MILITARY SEALIFT COMMAND
N32205-18-R-4150
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
1. Specification Item No. 427 - Please provide actual list of CFM, as 2.1.4 list several tabs on bottom of sheet and when you lool at them most do not give unit of measure or type, GRD etc, and item list no GFM but Ref has separate tab for GFM, will any GFM be provided. The way all the material lists that re provided like this one and on a few other items is confusing on who will be providing what material and or what type or unit or measure should be provided. Please clarify all items that have this type of material listing provided with item.
ANSWER:
WI 427 and reference 2.1.4 have been revised to reflect installing activity furnished material requirements. WI 427 reflects that no GFM will be provided.
2. Specification Item No. 427 - Is the material listed in reference 2.1.4, drawing 032-8452118, to be provided as GFM?
ANSWER:
See response to question No.
3. Specification item 524 – Paragraph 5.2.3 states reference 2.1.14 install cable supports for accomplishment of this work item. Since item 355 has been cancelled, are these cable supports now installed in item 524?
ANSWER:
WI 524 has been revised to delete Paragraph 5.2.3 and Reference 2.1.1.