N4891518RCBA097

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

USS GLADIATOR SRA - RFP No. N4033918RF014- P0003

A) The purpose of this amendment is to provide the Government responses to the Questions received from the industry for the USS

GLADIATOR SRA repairs.

B) The proposal submission date is extended from 10 May 2018 at (09:00AM) to 15 May 2018 at (10:00AM) Bahrain Local Time.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-May-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4033918RF014

X 9B. DATED (SEE ITEM 11)

25-Apr-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-May-2018

CODE

NAVSUP FLC BAHRAIN CODE 200

PSC 851 BOX 430

FPO AE 09834-0005

N40339 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4033918RF014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Work

Item/

Description

QUESTION/CLARIFICATION GOVERNMENT’s

RESPONSE/ANSWER

GENERAL

- Force protection layout Diagram, total shipyard workload manning curves and Production schedule shall be submitted upon award of contract.

- This must be submitted upon Contract Award.

042-00-003: Work

Completion Certification;

accomplish.

- Paragraph 3.1: Assume that the Contractors will not develop an Event Readiness List for others work (AIT, SF, CIS, FMA), as they are not directly under the Contractor's control. Assume that they will be dealt directly by FDRMC. Please confirm.

- The Government concurs that the contractor is

Not Responsible to develop and event Redniess

List for others work(AIT,SF,CIF,FMA)

- Correcting this specfication errata.

110-11-001:

Limber Chain; repair.

- Paragraph 3.2: Please advise if the new limber chain, limber chain handle and springs will be GFM, as these were provided as GFM in all the past availabilities. If CFM, then please provide the Manufacturer / Supplier contact details and address, as it is not provided in the given reference drawings and these parts are not available locally.

- Material shall be provided by contractor furnished material and ordered by contractor.

- Materials Required shall be local Available. - Material shall be provided by contractor furnished material and ordered by contractor.

130-11-001: Exterior Wood

Repair Accomplish.

- Paragraph 1.3.1: Contractor price will be for tender purpose only, POP-subject to exact repair quantity determination and CFR.

- Contractor shall proposal to reflect the requirements of the Spec.

130-11-002: Overhead

Repairs; accomplish

- Ref 2.9: Received Rev B drawing. Please provide Rev F drawing.

- This is a typographical error, please see errata correct revision.

- Paragraph 3.1: Accomplish Main Mast Stage. - Question does not reflect work item.

-Paragraph 3.7: Please note that the requirements of 009-

32 of 2.1, including Table 2, Line 67, do not exist in NAVSEA Standard Items (FY -19 Change 2). Please advise.

- The contractor shall use Standard Items FY 19

CH-1.

171-11-001: Main Mast, Stage, Repair and Preserve.

- Paragraph 3.1.1: Please note that the requirements of

009-32 of 2.1, including Table 2, Line 67, do not exist in NAVSEA Standard Items (FY -19 Change 2). Please advise.

- The contractor shall use Standard Items FY 19

CH-1.

233-11-001: Main Propulsion

Diesel Engine (MPDE)

Jacket Water Coolers; Clean and Test.

-Paragraph 3.3.5: Please note that the requirements of

Paragraph 220-41.2 do not exist in Ref 2.5. Please advise.

- Please see errata for reference 2.5 TO 2.6.

- Paragraph 3.7.1: Please note that the quantity and purity requirements of Mineralized water could not be found in

Section 42 of Ref 2.6. Please advise.

- Please See 220-42.1 para C of reference 2.6.

233-11-002: No. 2A Main

Propulsion Diesel Engine

(MPDE) Vibracon Mount;

replace.

- Paragraph 3.3: Please advice if the holes to weld, fill and re-drill is for the engine mounting brackets or the engine foundation girder plate. If it is for engine mounting brackets then please advise the material specification of the engine mounting brackets.

- Weld fill and drill is for the Engine Mounting

Rails.

- Paragraph 3.3: Weld, Fill, Re-drill in accordance with

Paragraph 2.2 Reference S9233-B9-MMM-010 is for engine Rail or Foundation?

- Weld fill and drill is for the Engine Mounting

Rails.

233-11-003: Main Reduction

Gear (MRG to Main

Propulsion Diesel Engine

(MPDE) Alignment;

accomplish

- Paragraph 3.2.1: We assume that the new labyrinth gasket is GFM (Para 5.1.3 - Oil Guard), as per ship check. Please confirm.

- Oil Guard and Labyrinth seal are the same.

241-11-001: Main Propulsion

Diesel Engine and Reduction

Gear Resilient Mounts;

Replace.

- Ref 2.7: Received Rev A drawing. Please provide Rev

B drawing.

- This is a typographical error please see errata

- Paragraph 3.3: Please advice the duration of the holes to weld, fill and re-drill is for the raft plate or the girder plate.

- Comply with spec as written.

252-11-001: MCM-11 SCD

89081/86374 Alteration

Installation Team (AIT)

Industrial Support Service;

provide.

- Paragraph 3.9 & 3.10: Please advise the duration of the temporary services and compressed air services required.

- The temporary services shall be provided.

- Paragraph 3.11: Please advice the quantity and specification of industrial waste to dispose.

- Paragraph refers to trade litter left by AIT

Contractor to bid worst case scenario.

Paragraph 3.9 Temporary Services, to be provided for entire availability?

- The temporary services shall be provided.

256-11-001: Auxiliary

Seawater Cooling Pumping

Unit, overhaul.

- Paragraph 3.1: Assume that the requirement of 009-09 for the installation of Cofferdams will not be required, if the diving services and cofferdam installation/removal will be done by U.S. Navy divers. Please confirm.

- The Navy Divers shall install Cofferdams.

Paragraph 3.1: Coffer dam installation Diving services to be provided by GFM. - The Navy Divers shall install Cofferdams.

- Paragraph 3.2: Assume that the requirement of

009-77 for providing the diving services and supply

/ install / maintain /removal of cofferdams will be done by U.S. Navy divers. Please confirm.

- The Navy Divers shall install Cofferdams.

- Paragraph 3.5: We will allow to inspect the pump shaft and submit a CFR only. Upon determination and CFR.

Assume that any weld build-up required will be covered under a change order or RCC, as the actual required weld build-up is unknown at the moment. Please confirm. Also note that dimensional sketch and material specification of the pump shaft are not given in Ref 2.2.

- Any repairs found shall be submitted by contractor via condition found report (CFR).

264-30-001: Main Reduction

Gear (MRG) and

Controllable Pitch Propeller

(CPP) Lube Oil Polisher

Heater; inspect and clean.

- Paragraph 3.3.1: Please note that the new gasket and O-ring were provided as GFM in all the past availabilities, as these are OEM parts and not available locally.

- Any Material.

- Paragraph 3.4: Please note that the MIL-PRF-900 specification is for the rubber gasket material. We will allow to provide the oil locally available (see attached lube oil specification). Please confirm or provide specification of equivalent oil locally available.

- Any Material.

321-11-001: 2Sp Shore

Power cable; Replace.

- Paragraph 3.2.3: We assume that the tool set will be provided as GFM, as this is a specialized tool and is not available locally. Please confirm.

- Any Material and tools.

- Provide Reference 2.2 to 2.8.

- The reference was provided on amendment 02.

442-11-001: AN/WQC-2

Sonar Communication Set

Transducer; Replace.

- Paragraph 3.1: We assume that the U.S. Navy divers will remove the existing and install the new transducer underwater. Please confirm.

- The Navy Divers will provide assistance.

- Provide References 2.2 to 2.5.

- Waterborne Sonar Transducer Replacement

Procedure. See WQC-2 in the Tech Man.

- Paragraph 3.1: Please note that the requirement of 009-77 is not mentioned in the work item specification. We assume that any requirement of diving services and supply / install / maintain /removal of cofferdams will be done by U.S. Navy divers. Please confirm.

- The Cofferdam is not Required.

- Paragraph 3.1.4: We assume that the new fasteners and gaskets will be provided as GFM, as these are Mil Spec

Material and they should come together with the new Transducer (GFM). Please confirm. If CFM, then we will allow to provide locally available fasteners and gaskets, as these are special parts / Mil Spec parts that are not available locally. Please confirm.

- Fasteners and Gaskets will be provide as

Government Furnished Material,. See attached errata.

476-11-001: Vehicle

Handling System (VHS);

repair.

- Paragraph 1.3.2: We assume the rating of motors as 10/3.3

HP, as per ship check. Please confirm. This information is not available in the given reference 2.2 and 2.3.

- The contarctor shall Accomplish the requirements of paragraph in accordance with

3.1.3 to determine H.P. rating.

505-00-002: Silicon

Aluminum Bronze (SAB)

Union Fittings; inspect and

- Ref 2.2: Received Rev B drawing. Please provide Rev G

- Ref 2.4: Received Rev C drawing. Please provide Rev D

- Ref 2.5: Received Rev B drawing. Please provide Rev C

508-11-001: Machinery

Spaces and Non Machinery

Interior Spaces Lagging and Insulation; repair

NTE Labor: 80 Man Days

NTE Materials: $20,000.00

- Paragraph 3.1 & 3.2: We will allow to quote the allowances of man-hours and materials only, as per ship check. Please confirm.

- The contarctor shall propose for man-hours and materials only.

512-11-003: Ventilation Fan;

repair and test.

- Ref 2.2: Received Rev D drawing. Please provide Rev F

- Ref 2.5: Received Rev B drawing. Please provide Rev C

- Paragraph 1.3: We assume the rating of each motor as

1.75 HP, as per ship check. Please confirm. This

information is not available in the given reference 2.2.

- The HP rating will vary depending on size of motor and H.P. rating shall be determined upon disassembly.

- Paragraph 3.2 & 3.2.1: Please advise if we have to allow to carry out the requirements of 009-17 or 009-33.

- Both are applicable to motor repair.

514-11-001: Number One &

2 AC Condenser Retube;

- Paragraph 3.4: We will allow to reuse the existing support plates from each condensers, as per the ship check. Please

- Plates will be inspected to determine condition of plates. Replacement in needed shall be determined upon disassembly.

516-11-002: Number 2

Refrigeration Plant Valve;

- Paragraph 1.3.1: We assume that the size of the valve is

3/4 inch in lieu of 3/8 inch, as per ship check. Please

- The Govrnment Concur with contractor.

521-21-001: Fire Pump and

Motor; repair and test.

- Ref 2.5Received Rev 3 drawing. Please provide Rev 9

- Paragraph 3.5: Weld Build upon determination and CFR. - The Government Concur with contractor.

524-11-001: Sea Valves;

remove and replace.

- Paragraph 3.4 & 3.5: We will allow to pressure body test the new GFM valves prior to installation and hand over the existing removed valves to FDRMC, as per ship check.

Please confirm.

- The Government Concur with contractor.

Paragraph 3.4 & 3.5: Repair of each valve is for new valves? Or existing valves?

- The Repair is for New Valves.

524-11-001: Fire main Piping

System; clean and flush.

- Paragraph 3.4: We will allow to inspect the defective or leaking piping and submit a CFR only. Assume that any required repairs or replacement of piping, including fittings will be covered under a change order or RCC, as the actual required repairs or replacement is unknown at the moment.

524-11-003: Auxiliary Sea

Water Piping; clean and flush.

- Paragraph 3.5: We will allow to inspect the defective or required repairs or replacement of piping, including fittings will be covered under a change order or RCC, as the actual

526-11-001: Deck Drain and

Deck Penetration; repair.

- Paragraph 3.5.2: We will allow to inspect the deck drain piping and submit a CFR only. Assume that any required replacement of deck drain piping will be covered under a change order or RCC, as the actual required replacement is unknown at the moment. Please confirm.

533-11-001: Potable Water

Pump and Motor; overhaul.

and submit a CFR only. Assume that any weld build-up required will be covered under a change order or RCC, as the actual required weld build-up is unknown at the moment. Please confirm. Also note that dimensional sketch and material specification of the pump shaft are not given in Ref 2.2.

- Paragraph 3.5: Weld build up-upon determination and

CFR.

- The Government Concur with contractor.

551-11-001: Medium

Pressure Air Compressor

(MPAC); repair.

- Paragraph 3.4: We assume that there is no requirement of repairs to the equipment identified in 1.3.2, as per ship check. Please confirm.

Paragraph 3.4: Accomplish Repairs of equipment 1.3, for item listed in 1.3.2 doesn’t state for repair standard item-

009-17 or 009-33?

- Paragraph 3.4 changed to read: Accomplish repairs to the equipment listed in 1.3.1.

- Paragraph 3.4.6: We will allow to provide the oil locally available (see attached lube oil specification). Please confirm or provide specification of equivalent oil locally available.

- The Contractor shall provide lube oil equivalent to MIL-L-17331.

581-11-002: Anchor

Windlass; replace.

- Paragraph 3.4: Please advise if the requirements of 009-16

(Electronic Equipment; repairs) is applicable for the electrical repairs of the equipment listed in 1.3.1. If not, then please advise the correct NAVSEA Standard item.

- 009-16 shall be removed not applicable

583-11-001: Boat Davit:

repair and weight test;

- Paragraph 3.2: We will allow to repair the loosen bolt holes in the motor casing using Heli coils, in lieu of weld/fill/re-drill, as per ship check. Please confirm.

- The Government Concur with contractor.

593-11-001: Waste Water

Ejection Pump; overhaul.

and submit a CFR only. Assume that any weld build-up required will be covered under a change order or RCC, as the actual required weld build-up is unknown at the moment. Please confirm. Also note that dimensional sketch and material specification of the pump shaft are not given in

Ref 2.2 & 2.4.

- The Governemnt Concur with contractor. The material shall be determined upon disassembly.

593-11-002: CHT Piping

System Chemical Cleaning;

- Paragraph 2.4: Received Rev C drawing. Please provide Rev F drawing.

- Paragraph 3.6: We will allow to inspect the defective or required repairs or replacement of piping, including fittings will be covered under a change order or RCC, as the actual

- Paragraph 3.6: Replacement of piping –upon determination and CFR.

- The Government Concur with contractor.

622-11-001: GRP Deck Plate, Replace.

- Provide Reference 2.2 (622-6645230 & 6226645231). - Drawings is provided in CD.

622-11-002: PVC Pipe

Connector, Fabricate and

Install.

- Provide Reference 2.2 (622-6645230). - Drawings is provided in CD.

624-1-001: Joiner Door, Repair.

- Contractor to accomplish repair? Ship check it is informed the jobs are completed in CMAV1.

- Contractor to proposal on Repair. If job is completed prior to CNO job will be de-scoped from work package.

624-11-002: Fume tight

Joiner Door; repair.

- Paragraph 3.3.2: We will allow to inspect the missing and defective components and submit a CFR only. Assume that any required replacement of missing or defective components will be covered under a change order or RCC, as the actual required missing or defective components for replacement is unknown at the moment. Please confirm.

631-11-001: Superstructure;

preserve.

- Paragraph 3.4: Please note that the requirements of 009-32 of 2.1, including Table 2, Line 69, do not exist in NAVSEA Standard Items (FY -19 Change 2). Please advise.

- Use Standard Items FY 19 CH-1.

- Paint shall be equivalent and local available. - Concur with contractor.

631-11-002: Bilge; preserve.

- Paragraph 3.3: Please note that the requirements of 009-32 of 2.1, including Table 3, Line 59, do not exist in NAVSEA

- The contractor shall Use Standard Items FY 19

CH-1

- Paint shall be equivalent and local available. - The Government Concur with contractor.

631-41-001: Freeboard;

preserve.

- Paragraph 3.1: Please note that the requirements of 009-32 of 2.1, including Table 2, Line 66, do not exist in NAVSEA

- The contrcator shall Use Standard Items FY 19

CH-1

- Paint shall be equivalent and local available. - The Government Concur with contractor.

631-11-002: Nonskid;

- Paragraph 3.3: Please note that the requirements of 009-32 of 2.1, including Table 2, Line 67, do not exist in NAVSEA

- The contarctor shall Use Standard Items FY 19

- Paragraph 3.10: Please note that the requirements of 009-

32 of 2.1, including Table 2, Line 67, do not exist in NAVSEA Standard Items (FY -19 Change 2). Please advise.

634-11-003: Decking; repair.

- Paragraph 3.2: Please note that the requirements of 009-32 of 2.1, including Table 3, Line 59, do not exist in NAVSEA

- Paragraph 3.1: Provide attachment C. - Please see NSI 009-26 as saved in to the provided

CD.

- Paragraph 3.1.1: Please provide attachment A. - Please see NSI 009-26 as saved in to the provided

CD.

634-11-004: Electrical Grade

Mating Replace

- Paragraph 3.2: Provide attachment D. - Please see NSI 009-26 as saved in to the provided

CD.

641-11-001: Crew Head

Counter Top; replace.

- Paragraph 3.1: We will allow to renew the Formica lamination only on the existing sink counter top and back splash, as per ship check. Please confirm.

- Please provide Reference 2.2 (644-6645261). - Drawings will be provided in CD.

642-11-001: Watch Chair;

repair.

- Paragraph 3.2: We will allow to renew the upholstery of the equipment identified in 1.3, as per ship check. Please

- Paragraph 3.2: Repairs of upholstery will be considered in

Tender, any chair structural repairs shall be upon determination and CFR.

897-11-001: Availability

Program Management AIT

Integrator; provide.

- Paragraph 3.1: Assume that the prime Contractors will coordinate, integrate and de-conflict all maintenance and modernization activity schedule for prime contractor and their direct sub-contractors work schedule only. For all others work carried out by I Level, AITs, SF, CIS, FMA) the prime contractor is not responsible, as they are not directly under the prime Contractor's control. Assume that they will be dealt directly by FDRMC. Please confirm.

980-11-001: Alteration

Installation Team (AIT)

Support Services (SA70392K

BOW THRUSTER MODS);

- Paragraph 3.9: Please advise the USD Allowance for the welding consumables in order to provide the welder services.

- Concur with contractor to propsol worst case scenario.

980-11-002: Assist Ship's

Force; provide.

- Paragraph 3.3.2: Please re-write this paragraph to delete

"to document lift services provided to the supervisor".

- The stateemnt of work is hereby corrected please see errata.

992-11-002: Temporary

Service Provide

- Paragraph 3.17.1: Protective coverings following spaces to be listed.

- The stateemnt of work is hereby corrected please see errata.

992-21-001: Small Boat

Storage and Repair Facility;

- Paragraph 3.1.2: We assume that the climate control equipment is not required, as we will allow to provide a shaded and well ventilated small boat storage facility.

- The stateemnt of work is hereby corrected please see errata.

992-31-001: Cleaning and

Pumping; accomplish.

- Ref 2.3: Please confirm if the required reference is CH-

541 or CH-542. We have received CH-542 only.

- S9086-SP-STM-010/CH-542, Ship's Fuel and

Fuel Systems is correct STM, corrected on errata.

- Paragraph 3.5.2: We assume that the off-loaded Navy fuel, contaminated oil and lubricating oil will be disposed, as per ship check. Please confirm.

- The Government Concur with contractor.

- Paragraph 3.10.1.1: Chemical analysis, Total quantity of samples, parameters of analysis required.

- This paragraphs do not apply to MCM Class ships, please see errata.

- Paragraph 3.6: Assume that the new Navy fuel and miscellaneous petroleum products will be GFM. Please

- Fuel for the ship shall be Government furnished material all other petroleum products to be

Contractor furnished material.

- Paragraph 3.10.1: Please advise the total quantity of each sample to allow for chemical analysis.

- Paragraph 3.15: We assume that the requirement of this paragraph is not applicable, as per ship check. Please

993-11-001: Alteration

Installation Team (AIT)

Support Services (SA70392K

BOW THRUSTER MODS);

- Paragraph 3.3.1: Forklift: We will allow to provide a total of 25 lifts for the AIT team during the availability. Please

- Comply with spec as written in errata.

- Paragraph 3.3.4: Painting: We assume that the AIT will provide all materials for painting (as per para 4.7). Please

991-12-001: Temporary

Staging for Ship's Force Use;

install.

- Paragraph 3.2.1: We assume that the staging to be installed within first 5 days of availability and not docking.

992-00-001: Force

Protection; provide.

- Paragraph 3.7: Please note that we will provide a separate quote for per week for each increase in FPCON, in our notes and clarifications with the final submission of our quotation. Please confirm.

992-11-002: Temporary

Service; provide.

- Paragraph 3.2: Please correct the typo error "3.2" to as

"3.3".

- Paragraph 3.23.5: Please note that it is not possible to provide 30 liters per second chill water at 4.5 degrees

Celsius. As per the past experience on previous availabilities, we can provide 10-13 liters per second chill water at 6 degree Celsius. Please confirm.

- Accomplish requirements of spec as written.

- Paragraph 3.23-.5.1: Please correct the typo error "3.22.5" to as "3.23.5".

982-31-003: Dock Trials, Fast Cruise and Sea Trial;

accomplish.

- Paragraph 4.2: Please advise if the crane services will be provided by U.S. Navy or Contractors.

042-00-002: Continuation of

Temporary Services; provide

(First Option) (15 Days

Extension).

- Paragraph 4.2: Please correct the typo error in the work item number "992-11-003" to read as "857-11-002".

- Paragraph 3.1.4: Please note that we do not have the work specification for work item no. 992-11-005 "Government

Representatives and Ship's Force Office and Parking Space;

provide". Please advise.

- Paragraph 3.1.5: Please note that we do not have the work specification for work item no. 992-11-005 "Government Representatives and Ship's Force Office and Parking Space;

provide". Please advise.

- Paragraph 3.1.5: Listed work item, work scope to be provided.

- The stateemnt of work is hereby corrected please see errata.

- Paragraph 3.1.6: Please correct the typo error in the work item number "992-11-007" to read as "992-00-001".

- Paragraph 3.1.7: Please correct the typo error in the work item number "993-11-001" to read as "993-31-001".

Typographical error for work item number on paragraph

3.1.2, 3.1.3, 3.1.4, 3.1.6 and 3.1.7.

- The stateemnt of work is hereby corrected please see errata.

311-22-001 Para 3.4.1: Typo Error - The stateemnt of work is hereby corrected please

311-22-001: Ship Service

Diesel Generator (SSDG);

clean, repair and test

(Option).

- Paragraph 3.4.1: Please correct the typo error "3.5" to as

"3.4".

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 08-May-2018 01:00 PM to 15-May-2018 10:00 AM.

(End of Summary of Changes)