N32205-18-R-4150_Conformed_Solicitation.docm

DOCM document 144 KB Posted

Attached to
USNS HERSHEL WILLIAMS (T-ESB 4) PSA Federal contract opportunity
Solicitation number
N32205-18-R-4150
Issued by
Department of the Navy Military Sealift Command

About this file

Conformed Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to USNS HERSHEL WILLIAMS (T-ESB 4) PSA, newest first.
File Type Posted
RFP_QandA__18_Solicitation_N32205-18-R-4150.docx DOCX document
Conform_Document.docx DOCX document
N32205-18-R-4150_P00007.docx DOCX document
N32205-18-R-4150_P00006.docx DOCX document
J_-_1_Work_Item_Package_-_18-R-4150.docx DOCX document
Conform_Document.docx DOCX document
J_-_2_Category_A_Items_-_8-R-4150.xlsx XLSX spreadsheet
J_-_3_Category_B_Items_-_18-R-4150.xls XLS spreadsheet
N32205-18-R-4150-0005.docx DOCX document
RFP_QandA__10_Solicitation_N32205-18-R-4150.docx DOCX document
RFP_QandA__11_Solicitation_N32205-18-R-4150.docx DOCX document
RFP_QandA__16_Solicitation_N32205-18-R-4150.docx DOCX document
RFP_QandA__15_Solicitation_N32205-18-R-4150.docx DOCX document
J_-_10_Interport_Differential_-_18-R-4150.doc DOC document
RFP_QandA__12_Solicitation_N32205-18-R-4150.docx DOCX document
N32205-18-R-4150-0004.docx DOCX document
RFP_QandA__9_Solicitation_N32205-18-R-4150.docx DOCX document
RFP_QandA__13_Solicitation_N32205-18-R-4150.docx DOCX document
RFP_QandA__14_Solicitation_N32205-18-R-4150.docx DOCX document
N32205-18-R-4150-0002.docx DOCX document
Amendment_0002.zip ZIP file
N32205-18-R-4150-0001.docx DOCX document
J_-_3_Category_B_Items_-_18-R-4150.xls XLS spreadsheet
J-6_CDRLs.zip ZIP file
N32205-18-R-4150.docx DOCX document
J_Attachments.zip ZIP file
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220518R4150

Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" Work Items (WIs)

FFP

Prepare for and accomplish the Post Shakedown Availability of the USNS HERSHEL WILLIAMS (T-ESB 4) Total Category "A" WIs $_____________

Proposed unit price per KWh $_____ in accordance with (IAW) WI 011, 7.1.1.4

Proposed unit price per gallon of potable water $______ IAW WI 011, 7.1.3.2

Proposed unit price per gallon of distilled water $______ IAW WI 011, 7.1.4.2

Proposed unit price per gallon of bilge water removal $______ IAW WI 011, 7.1.18.8

Proposed unit price per crane usage $______ IAW WI 11, 7.7.1.1

Proposed Hazardous Waste handling fee rate IAW WI 023, 7.4.1 ______%

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AA

MSC Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA MSC GENERAL REQUIREMENTS FUNDED CAT A WIs CAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023

FOB: Destination J998

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AB

MSC Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA MSC FUNDED CAT A WIs CAT A WORK ITEMS 101, 102, 301, 302, 303, 401, 403, 501, 502, 503, 504, 505, 506, 508, 509, 601, 602, 603, 604

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AC

PMS-385 PD Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA PMS-385 PD GENERAL REQUIREMENTS FUNDED CAT A WIs CAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AD

PMS-385 Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA PMS-385 SOF981 GENERAL REQUIREMENTS FUNDED CAT A WIs CAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AE

PMS-385 Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA PMS-385 PD GENERAL REQUIREMENTS FUNDED CAT A WIs

CAT A WORK ITEMS 332, 333, 432, 433, 507, 529, 582, 583, 584, 595, 613, 625

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AF

PMS-385 Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA PMS-385 SOF981 FUNDED CAT A WIs

CAT A WORK ITEMS 321, 322, 423, 521, 522, 523, 621, 623

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0001AG

PMS-385 NC Category "A" Work Items (WIs)

USNS HERSHEL WILLIAMS (T-ESB-4) PSA PMS-385 New Construction FUNDED CAT A WI

CAT A WORK ITEM 820

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR AND ODC

USNS HERSHEL WILLIAMS (T-ESB-4) PSA MSC FUNDED ADDITIONAL GOVERNMENT REQUIREMENTS (AGR) AND OTHER DIRECT COSTS

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0002AA

MSC AGR AND ODC

MSC AGR

(15,814) man-hours @ $________ per man-hour = $_____________

ODC

Base $2,080,948.00_____________

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0002AB

PMS 385 PD AGR AND ODC

PMS 385 Post Delivery AGR

(1,152) man-hours @ $________ per man-hour = $_____________

ODC

Base $329,454.00_____________

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0002AC

PMS 385 SOF AGR AND ODC

PMS 385 SOF AGR

(11,585) man-hours @ $________ per man-hour = $_____________

ODC

Base $2,352,479.00_____________

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0002AD

PMS 385 NC AGR AND ODC

PMS 385 New Construction AGR

(1,650) man-hours @ $________ per man-hour = $_____________

ODC

Base $385,172.00_____________

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 - Continuation of Services

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0355

CAT "B" WI 0355 – Misc. Electrical Conduits and Trays

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0421

CAT "B" WI 0421 – Radio Infrastructure for CBSP and OE-570

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0422

CAT "B" WI 0422 – Radio Infrastructure for HF, UHF and VHF

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0425Y

CAT "B" WI 0425Y – Secure Tactical Briefing Room Conversion

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0426Y

CAT "B" WI 0426Y – Unmanned Aerial System (UAS) RQ-21A Blackjack Installation

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0427Y

CAT "B" WI 0427Y – Scan Eagle Installation

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0428Y

CAT "B" WI 0428Y – Fire Scout Installation - Industrial Support

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0434Y

CAT "B" WI 0434Y – Sea Giraffe Industrial Assist

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0524

CAT "B" WI 0524 – Addition of 28 VDC at Spots 3 and 4

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0528

CAT "B" WI 0528 – Grey and Black Water Mods

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0555

CAT "B" WI 0555 – Install FibaClading

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0596

CAT "B" WI 0596 – OP4 Crane Certification Test

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0612

CAT "B" WI 0612 – Modify flight Deck Life Rails

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0622

CAT "B" WI 0622 – Additional Temporary Expandable Unit - Armory/Medical

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0632

CAT "B" WI 0632 – Repair Non-Skid Coatings

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0755

CAT "B" WI 0755 – Install Tie Downs in Seafox Magazine No. 2

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0801

CAT "B" WI 0801 – Install Independent AC Units in Adjacent Spaces to HELO Hanger

Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0821

CAT "B" WI 0821 – Forward House HVAC System Upgrade (Aviation Support Spaces HVAC Upgrade Phase II) Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.

NET AMT

CLAUSES INCORPORATED BY FULL TEXT

TOTAL PROPOSED PRICE

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0021 $______________

The contractor shall enter the total proposed price of all CLINs.

PART I - THE SCHEDULE

Section B, Price Schedule, detailed information

CLIN 0001 –Attachment J-2 – Category “A” WIs provides a WI breakdown of CLIN 0001 pricing.

CLIN 0002: This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated under the H-3 Clause - AGR and H-4 Clause ODC, for the duration of the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blastingTank cleaning
WeldingMachinists (inside and outside)
BurningBrazing
CarpentryElectrical work
Electronic workShipfitting
LaggingPainting
BoilermakingPipefitting
Sheetmetal workEngineering
RiggingStaging/scaffolding
General laborFire Watch

Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

TestingQuality Assurance
PlanningCleaning (except tank cleaning)
Material handling & warehousingSecurity
SurveyingAdministration
TransportationPurchasing staff
LoftingOther indirect support
Supervision

Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's fully loaded manhour rate and not separately priced.

The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The KO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

The base cost, stated in this CLIN does not include the profit or G&A rates.

NOTE: This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

CLINs 0003 through 0021 –Attachment J-3 – Category “B” WIs provides a WI breakdown of CLIN 0003 through 0022 pricing.

Section C - Descriptions and Specifications

ACRONYM TABLE

ABIH
American Board of Industrial Hygiene
ABR
Agreement for Boat Repair
ABS
American Bureau of Shipping
ACO
Administrative Contracting Officer
AGR
Additional Government Requirements
AIHA
American Industrial Hygiene Association
ALT
Alternate
AMRDEC
U.S. Army Aviation and Missile Research Development and Engineering Center
AMT
Amount
BLDG
Building
CCO
Contract Change Order
CD
Compact Disc
CDRL
Contract Data Requirements List
CD-ROM
Compact Disc Read-Only Memory
CFM
Contractor Furnished Material
CFP
Contractor Furnished Property
CFR
Condition Found Report
CHENG
Chief Engineer
CFR
Code of Federal Regulations
CIH
Certified Industrial Hygienist
CLIN
Contract Line Item Number
CONUS
Contiguous United States
DBIDS
Defense Biometric Identification Systems
DET
Detachment
DFARS
Defense Federal Acquisition Regulation Supplement
DOD
Department of Defense
DON
Department of the Navy
E-MAIL
Electronic Mail
EPIC
El Paso Intelligence Center
ESRS
Electronic Subcontract Report System
FAPIIS
Federal Awardee Performance and Integrity Information System
FAR
Federal Acquisition Regulation
FBLR
Fully-Burdened Labor Rate
FBO
Federal Business Opportunities (FebBizOpps)
F/CC
Fibers Per Cubic Centimeter
FPCON
Force Protection Condition
FR
Federal Register
FTR
Federal Travel Regulations
G&A
General and Administrative
GFI-TD
Government Furnished Information – Technical Data
GFM
Government Furnished Material
GFP
Government Furnished Property
IAW
In Accordance With
ID
Identification
ISO
International Organization for Standardization
JTR
Joint Travel Regulations
KO
Contracting Officer
KWh
Kilowatt Hour
LLTM
Long Lead Time Material
LPTA
Lowest Price Technically Acceptable
M&IE
Meals and Incidental Expenses
MSC
Military Sealift Command
MSCREP
Military Sealift Command Representative
MM
Millimeter
MSRA
Master Ship Repair Agreement
MTA
Mid-Term Availability
N/A
Not Applicable
NCACS
Navy Commercial Access Control System
NDA
Non-Disclosure Agreement
NLT
No Later Than
NO
Number
NSP
Not Separately Priced
ODC
Other Direct Costs
OSHA
Occupational Safety and Health Administration
PAT
Proficiency in Analytical Testing
PDF
Portable Document Format
PM
Program Manager
POC
Point of Contract
PPE
Principle Port Engineer
PPIRS
Past Performance Information Retrieval System
PRIME
Prime Contractor
PWS
Performance Work Statement
QA
Quality Assurance
QC
Quality Control
REV
Revision
RFC
Request for Specification Clarification
RFP
Request for Proposal
ROH/DD
Regular Overhaul/Dry-Docking
SECNAV
Secretary of the Navy
SF
Standard Form
SOW
Statement of Work
SUB
Subcontractor
TPSN
Time Phased Sequencing Network
TWA
Time-Weighted Average
USC
United States Code
USCG
United States Coast Guard
USNS
United States Navy Ship
VR
Voyage Repair
WAWF
Wide Area Workflow
WI
Work Item

C-1 GENERAL

1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS HERSHEL WILLIAMS (T-ESB 4) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.

2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):

(a) Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.

(b) Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR Clause 52.245-1 and DFARs Clauses 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.

(c) Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.

(d) Using management procedures and systems to identify behind schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.

(e) Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted in accordance with the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 013.

(f) Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.

(g) Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.

(h) Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.

(i) Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.

(j) Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.

(k) Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.

3. Contract work shall be performed by an eligible contractor as defined below.

(a) The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.

(b) The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:

a. Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.

b. Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.

c. Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.

d. Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.

e. Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.

f. Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.

g. Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.

h. Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.

i. Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.

j. Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:

· Pier, with services in place, accessible to the CLASS size ship for birthing

· Structural Shop

· Machine Shop

· Pipe Shop

· Electrical/Electronic Shop

· Carpentry Shop

· Rigging Equipment

· Dry-dock – when required for docking of vessel in performance of the specification

k. Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.

(c) The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.

This award consummates the contract which consists of the following documents: (a) the Government’s solicitation and your final proposal revision submitted on 08/28/2018 inclusive of all discussion and clarifications responses and (b) this award/contract.

C – 2 List of Standard WIs included for this solicitation:

NOT SEPARATELY PRICED (NSP) REQUIREMENTS Category

001INTENT, SCOPE, GENERAL CONDITIONS AND DEFINITIONSNSP
002TECHNICAL AND MANUFACTURER’S REPRESENTATIVESNSP
003APPROACH, BERTH, AND MOORING REQUIREMENTSNSP
004TESTING AND QUALITY ASSURANCENSP
005ELECTRICAL SAFETY PROCEDURE REQUIREMENTSNSP
006HEAVY WEATHER PLANNSP
007COLD WEATHER PLANNSP
024PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY (NSP)NSP

CATEGORY “A” WORK ITEMS

010FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM (OMT)A COMBINED
011FURNISH GENERAL SERVICESA COMBINED
012TELEPHONE SERVICESA COMBINED
013PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTSA COMBINED
014PREPARATION OF WEIGHT AND MOMENT REPORTA COMBINED
015INTEGRATED LOGISTICS AND GFM SUPPORT REQUIREMENTSA COMBINED
016FIRE PROTECTION AND SHIP’S SAFETY PROGRAMA COMBINED
017HANDLING SHIP’S STORESA COMBINED
018DELIVERY AND REDELIVERY OF THE VESSELA COMBINED
019SHIPBOARD ACCESS AND SECURITYA COMBINED
020GAS FREE CERTIFICATESA COMBINED
021CLEAN AND GAS FREE TANKS, VOIDS, COFFERDAMS AND SPACESA COMBINED
022MACHINERY SPACE TURN-OVER DOCK TRIALS AND SEA TRIALA COMBINED
023HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR’S FACILITYA COMBINED

CATEGORY “B” WORK ITEMS

025PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITYB COMBINED
030CONTINUATION OF SERVICESB COMBINED

SECTION 100 HULL STRUCTURE Category

CATEGORY “A” WORK ITEMS

101MACHINERY ROOM TO PUMP ROOM DOOR INSTALL (T-ALT 15-002)A
102MACNINERY SPACE DECK UTILIZATION PLAN (T-ALT 15-057)AMSC

SECTION 200 PROPULSION MACHINERY

N/A

SECTION 300ELECTRICAL
CATEGORY “A” WORK ITEMSCategory
301HULL PERIMETER LIGHTING (T-ALT 15-005)A
302FORWARD AND AFT HOUSE MSC LAND CABLE INSTALL (T-ALT 16-017)A
303HIGH VOLTAGE AND MEDIUM VOLTAGE SWITCHBOARDA
INSPECTION AND CLEANING
321NIGHT VISION DEVICE (NVD)A
322MISSION DECK NVD LIGHTING (T-ALT TBD)A
332RELOCATE FLIGHT DECK LIGHTS (T-ALT 16-057)A
333INSTALL LIGHT FIXTURES FORWARD MEDICAL TREATMENT ROOM (T-ALT 17-034)A

CATEGORY “B” WORK ITEMS

355 MISC. ELECTRICAL CONDUIT AND CABLE TRAYS (T-ALT 18-021) B

SECTION 400 COMMUNICATION AND NAVIGATIONAL AIDS Category

CATEGORY “A” WORK ITEMS

401EXPAND SHORE TELEPHONE CABABILITY (T-ALT 15-033)A
403MACHINERY SPACE CCTY AND BOW CAMERA MONITORING SYSTEM
(T-ALT 15-018/048)A
423ADDITIONAL AIRCRAFT OPERATING TYPES – VISUAL LANDING AIDS(T-ALT 16-031)A
432INSTALL SOUND POWERED PHONE LINES (T-ALT 16-005)A
433AUTOMATIC DIAL TELEPHONE SYSTEM (T-ALT 16-024)A

CATEGORY “B” WORK ITEMS

421RADIO INFRASTRACTURE FOR CBSP AND OE-570 (T-ALT 16-028)B
422RADIO INFRASTRUCTURE FOR HF, UHF AND VHF (T-ALT 16-029)B
425YSECURE TACTICAL BRIEFING ROOM CONVERSION (T-ALT 16-021)B
426YUNMANNED AERIAL SYSTEM (UAS) RQ-21A BLACKJACK INSTALLATION
(T-ALT 16-030)B
427YSCAN EAGLE/AEROSONDE UAS INSTALLATION (T-ALT 16-029)B
428Y UNMANNED AERIAL SYSTEM (UAS) FIRE SCOUT (T-ALT 18-002)B
434Y SEA GIRAFF INDUSTRIAL ASSIST (T-ALT 18-034)B

SECTION 500 AUXILIARY SYSTEMS Category

CATEGORY “A” WORK ITEMS

501INSTALL DUMBWAITER FROM UPPER DECK TO A DECK (T-ALT 15-006)A
502FORWARD ADDITIONAL A/C INSTALLATION (T-ALT 15-021)A
503SEGREGATION OF BLACK AND GREY WATER LINES (T-ALT 15-022)A
504 AFT HOUSE GREY WATER SYSTEM ISLOATION (T-ALT 15-036/37)A
505MISSION DECK BOAT REFUEL ENHANCEMENT (T-ALT 15-052)A
506FORWARD FIRE MAIN LOOP INSTALLATION (T-ALT 15-055)A
507INSTALL SCBA COMPRESSOR AND FILL STATION (T-0ALT 15-010)A
508RO FEED WATER CYCLONE SEPATOR INSTALL (T-ALT 17-028)A
509HTFW AND LTFW SYSTEM FLUSHA
521ADDITIONAL AIRCRAFT OPERATING TYPES JP-5 RELOCATION (T-ALT 16-038)A
522ADDITIONAL AIRCRAFT OPERATIONAL TYPES 28VDC SPOTS 1 AND 2 (T-ALT 16-037)A
523MOTOR GASONLE (MOGAS) CARGO FUEL STOWAGE (T-ALT 16-036)A
528FORWARD OVERBOARD BLACK AND GREY DISCHARGE AND SHOREA
CONNECTION (T-ALT 16-043)
529INSTALL BALLAST STANDPIPE FLOW SWITCH (T-ALT 15-066)A
582INSTALL MISSION DECK MOORING FITTINGS (T-ALT 16-006)A
583INSTALL MISSION DECK BOAT HANDLING BITTS (T-ALT 15-060)A
584MISSION DECK CLEATS AND CHAFING BARS (T-ALT 18-004)A
595INSTALL DECK EDGE FAIRING (T-ALT 18-005)A

CATEGORY “B” WORK ITEMS

524ADDITIONAL AIRFCAFT OPERATIONAL TYPES 28VDC SPOTS 3 AND 4 (T-ALT 16-035)B
528FORWARD OVERBOARD BLACK AND GREY DISCHARGE AND SHOREB
CONNECTION (T-ALT 16-043)
555INSTALL FIBACLAD (T-ALT 16-010)B
596OP-4 CRANE CERTIFICATION TSTINGB

SECTION 600 OUTFIT, FURNISHINGS AND HABITABILITY Category

CATEGORY “A” WORK ITEMS

601AFT HOUSE HABITABILITY MODIFICATIONS (T-ALT 15-008/15-013/17-023)A
602ENGINE CONTROL ROOM NO. 1 DECK HEAD INSTALLATION (T-ALT 15-040)A
603SELF SERVE LAUNDRY CAPACITY EXPANSION (T-ALT 15-053/054)A
604INSTALL GALLEY SHELVING (T-ALT 17-002)A
613INSTALL FLIGHT DECK SAFETY NETS (T-ALT 16-011)A
621ADDITIONAL TEUS - ACCOMMODATION TEUS AND PLATFORM (T-ALT 16-034)A
623ADDITIONAL TEUS – MODIFICATIONS –A6 LEVEL (T-ALT 16-032)A
625INSTALL HELICOPTER CONTROL STATION SUN SHADES (T-ALT 17-035)A

CATEGORY “B” WORK ITEMS

612MODIFY FIXED LIFERAILS TO ELIMINATE FLIGHT DECK INTERFERENCES
(T-ALT 16-001)B
622ADDITIONAL TEUS – ARMORY AND MEDICAL AND OTHER TEUS (T-ALT 16-033)B
632REPAIR EXTERIOR NON-SKID DECK COATINGSB

SECTION 700 SPONSOR EQUIPMENT Category

755 INSTALL TIE DOWNS IN SEAFOX MAGAZINE NO. 2 (T-ALT 18-032)

SECTION 800 HEATING, VENTILATION AND CONDITIONING Category

CATEGORY “A” WORK ITEMS

820 AVIATION SUPPORT SPACES HVAC UPGRADE PHASE I (T-ALT 18-013) A

CATEGORY “B” WORK ITEMS

801INSTALL INDEPENDENT A/C UNITS IN ADJACENT SPACES TO HELO HANGER B
(T-ALT 16-051)

821 FORWARD ACCOMMODATIONS HVAC SYSTEM UPGRADE (AVIATION

SUPPORT SPACES HVAC UPGRADE PHASE II) B

Section D - Packaging and Marking

WOOD PACKAGING MATERIAL (WPM) - ADDITIONAL DELIVERY INSTRUCTIONS

In accordance with the requirements of International Standards for Phytosanitary Measures (ISPM) 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM). WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). All materials must include certification markings in accordance with ALSC standards and be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved "DUNNAGE" stamp. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
0001
N/A
N/A
N/A
N/A
0001AA
Destination
Government
Destination
Government
0001AB
Destination
Government
Destination
Government
0001AC
Destination
Government
Destination
Government
0001AD
Destination
Government
Destination
Government
0001AE
Destination
Government
Destination
Government
0001AF
Destination
Government
Destination
Government
0001AG
Destination
Government
Destination
Government
0002
N/A
N/A
N/A
N/A
0002AA
Destination
Government
Destination
Government
0002AB
Destination
Government
Destination
Government
0002AC
Destination
Government
Destination
Government
0002AD
Destination
Government
Destination
Government
0003
Destination
Government
Destination
Government
0004
Destination
Government
Destination
Government
0005
Destination
Government
Destination
Government
0006
Destination
Government
Destination
Government
0007
Destination
Government
Destination
Government
0008
Destination
Government
Destination
Government
0009
Destination
Government
Destination
Government
0010
Destination
Government
Destination
Government
0011
Destination
Government
Destination
Government
0012
Destination
Government
Destination
Government
0013
Destination
Government
Destination
Government
0014
Destination
Government
Destination
Government
0015
Destination
Government
Destination
Government
0016
Destination
Government
Destination
Government
0017
Destination
Government
Destination
Government
0018
Destination
Government
Destination
Government
0019
Destination
Government
Destination
Government
0020
Destination
Government
Destination
Government
0021
Destination
Government
Destination
Government
0022
Destination
Government
Destination
Government

CLAUSES INCORPORATED BY REFERENCE

252.217-7005
Inspection and Manner of Doing Work
JUL 2009
252.217-7006
Title
DEC 1991
252.217-7013
Guarantees
DEC 1991

Section F - Delivery and Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE
0001
N/A
N/A
N/A
N/A
0001AA
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AB
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AC
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AD
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AE
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AF
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0001AG
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0002
N/A
N/A
N/A
N/A
0002AA
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0002AB
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0002AC
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0002AD
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0003
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0004
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0005
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0006
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0007
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0008
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0009
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0010
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0011
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0012
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0013
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0014
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0015
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0016
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0017
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0018
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0019
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0020
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0021
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
0022
POP 07-JAN-2019 TO

07-MAY-2019

N/A
N/A
52.242-15
Stop-Work Order
AUG 1989
52.242-17
Government Delay Of Work
APR 1984

52.211-11 LIQUIDATED DAMAGES--SUPPLIES, SERVICES, OR RESEARCH AND DEVELOPMENT (SEP 2000)

(a) If the Contractor fails to deliver the supplies or perform the services within the time specified in this contract, the Contractor shall, in place of actual damages, pay to the Government liquidated damages of $129,154.00 per calendar day of delay.

(b) If the Government terminates this contract in whole or in part under the Default--Fixed-Price Supply and Service clause, the Contractor is liable for liquidated damages accruing until the Government reasonably obtains delivery or performance of similar supplies or services. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(c) The Contractor will not be charged with liquidated damages when the delay in delivery or performance is beyond the control and without the fault or negligence of the Contractor as defined in the Default--Fixed-Price Supply and Service clause in this contract.

(End of clause)

F-1 SHIP AVAILABILITY PERIOD

It is anticipated the ship will arrive at contractor’s yard on or about 07 January 2019. All work shall be completed in no more than 120 calendar days from actual start date designated by the Government at time of contract award.

F-2 PLACE OF PERFORMANCE

The place of performance for this contract shall be the contractor’s facility.

Section G - Contract Administration data

252.232-7003
Electronic Submission of Payment Requests and Receiving Reports
JUN 2012

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)

(a) Definitions. As used in this clause--

Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall--

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

Invoice

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

Government

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table* Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAACN32205
Issue By DoDAAC____
Admin DoDAAC____
Inspect By DoDAAC____
Ship To Code____
Ship From CodeN62387
Mark For Code____
Service Approver (DoDAAC)____
Service Acceptor (DoDAAC)____
Accept at Other DoDAAC____
LPO DoDAAC____
DCAA Auditor DoDAAC____
Other DoDAAC(s)____

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.

Not Applicable

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

MSCHQ_WAWF@navy.mil

(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.

ADDENDUM TO 252.232-7006

The following information, at a minimum, must be attached into Wide Area Work Flow (WAWF) and submitted with each and every invoice showing certification with the Onsite Management Team prior to submission:

CLIN #
Contract Price Through Mod P0000x
% Complete
Contract Completed ($)
Less Retainage ($)
Less Prev Payments ($)
Amount due this Invoice ($)
Total Invoiced to Date ($)
004
Option
005
Option
00X
Option

Military Sealift Command

Administrative Contracting Officer

Military Sealift Command

Ship Yard Representative

Port Engineer

(End of instructions)

MSC SPECIFIC WIDE AREA WORKFLOW (WAWF) INSTRUCTIONS (AUG 2012)

The information contained in this instruction is supplemental to DFARS 252.232-7006.

The information contained in the table in DFARS 252.232-7006 is for WAWF purposes only. Information included in DFARS 252.232-7006 and this WAWF instruction apply only to WAWF Invoicing and WAWF Receiving Reports. Contradictory information elsewhere in this contract, e.g. Ship to DoDAAC, shall be followed per the terms and conditions of the contract.

When entering the invoice into WAWF, the Contractor shall fill in the DoDAAC fields or DoDAAC extensions exactly as shown in the table in DFARS 252.232-7006. Fields that should not be filled in when entering the invoice into WAWF will be indicated with the direction, “Leave Blank.”

In some situations the WAWF system will pre-populate the “Pay DoDAAC,” “Admin By DoDAAC” and “Issue By DoDAAC.” The Contractor shall verify that those DoDAACs automatically entered by the WAWF system match the information in the table in DFARS 252.232-7006. If these DoDAACs do not match, then the Contractor shall correct the field(s).

If Receiving Reports are required, ensure that the “Inspection” and “Acceptance” defaults of “destination” for both fields are not changed in the WAWF online interface.

The CLINs on the WAWF invoice shall be entered exactly as set forth in the contract document including CLIN number (e.g. 0001), Quantity (may be adjusted for actual quantity or dollar value delivered and invoiced), and Unit Price (e.g. $1.00). The dollar amounts on each CLIN or SubCLIN on the WAWF invoice shall reflect final performance values, but in no instance can the dollar amount for each CLIN or SubCLIN exceed what is specified in the contract document. The Contractor shall bill to the lowest level, e.g., the SubCLIN level. The Quantity and Unit of Measure fields must be filled out exactly as indicated in the CLINs and SubCLINs to reduce the possibility of the invoice being delayed or rejected during processing.

Before closing out of an invoice session in WAWF, but after submitting the document or documents, the Contractor will be given the option to send additional email notifications by clicking on the “Send More Email Notifications” link that appears on the page. The Contractor shall click on this link and add the Technical Point of Contact’s (TPOC) or Contracting Officer’s Representative’s (COR) email address in the first email address block and add any other additional email addresses desired in the following blocks. This additional notification to the Government is important to ensure the acceptor/receiver is aware that the invoice documents have been submitted into the WAWF system.

(End of instructions)

Section H - Special Contract Requirements

SECTION H CLAUSES

H-1 OPTION FOR INCREASED QUANTITIES

The Government may require delivery of the numbered line items identified in Section B as option items in any amount up to the unit quantities and at the unit prices stated in the contractor’s J-3, “Contractor Price Breakdown – Category B Items.” The KO may exercise the options by giving the contractor written notification or via issuance of standard modification (SF 30). Delivery of option items shall be within the performance period identified in Section F unless the parties otherwise agree.

H-2 PREVENTION OF THE DISCHARGE OF OIL AND HAZARDOUS SUBSTANCES

(a) Policy. In compliance with Executive Order Number 11752 (38 F.R. 34793), the policy of the DON is to conform to the provisions of the Federal Water Pollution Control Act, as amended (Title 33 U.S.C. 1251 et seq), and the Oil Pollution Act of 1990, as amended (Title 33 U.S.C. 2701 et seq.), insofar as these Acts prohibit the discharge of oil, oily mixtures, and hazardous substances, and regardless of whether or not these Acts pertain specifically to the Naval vessel and shore activities. The prescribed clause is intended to implement that policy with respect to the ship(s) being constructed or undergoing repair and overhaul under this contract.

(b) Definitions. For the purpose of this clause, the terms "oil," "oily mixtures," "hazardous substance," and "discharge" shall have the meanings as defined in the Acts referred to in paragraph (a) of this clause and other environmental statutes.

(c) Trials. Prior to commencement of any dock or sea trials hereunder, the contractor shall assure the Ship’s Master and CHENG as well as the PPE by demonstrations, completed test memoranda, or other means reasonably acceptable to the Ship’s Master and CHENG, as well as the PPE, that all equipment, the function of which is to prevent the accidental discharge of oil, oily mixtures, or hazardous substances from the ship, that the contractor shall be required by the specifications to install, is fully operable.

(d) Reports. The contractor shall, as soon as it has knowledge of any discharge of oil, oily substance, or hazardous substance from the ship, immediately notify the Ship’s Master and CHENG, as well as the Principle Port Engineer, thereof and shall immediately take all reasonable steps to prevent further discharge. Within 24-hours thereafter, the contractor shall file with the Ship’s Master and CHENG, as well as the PPE, the "Oil or Hazardous Substance Discharge Report.”

(e) Liability. The contractor shall be liable to the Government for all such costs of removal of such oil, oily mixture, or hazardous substance where such discharge was the result of willful negligence or willful misconduct within the privity and knowledge of the contractor. All documentation related to such waste shall bear the contractor’s generator number in accordance with WI 0023 HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR'S FACILITY. The contractor shall not be liable for the costs incurred by the Government for the removal of such oil, oily mixture, or hazardous substance when initiated by the Government.

H-3 AGR CONTRACT LINE ITEM NUMBER (CLIN 0002)

(a) The Government may utilize CLIN 0002 for and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work.