent Plenum 01-74-1-Q; preserve631-13-021
Vent Plenum 01-88-3-Q; preserve631-13-022
Vent Plenum 01-162-2-Q; preserve631-13-023
Vent Plenum 01-235-4-Q; preserve631-13-024
Vent Plenum 02-229-2-Q; preserve631-13-025
Void (3-123-1-V); preserve631-13-026
Void (4-152-1-V); preserve631-13-027
Availability Work Package (AWP) Integration; provide813-31-001
Project Management; provide897-10-001
Contractor Facilities; provide992-10-001
Page 6 of 6 EXECUTING WORK
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 042-01-001
COAR: 16 PCN: PM01-Q062
CMP: NONE
PLANNER: VARNEY , ROBERT
ARCHUT ,
CHRISTOPHER
SSP: NWRMC-502-16 1 of 7 ITEM NO: 042-01-001
1. SCOPE:
1.1 Title: Workplace Requirements; accomplish
1.2 Location of Work:
1.2.1 Bremerton Naval Complex (BNC)
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 099-01NW, General Occupational Safety and Health Requirements for the BNC
2.3 099-02NW, General Contractor Environmental Protection Requirements for BNC
2.4 099-03NW, General Contractor Air Pollution Control and Reporting Requirements for BNC
2.5 099-04NW, General Contractor HAZMAT Requirements for BNC
2.6 099-05NW, General Contractor Water Pollution and Spill Prevention Requirements for BNC
2.7 099-06NW, General Contractor Waste Management Requirements for BNC
2.8 099-07NW, General Contractor Solid Waste Management Requirements for
BNC
2.9 099-08NW, Forms
2.10 099-10NW, Maintaining Protection and Cleanliness for Non- Radioactive Operations; accomplish
3. REQUIREMENTS:
3.1 Coordinate work schedule to include the below listed items:
3.1.1 Prepare for work interruption periods of 2 each, up to 2 hour duration, shipyard drills to take place during this period of performance. Pass this requirement to all subcontracted work.
Notification of work interruption will be provided as soon as SUPERVISOR is notified.
3.1.2 Notify the SUPERVISOR, 72 hours in advance, if the Contractor plans to work during the following listed dates: 2/20/2017, 5/29/2017, and 7/4/2017. No Government services will be available on the preceding dates as these are federal holidays or shut-down periods for the shipyard.
3.2 Ensure all Contractor and Subcontractor employees observe the following general workplace requirements in accordance with 2.1 through 2.10:
3.2.1 Require each employee, requiring access to the CIA, to view a
SHIP: USS JOHN C. STENNIS (CVN 74)
SSP: NWRMC-502-16 2 of 7 ITEM NO: 042-01-001 training video approximately 45 minutes in length while Government access badge application is being processed.
3.2.2 Prohibit smoking or the use of smokeless tobacco products on the entire ship, drydock, piers, and buildings within the shipyard except in designated and posted areas.
3.2.3 Ensure employees eat and drink only in approved eating
facilities and not aboard the ship or in the industrial environment.
3.2.3.1 Remove coveralls and hard hats prior to entering eating areas, facilities, or areas where food items are being handled.
3.2.4 Wear appropriate safety equipment, including OSHA approved hard hats with Contractor Company name and the employee's name clearly visible, and the employee Company and PSNS & IMF identification badges visible at all times.
3.2.5 Inform employees that personal property taken within the shipyard and aboard the ship, such as tool boxes, special tools, clothing and so forth are subject to search and inventory daily on arrival and departure and that personal property must not be left unattended or left on on board the ship. A listing of prohibited items is included on Attachment A.
3.2.6 Prohibit unauthorized Contractor or personal electronic devices (PEDs) from entry into the Government facility. Exceptions may be granted by the PSNS & IMF Information Assurance Manager (IAM)(Code 109.2) in situations where PED is required to support an existing contract and is used following the restrictions provided by the PSNS & IMF IAM. Submit an automated information system (AIS) Security Survey for Visitor Computer Equipment, PSNS&IMF 5239/49 (Rev. 3-15) (Attachment B) a minimum of 5 working days before coming on site.
3.2.7 Prohibit vehicle operators on a DOD installation from use of cell phones unless the vehicle is safely parked or unless they are using a hands free device. Cell phones are to be turned off and never used when at a gas station or anywhere fuel is stored.
3.2.8 Prohibit personal and company provided cell phones having internet connection or picture taking capabilities. The Government Shipyard Security Director (Code 1120) must authorize any exceptions.
3.2.9 Prohibit mercury or mercury containing compounds being taken onboard naval warships except for functional mercury used in batteries; fluorescent lights; required instruments, sensors, or controls; weapon systems; and chemical analysis reagents specified by NAVSEA. Ensure portable fluorescent lamps and portable instruments containing mercury are shock-proof and include a second boundary of containment for the mercury or mercury compound.
3.3 Request permission to use contractor owned computers at Government facility as follows:
3.3.1 Complete and submit PSNS Form 5239/49 (Attachment B) and provide for a Government review and approval timeframe of 5 business days.
3.3.2 Prohibit Contractor-owned computers/system connection to the PSNS & IMF Local Area Network (LAN) or any other Government LAN without Code 109.2 approval.
SSP: NWRMC-502-16 3 of 7 ITEM NO: 042-01-001
3.3.3 Ensure personally owned computing devices are not utilized inside PSNS & IMF CIA, including hand held sized computers, cellular phones capable of internet connection and personal data assistants (PDAs).
3.3.4 Request approval from Code 109.2 for computers (laptop or desktop) to be equipped with a modem card for outside connectivity, via the form in 3.3.1 for each system, prior to entry into the PSNS &
IMF CIA.
3.3.5 Prohibit combination Modem/Network card usage within the PSNS
& IMF CIA.
3.4 Arrange and chair a meeting with the SUPERVISOR, NSA and Ship's Fire Marshall, within 5 days prior, to the start of availability, to exchange information on Contractor Gas Free Engineering, Hot and Cold Work Permits, and terminology to be used by all parties to prevent violations of gas-free certificates and hot/cold work permits during the maintenance availability period.
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: NWRMC-502-16 4 of 7 ITEM NO: 042-01-001
PROHIBITED ITEMS
Pursuant to the authority contained in 10 U.S.C. 6011 and U.S. Navy Regulations, Chapter 8, Article 0826, the following items are prohibited from areas under NAVSEA cognizance unless specifically authorized by the Office of Security and Law Enforcement (SEA 104):
• Personal photographic equipment of any kind; including, but not limited to, cameras (still and/or video), film, and cell phones with cameras.
• Weapons or other dangerous materials of any kind; including, but not limited to, firearms, ammunition, knives (blades longer than 2-inches), explosives, incendiaries, and personal defense aerosols/sprays.
• Personal reproduction equipment of any kind; including, but not limited to, photocopying, copying, and/or recording devices.
• Any alcoholic beverages.
• Personally owned portable electronic devices (PEDs) used for storing data; including, but not limited to, removable storage devices (e.g., memory sticks, rewriteable CDs and DVDs, Zip and floppy disks).
• Any other item, the possession of which is prohibited by Federal, State, or municipal law, Department of Defense, or Department of Navy instruction, directive, or policy.
PROHIBITED ITEMS
SSP: NWRMC-502-16 5 of 7 ITEM NO: 042-01-001
AIS SECURITY SURVEY FOR VISITOR COMPUTER EQUIPMENT Ref: PSNS&IMFINST 5239.6
COMPANY OR ACTIVITY NAME EQUIPMENT ARRIVAL DATE EQUIPMENT DEPARTURE DATE
(NOT TO EXCEED 1 YEAR)
MFG & MODEL ID SERIAL NUMBER OPERATING SYSTEM VERSION
AUTHORITY TO OPERATE ON PUGET SOUND NAVAL SHIPYARD AND INTERMEDIATE MAINTENANCE FACILITY (PSNS & IMF)
I certify that this system is owned by a company under contract with the U.S. Government. I understand that personally owned computers and peripherals are not authorized at PSNS & IMF, and are not covered by this Authority to Operate.
I understand that while at PSNS & IMF, I will not connect to the PSNS & IMF Local Area Network. I will ensure a daily virus scan of memory and all storage media is performed prior to any use of this system, and all removable media will be identified with the appropriate sensitivity labels. A copy of this Authority to Operate shall accompany the system at all times while at PSNS & IMF.
I understand that all users must have a security clearance equal to, or higher than, the highest level of information on the system, as well as a need-to-know.
DATE: SIGNATURE:
PHONE NUMBER: FAX NUMBER: PRINTED NAME:
DATA SENSITIVITY
INDICATE THE SENSITIVITY LEVEL OF THE INFORMATION STORED ON THE SYSTEM BY PERCENTAGE (MUST TOTAL 100%)
LEVEL PERCENT YES NO (IF YES, EXPLAIN IN COMMENTS BLOCK, BELOW.)
COMPANY DATA (NON-NAVY) % WILL THE LAPTOP BE USED TO CONNECT TO ANY NETWORK?
IF YES, EXPLAIN IN THE COMMENTS BELOW.
UNCLASSIFIED (NAVY) %
DOES THE LAPTOP HAVE A WIRELESS NETWORK CARD?
FOUO IF YES, HAS IT BEEN PROPERLY DISABLED?
PRIVACY ACT
NNPI/NOFORN DOES THE LAPTOP HAVE BLUETOOTH CAPABILITY?
IF YES, HAS IT BEEN PROPERLY DISABLED?
CONFIDENTIAL (NAVY) %
DOES THE LAPTOP HAVE A CAMERA?
SECRET (NAVY) % IF YES, HAS IT BEEN PROPERLY DISABLED?
TOTAL 100 %
NOTE: PER NAVSEA AND PSNS&IMFINST 5510.1H, CAMERAS ARE NOT AUTHORIZED INSIDE PSNS & IMF WITHOUT AN APPROVED CAMERA PERMIT (ISSUED BY THE SECURITY DIVISION (CODE 1120)). If a camera-type device can be opened, the camera module must be removed. The void (area) where the camera module existed must be filled COMPLETELY up to the surface of the camera backing with a PERMANENT, NON-TRANSLUCENT (cannot see through it or light pass through it) epoxy. The camera lens (very small pinhole-sized lens), NOT the glass/plastic cover over the camera, must be DRILLED or GROUND OUT with a fine drill, permanently damaging the camera from operating. (The camera will NOT display a picture.) The void or area from the top cover down into the camera, must then be filled with a PERMANENT, NON-TRANSLUCENT (cannot see through it or light pass through it) epoxy; e.g., JB KWIK, JB Weld, or Liquid Metal.
COMMENTS:
COMPANY ADDRESS COMPANY POINT OF CONTACT COMPANY PHONE NUMBER
SSP: NWRMC-502-16 6 of 7 ITEM NO: 042-01-001
PSNS & IMF CODE/SHOP SUPPORTED PSNS & IMF PROJECT NAME
AND LOCATION OF SYSTEM PSNS & IMF LOCAL POINT OF CONTACT
PROJECT: LOCATION: NAME: PHONE:
PSNS & IMF APPROVAL TO OPERATE
I hereby grant authority to operate this system on PSNS & IMF during the period specified and under the conditions specified above. Code 109.21, Fax (360) 476-0962, Email BREM.PSNS.INFOSEC.FC@NAVY.MIL
PSNS&IMF 5239/49 (Rev. 3-15) mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil mailto:BREM.PSNS.INFOSEC.FC@navy.mil
SSP: NWRMC-502-16 7 of 7 ITEM NO: 042-01-001
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 042-11-001
COAR: 16 PCN: PM01-Q063
CMP: NONE
PLANNER: FERREIRA, SHANE
SSP: NWRMC-502-16 1 of 3 ITEM NO: 042-11-001
1. SCOPE:
1.1 Title: Scheduling, Progressing, and Associated Reports; provide
1.2 Location of Work:
1.2.1 Not Applicable
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
3. REQUIREMENTS:
3.1 Accomplish the requirements of each approved work specification in accordance with the integrated work sequence and schedule provided in Attachment A.
3.2 Accomplish the requirements of this work item in addition to the requirements of 2.1, as amended by the requirements contained herein.
3.2.1 Identify any changes from the original schedule, for each work item, providing the reason for the change and the corrective action being taken or proposed in order to maintain scheduled milestones, when submitting revised production schedules to the SUPERVISOR at weekly progress meetings.
3.2.2 Provide Company senior representative to attend Naval
Supervising Activity (NSA) weekly progress meetings to brief ship's Commanding Officer of contractor schedule progress and issues/resolutions.
3.2.3 Provide Company representation to attend and participate in project Daily Production List (DPL) meeting to provide updates to status of any critical path work, stopped work, work scheduled to start and not started, work scheduled to finish and not finished, and certification status of work completed but not certified.
3.2.4 Provide Company representative to attend and participate in project weekly Short Range View (SRV) meetings to provide required information to conduct an effective SRV meeting, validating the next 4 to 6 weeks of scheduled work is accurate. NSA will provide SRV meeting reports a minimum of 2 working days prior to scheduled meeting.
3.2.4.1 Review SRV Key Event Milestone Analysis Report and SRV Tally Sheets for errors, omissions, and correct prior to meeting.
3.2.4.2 Ensure correct Zone Manager is indicated for Contractor work item CU Phases.
3.2.4.3 Verify all shift calendars reflect the actual plan for work accomplishment.
3.2.4.4 Validate all work stoppages have work stoppage
information and realistic/current Estimated Resolution Date (ERD) reflecting when work, paper, material or other issues will be
SSP: NWRMC-502-16 2 of 3 ITEM NO: 042-11-001 resolved to continue work.
3.2.4.5 Verify or reschedule all Start Dates Riding on Time
Now(ROTN), claim completion, certify or change the Remaining Duration (RDU) for all Finish Dates Riding on Time Now (ROTN).
Verify correct sequence of work and that no obstacles exist that will prevent starting work as scheduled or sequence/reschedule work prior to SRV meeting.
3.3 Schedule the submission of the reports required by this contract in accordance with the following:
3.3.1 Submit one legible copy, in approved transferrable media, of a schedule of all reports required by the contract, work specifications and reports required by 2.1, to the SUPERVISOR no later than Contract Award plus 14 calendar days.
3.3.1.1 Update and include the status of submission/acceptance of each report in the submission of management information for each weekly progress meeting.
3.3.2 Submit one legible copy, in approved transferrable media, of a report detailing Lessons Learned within 10 working days of completion of each production work specification. Provide recommended changes to both Government and Contractor processes as a result of lessons learned collected.
3.4 Provide daily schedule updates (Monday through Friday) to NSA scheduler for all contractor work, by CU phase, to maintain NSA integrated schedule validity in addition to the requirements of 2.1.
4. NOTES:
4.1 Specified dates designated in this item are days or dates identified by referring to known events in the contract. Days after a specific event are indicated by the event title followed by a plus sign (+) and the date identifier. Days before a specific event are identified by the event title followed by a minus sign (-) and the date identifier. Events and legends used in the Job Order are:
4.1.1 Contract Award -- A
4.1.2 Availability Start -- SA
4.1.3 Availability Completion -- CA
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SSP: NWRMC-502-16 3 of 3 ITEM NO: 042-11-001
Attachment A
The layer chart below illustrates the integrated work sequence and schedule of the work package. It has been split into four zones utilizing two blast cells. Each space/compartment will be available for isolation and access between the dates listed on its respective line.
Compartment Work
Specification Zone Milestones
01-235-4-Q 631-13-024 1 AW43
02-229-2-Q 631-13-025 1 AW43
03-175-18-Q 631-13-019 1 AW43
01-172-1-Q 631-13-017 1 AW43
4-152-1-V 631-13-027 2 AW43
3-123-1-V 631-13-026 2 AW43
01-162-2-Q 631-13-023 2 AW43
01-143-6-Q 631-13-016 2 AW43
1-165-4-Q 631-13-007 2 AW43
01-156-3-Q 631-13-005 2 AW43
01-156-5-Q 631-13-006 2 AW43
WING VOID 631-13-002 3 AW43
01-88-3-Q 631-13-022 3 AW43
02-95-1-Q 631-13-015 3 AW43
02-94-1-Q 631-13-014 3 AW43
02-78-2-Q 631-13-013 3 AW43
02-77-2-Q 631-13-012 3 AW43
01-74-1-Q 631-13-021 4 AW43
01-68-2-Q 631-13-011 4 AW43
01-66-1-Q 631-13-020 4 AW43
02-16-2-Q 631-13-008 4 AW43
02-21-4-Q 631-13-010 4 AW43
03-D-1-W 587-21-002 4 AW43
03-D-2-W 587-21-001 4 AW43
30 APR 17 to 25 MAY 17
09 APR 17 to 06 MAY 17 09 APR 17 to 06 MAY 17
19 MAR 17 to 14 APR 17 19 MAR 17 to 14 APR 17
M O
BILIZE &
SETUP
16 FEB 17 TO
25 FEB 17
26 FEB 17 to 14 MAR 17 26 FEB 17 to 14 MAR 17
26 FEB 17 to 21 MAR 17 26 FEB 17 to 21 MAR 17
26 FEB 17 to 21 MAR 17 26 FEB 17 to 21 MAR 17
19 MAR 17 to 14 APR 17
09 APR 17 to 28 APR 17 09 APR 17 to 28 APR 17
21 MAY 17 to 17 JUN 17 21 MAY 17 to 17 JUN 17 21 MAY 17 to 17 JUN 17
30 APR 17 to 24 MAY 17 09 APR 17 to 06 MAY 17
30 APR 17 to 01 JUN 17 30 APR 17 to 01 JUN 17
14 MAY 17 to 08 JUN 17 14 MAY 17 to 08 JUN 17
21 MAY 17 to 17 JUN 17
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 077-01-001
COAR: 16 PCN: PM01-Q064
SWT FILE NO: 077-001 CMP: NONE
REVISED: 23 Jan 2015 PLANNER: VARNEY , ROBERT
FERREIRA, SHANE
SSP: NWRMC-502-16 1 of 5 ITEM NO: 077-01-001
1. SCOPE:
1.1 Title: Hazardous Waste Produced on Naval Vessels; control
1.2 Location of Work:
1.2.1 Bremerton Naval Complex (BNC)
1.2.2 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 42 U.S.C. 6901, Resource Conservation and Recovery Act (RCRA)
2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act
2.3 10 U.S.C. 7311, Repair or Maintenance of Naval Vessels; Handling of Hazardous Waste
2.4 099-04NW, General Contractor Hazardous Waste Requirements for Bremerton Naval Complex (BNC)
2.5 099-08NW, Forms
3. REQUIREMENTS:
3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with the requirements of 2.1 through 2.5.
3.1.1 When a Navy generator number is required by this Work Item, submit the original hazardous waste manifest form to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.
3.1.2 Manage and transport for Navy disposal, Navy-generated
hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.
3.1.3 Submit one legible copy, in approved transferrable media, of hazardous waste manifest form signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.
3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.3.
3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor shall obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.
SSP: NWRMC-502-16 2 of 5 ITEM NO: 077-01-001
3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law.
Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator number issued to the contractor.
3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste shall bear a generator identification number issued to the contractor and shall also cite in the remarks block a generator identification number issued to the Navy. The contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor shall obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Manifests prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.
3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.
3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.
3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:
AMOUNT
TYPE NAVY CO-GENERATED CONTRACTOR
Acid Solutions (may include N/A N/A N/A spent sulfamic, citric, SSP: NWRMC-502-16 3 of 5 ITEM NO: 077-01-001 chromic, nitric, sulfuric, hydrochloric, etc.)
Ethylene Glycol (Antifreeze) N/A N/A N/A
Sodium Hydroxide N/A N/A N/A
Cleaning Solvents N/A N/A 47 Gallons
Sodium Phosphates (Tri, Bi, N/A N/A N/A or Mono)
Fluorocarbons N/A N/A N/A
Morpholine N/A N/A N/A
Sodium Chromates N/A N/A N/A
Hydrazine N/A N/A N/A
Carbohydrazide N/A N/A N/A
Methyl Ethyl Ketone N/A N/A N/A
Spent Abrasive Blast Material N/A N/A 28 TONS
(contaminated with a known hazardous waste)
Trichloroethane N/A N/A N/A
Miscellaneous Chemicals N/A N/A N/A
(Ignitable)
Miscellaneous Chemicals N/A N/A N/A
(Corrosive)
Miscellaneous Chemicals N/A N/A N/A
(TCLP Toxic)
Miscellaneous Chemicals N/A N/A N/A
(Reactive)
Oil (Synthetic) N/A N/A N/A
Paints (Enamel, Latex, N/A N/A 120 Gallons
Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes)
Paints (May include lead, N/A N/A N/A cadmium, or chrome)
Paint Strippers (phenols, N/A N/A N/A lead, chromium)
Sludge (Contaminated with N/A N/A N/A a known hazardous waste)
SSP: NWRMC-502-16 4 of 5 ITEM NO: 077-01-001
Wool Felt (contaminated N/A N/A N/A with chromium and PCB's)
Ventilation debris/residue
(heavy metals, e.g., cadmium, chromium) N/A N/A 90 LBS
Solvent Soaked Rags N/A N/A 135 LBS
3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.
3.7 Submit one legible copy, in approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the
SUPERVISOR.
3.7.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.
3.7.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assurance programs.
3.7.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.
3.8 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.
4. NOTES:
4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to Paragraph (b) of 2.3. The contractor is expected to use best management practice to identify and dispose of all hazardous waste. Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of 2.1. Inclusion of these substances in the waste listed in
3.5 does not preclude the contractor from taking action consistent with
2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.
Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.
4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.3. They are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.
4.2 Hazardous wastes are determined by one or more of the following methods:
SSP: NWRMC-502-16 5 of 5 ITEM NO: 077-01-001
4.2.1 Chemical analysis which shows that the material
characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.
4.2.2 Reference to a Material Safety Data Sheet (MSDS).
4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.
4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West Coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 587-21-001
COAR: 16 PCN: VB02-Q003
CMP: NONE
PLANNER: KONKLER, SHAWN
SSP: NWRMC-502-16 1 of 2 ITEM NO: 587-21-001
1. SCOPE:
1.1 Title: Water Brake Tank Catapult Number 2, preserve
1.2 Location of Work:
1.2.1 Water Brake Tank Number 2, (03-D-2-W), including Vent Dampers
1.2.2 Water Brake Tank Number 2 Trough
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 123-6398099 Rev U, Manholes & Handholes (Non-Ballistic Lists & Orders)
2.3 123-4400940 Rev H, AT & NT Manholes - Bolted Cover -
2.4 525-4403618 Rev L, Brake Water Tanks Cat 1 & 2
2.5 525-4403620 Rev K, Brake Water Tank Vent Cat #1 & 2
2.6 525-4403622 Rev N, Vent Dampers for Brake Water Tanks
2.7 110-4322227 Rev D, Trough End Closure Pl Fwd End Cat #1, 2, 3, & 4
2.8 525-5941539 Rev D, Protection for Brake Water Tank Piping CAT #1 & 2
2.9 110-5941534 Rev T, Trough Sides, Webs, Girders and Decks Cat #2
2.10 099-10W, Maintaining Protection and Cleanliness from Non- Radioactive Operations; accomplish
3. REQUIREMENTS:
3.1 Remove Manhole cover for the Water Brake Tank Catapult Number 2 listed in 1.2.1, using 2.2 and 2.3 for guidance.
3.2 Accomplish the requirements of 2.10.
3.3 Accomplish the requirements of 009-32 of 2.1 including Table 4, Line 21, Column A for the Water Brake Tank Catapult Number 2 listed in 1.2.1, including the interior surfaces of the manhole cover.
(V)(G) "VISUAL INSPECTION"
3.4 Accomplish a joint visual inspection with the SUPERVISOR of the tank listed in 1.2.1, for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, and to determine required repair, using 2.4 through 2.7 for guidance.
3.4.1 Submit one legible copy, in hard copy or electronic media, of a report listing the results of the conditions found in 3.4 to the
SUPERVISOR.
3.5 In addition to the requirements of 009-06 of 2.1., accomplish the blanking/protection of critical equipment and machined surfaces as follows:
SSP: NWRMC-502-16 2 of 2 ITEM NO: 587-21-001
3.5.1 Catapult Vent dampers (blank), Catapult Buttress Plate
(critical machined surface and bolt holes - 1.25-12UNJF-2A), Trough cover upper and lower support rails (all surfaces and holes 5/8- 11UNC-3A),fwd portable trough cover rails, Power cylinders 15 feet from trough end closure plate aft (Protect inside and outside), Water brake cylinder support base plates (all surfaces and clamps), any exposed power cylinder support base plates (all surfaces and clamps), Catapult retraction cable (wrap), Catapult seal strip (recommend protection with 1-1/2 inch ID PVC pipe), In upper rails (insert bolts into barrel nuts and mask off all holes), and two forward access hatches below buttress plate. Remove blanking/protection upon completion of all work. Utilize 2.8 and 2.9 for guidance.
(V)(G) "PROTECTION INSPECTION"
3.6 Due to the critical tolerances and alignment accomplish an inspection of protection prior to start of blasting operation. Inspection shall be conducted by the Contractor, SUPERVISOR, Carrier and Field Services Unit (CAFSU), and those parties deemed necessary by the
SUPERVISOR.
3.6.1 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.6 to the
SUPERVISOR.
3.7 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line 21, Column B for the Water Brake Tank Catapult Number 2 listed in 1.2.1.
3.8 Install manhole cover removed in 3.1, using new gaskets and fasteners conforming to 2.3.
3.8.1 Chase and tap exposed threaded areas.
3.9 Accomplish the requirements of 009-32 of 2.1 for the new and disturbed surfaces.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 587-21-002
COAR: 16 PCN: VB01-Q007
CMP: NONE
PLANNER: KONKLER, SHAWN
SSP: NWRMC-502-16 1 of 2 ITEM NO: 587-21-002
1. SCOPE:
1.1 Title: Water Brake Tank Catapult Number 1, preserve
1.2 Location of Work:
1.2.1 Water Brake Tank Number 1, (03-D-1-W), including Vent Dampers
1.2.2 Water Brake Tank Number 1 Trough
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 123-6398099 Rev U, Manholes & Handholes (Non-Ballistic Lists & Orders)
2.3 123-4400940 Rev H, AT & NT Manholes - Bolted Cover -
2.4 525-4403618 Rev L, Brake Water Tanks Cat 1 & 2
2.5 525-4403620 Rev K, Brake Water Tank Vent Cat #1 & 2
2.6 525-4403622 Rev N, Vent Dampers for Brake Water Tanks
2.7 110-4322227 Rev D, Trough End Closure Pl Fwd End Cat #1, 2, 3, & 4
2.8 525-5941539 Rev D, Protection for Brake Water Tank Piping CAT #1 & 2
2.9 110-5941533 Rev T, Trough Sides, Webs, Girders and Decks Cat #1
2.10 099-10W, Maintaining Protection and Cleanliness from Non- Radioactive Operations; accomplish
3. REQUIREMENTS:
3.1 Remove Manhole cover for the Water Brake Tank Catapult Number 1 listed in 1.2.1, using 2.2 and 2.3 for guidance.
3.2 Accomplish the requirements of 2.10.
3.3 Accomplish the requirements of 009-32 of 2.1 including Table 4, Line 21, Column A for the Water Brake Tank Catapult Number 1 listed in 1.2.1, including the interior surfaces of the manhole cover.
(V)(G) "VISUAL INSPECTION"
3.4 Accomplish a joint visual inspection with the SUPERVISOR of the tank listed in 1.2.1, for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, and to determine required repair, using 2.4 through 2.7 for guidance.
3.4.1 Submit one legible copy, in hard copy or electronic media, of a report listing the results of the conditions found in 3.4 to the
SUPERVISOR.
3.5 In addition to the requirements of 009-06 of 2.1., accomplish the blanking/protection of critical equipment and machined surfaces as follows:
SSP: NWRMC-502-16 2 of 2 ITEM NO: 587-21-002
3.5.1 Catapult Vent dampers (blank), Catapult Buttress Plate
(critical machined surface and bolt holes - 1.25-12UNJF-2A), Trough cover upper and lower support rails (all surfaces and holes 5/8- 11UNC-3A),fwd portable trough cover rails, Power cylinders 15 feet from trough end closure plate aft (Protect inside and outside), Water brake cylinder support base plates (all surfaces and clamps), any exposed power cylinder support base plates (all surfaces and clamps), Catapult retraction cable (wrap), Catapult seal strip (recommend protection with 1-1/2 inch ID PVC pipe), In upper rails (insert bolts into barrel nuts and mask off all holes), and two forward access hatches below buttress plate. Remove blanking/protection upon completion of all work. Utilize 2.8 and 2.9 for guidance.
(V)(G) "PROTECTION INSPECTION"
3.6 Due to the critical tolerances and alignment accomplish an inspection of protection prior to start of blasting operation. Inspection shall be conducted by the Contractor, SUPERVISOR, Carrier and Field Services Unit (CAFSU), and those parties deemed necessary by the
SUPERVISOR.
3.6.1 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.6 to the
SUPERVISOR.
3.7 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line 21, Column B for the Water Brake Tank Catapult Number 2 listed in 1.2.1.
3.8 Install manhole cover removed in 3.1, using new gaskets and fasteners conforming to 2.3.
3.8.1 Chase and tap exposed threaded areas.
3.9 Accomplish the requirements of 009-32 of 2.1 for the new and disturbed surfaces.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 631-13-002
COAR: 16 PCN: VB03-XA12
CMP: NONE
PLANNER: VARNEY , ROBERT
ARCHUT ,
CHRISTOPHER
SSP: NWRMC-502-16 1 of 2 ITEM NO: 631-13-002
1. SCOPE:
1.1 Title: Catapult No. 3 Wing Voids Preservation; accomplish
1.2 Location of Work:
1.2.1 Catapult No. 3 Wing Voids, FR 74-155, inboard
1.3 Identification:
1.3.1 None.
2. REFERENCES:
2.1 Standard Items
2.2 122-7481761 Rev -, Cat Trough 1-4 Void Cover Replacement
2.3 124-7481762 Rev -, Catapult Trough Cover Manufacturing Details
2.4 116-5941535 Rev R, Aircraft Carrier CVN 72/73 Trough Sides, Webs, Girders & Decks - CAT #3
2.5 099-10NW, Maintaining Protection and Cleanliness from Non- Radioactive Operations; accomplish
3. REQUIREMENTS:
3.1 Remove manhole cover plates from the wing voids listed in 1.2.1.
3.1.1 Accomplish the requirements of 2.5.
3.2 Accomplish the requirements of 009-32 of 2.1, including Table 5, Line 28, Column A, for the voids listed in 1.2.1.
(V)(G) "VISUAL INSPECTION"
3.3 Accomplish a joint visual inspection with the SUPERVISOR of the void listed in 1.2.1, for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including piping and hangers, structural members, and manhole covers using 2.2 through 2.4 for guidance.
3.3.1 Submit one legible copy, in transferable media, of a report listing results of the requirements of 3.3 to the SUPERVISOR.
3.4 Accomplish the requirements of 009-32 of 2.1, including Table 5, Line 28, Column B, C, and D for the voids listed in 1.2.1, including framing, piping and hangers, and the interior side of manhole covers.
3.5 Install manhole cover plate removed in 3.1, using new gaskets and fasteners conforming to 2.2 and 2.3.
3.5.1 Chase and tap exposed threaded areas.
4. NOTES:
4.1 None.
SSP: NWRMC-502-16 2 of 2 ITEM NO: 631-13-002
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: USS JOHN C. STENNIS (CVN 74) ITEM NO: 631-13-005
COAR: 16 PCN: RX40-Q001
CMP: NONE
PLANNER: VARNEY , ROBERT
ARCHUT ,
CHRISTOPHER
SSP: NWRMC-502-16 1 of 2 ITEM NO: 631-13-005
1. SCOPE:
1.1 Title: Vent Inlet 01-156-3-Q; preserve
1.2 Location of Work:
1.2.1 Vent Inlet (01-156-3-Q)
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 123-4322592 Rev AF, Manholes & Handholes in Vent Trunks & Fdn List & Orders
2.3 123-4400940 Rev P, AT & NT Manholes-Bolted Cover
2.4 501-6669023 Rev B, Vent Plenums Inlets & Outlets MN-Gallery DK FR 148-170 (S)
2.5 100-5756376 Rev L, Upper Side Shell PLTG & Stringers MN-GAL DK FR 151-181 STBD Superlift 4427A
2.6 108-5756380 Rev…
This is the start of the file's text. The full file is on GovTribe.