Attachment_4_-_Status_Report_Requirements.pdf

PDF 141 KB Posted

Attached to
Touch Labor Support IDIQ Federal contract opportunity
Solicitation number
N39040-16-R-0001
Issued by
Department of the Navy Naval Sea Systems Command

About this file

Attachment 4 Status Report Requirements

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N39040-16-R-0001 Attachment 4

STATUS REPORT REQUIREMENTS

1. The monthly status report shall include the listed items:

* Project/Task number

* Task status

* Man-hour information (Include Labor Category, Hours expended for the period, and the cumulative total

* Funded Amount/Total estimated Cost

* Funds Expended To-Date

* Percentage of Funded Amount Spent To-Date

* Percentage of Completion To-Date

* Scheduled Completion Date

* Estimated Completion Date

* Remarks, including any disconnects between scheduled completion date, estimated completion date, and funds expended to date.

2. The format of the report shall be to the contractor’s discretion but shall include a graphical representation of the contractor’s progress. An X-Y graph shall be used with the X axis representing time and the Y axis representing man-hours. The contractor shall plot the estimated/projected values and the actual values on one graph. Ensure that there is a date, title, and Project/Task number on the graph.