USNS GUADALUPE
(T-AO 200)
OUTFITTING, FURNISHING AND HABITABILITY N32205-17-R-4005
20 NOV 2016
ITEM NO. 605 CATEGORY "A" MSFSC/JVS/rkk
TILE REPLACEMENT (VR15-019/20/21)
605-1
1.0 ABSTRACT
1.1 This item provides for replacement of tile in various spaces throughout the ship.
2.0 REFERENCES/ENCLOSURES
2.1 References
2.1.1 NAVSEA Dwg. No. 634-6580085 Rev B, Deck Covering Schedule.
2.1.2 46 CFR 32.57-10 Subpart 32.57 - Structural fire protection for tank vessels contracted for on or after January 1, 1963.
2.1.3 NVIC 9-97, Guide to Structural Fire Protection.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Description/Quantity
3.1.1 Tile replacement for locations in 3.1.2: Approximately 4,410 square feet
3.1.2 Locations:
LOCATION SPACE SQFT
1-99-0
Passageway(port pass way extending to officer’s mess entry) 160
1-97-8 Forward Crew Mess
Room 900 1-97-8 Aft Crew Mess Room 840
1-116-2 CPO Mess Room 630 1-114-1 Officer Mess Room 760 1-109-1 Passageway 320 1-75-1 Transit Stateroom 160 1-75-2 Transit Stateroom 160 1-78-1 Transit Stateroom 160 1-78-2 Transit Stateroom 160
OUTFITTING, FURNISHING AND HABITABILITY N32205-17-R-4005
20 NOV 2016
605-2
1-69-1 Transit Stateroom 160
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None
5.0 NOTES
5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s.
5.2 The contractor and all subcontractors, regardless of tier are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.
5.3 Contractor encouraged to ship check to verify scope of work.
5.4 All deck covering colors shall be approved in advance by the ship’s Master.
5.5 This item must be accomplished and completed before habitability turnover.
5.6 All dimensions, lengths, sizes, quantities and measurements are considered approximate. Contractor shall verify all dimensions, lengths, sizes, quantities and measurements during the ship check and bid to that square footage.
6.0 QUALITY ASSURANCE REQUIREMENTS:
6.1 All work shall be performed to the satisfaction of the ship’s Master, Port Engineer, and the Chief Engineer.
7.0 STATEMENT OF WORK REQUIRED
7.1 Remove and replace the tile in the spaces described in paragraph 3.1.2, using reference
2.1.1 and 2.1.3 for guidance and as follows.
OUTFITTING, FURNISHING AND HABITABILITY N32205-17-R-4005
20 NOV 2016
605-3
7.1.1 Remove and replace all interferences in way of accomplishment of this specification.
7.1.2 Install protective covering to protect the vessel’s equipment and to contain the dust generated by this work item to the affected compartments. The MSCREP or ship’s representative shall approve the protective coverings prior to the start of productive work.
7.1.3 Repair 50 SF. of underlayment at the direction of the MSC representative.
Fair the deck with underlayment to prevent high spots and deck irregularities. Ensure underlayment is smooth, sanding any high spots or rough spots, as necessary.
7.1.4 Wipe down the primed surfaces with solvent. When dry, apply a bond coat to the deck surface to ensure proper bonding
7.1.5 Install new wear resistant vinyl deck tiles (SOLAS approved for marine use, meeting the requirements of IMO Resolution A.652(16) in accordance with the FTP code). Color and pattern shall be approved by the Captain and/or Chief Engineer prior to installation.
7.1.6 During the adhesive setting period, tiles shall be rolled with a minimum 100 lb. floor tile roller to ensure a good bond. All excess adhesive shall be removed from the deck tiles.
7.1.7 Install tile transition strip and boarder coaming around perimeter of each area indicated in 3.1.2 using manufactured approved adhesive.
7.1.8 Mechanically clean, prepare, prime, paint and otherwise restore all new and disturbed surfaces to match surrounding surfaces
7.1.9 All installation of tile shall complete four(4) days prior to crew move aboard.
7.1.10 Dispose of the tile and vinyl cove base removed from the spaces listed above in paragraph 3.1.2.
OUTFITTING, FURNISHING AND HABITABILITY N32205-17-R-4005
20 NOV 2016
605-4
7.2 Conduct final room cleanliness and tile installation inspection in the presence of the MSC Port Engineer and CHENG.
7.3 All dirt and debris shall be removed from ship on a daily basis and work areas shall be left clean and in good order.
8.0 GENERAL REQUIREMENTS: None Additional