Q&A__6_Answer.docx
DOCX document 28 KB Posted
- Attached to
- USNS GRASP ROH/DD Federal contract opportunity
- Solicitation number
- N3220518R4555
About this file
Q&A #6
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment.docx | DOCX document | |
| Extension_Request_Answer.docx | DOCX document | |
| QA__5_Answers.docx | DOCX document | |
| J_-_2_Category_A_Item_Revised.xlsx | XLSX spreadsheet | |
| Amendment_3.docx | DOCX document | |
| J-3_Category_B_Item_Revised.xlsx | XLSX spreadsheet | |
| QA__4_Answers.docx | DOCX document | |
| Amendment_0002.docx | DOCX document | |
| Q&A__2_Answer.rtf | RTF text file | |
| QA__3_Answer.doc.rtf | RTF text file | |
| Q&A__1_PPE_Answer.rtf | RTF text file | |
| Amendment0001.docx | DOCX document | |
| J&A_Redacted.pdf | ||
| J-Attachments.zip | ZIP file | |
| N3220518R4555_SOLICITATION.docx | DOCX document | |
| SYNOPSIS_N3220518R4555.docx | DOCX document |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220518R4555
USNS GRASP (T-ARS 51) ROH/DD
REQUEST FOR SPECIFICATION CLARIFICATION
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: ___909A and 915B_____________________________
PARAGRAPH / SECTION NO:__All_____________________________________
TITLE: _909A Propulsion System Inspection and Maintenance and 915B Propulsion System Overhaul ______________________________________
QUESTION:
909A Propulsion System Inspection and Maintenance and 915B Propulsion System Overhaul appears to have the same scope of work stated to be accomplished.
Please identify which work item we should price to eliminate redundancies within our pricing submittal.
ANSWER:
Work Item 0909 is to be accomplished without removing shafts and disassembling the CPP hub. Work Item 0915 is a complete removal, disassembly and overhaul of CPP and Shafts. Please refer to Section 7.0 of both Work Items for comparison. Completion of Section 7.7.1 of Work Item 0909, will determine if Work Item 0915 will be activated. If Work Item 0915 is activated, the remainder of Work Item 0909 covered by Work Item 0915 will be descoped. Please review section 7.0 of both work items to determine required manpower to accomplish each work item independently accordingly. For clearification of shaft removals, Work Item 0915 Section 7.3.1 has been added.
ATTACHMENT J - 8