MILITARY SEALIFT COMMAND
NORFOLK, VIRGINIA
S P E C I F I C A T I O N S
FOR
USNS ROBERT E. PEARY (T-AKE 5)
USCG No.:
CG831773
ABS ID No.:
08157105 IMO No.: 9319806
RFP NO.: N32205-15-R-3003
12 JULY 2015 thru 26 AUGUST 2015 ROH/DD AVAILABILITY
PRINCIPLE DIMENSIONS
LENGTH
689 ft 00 in
BREADTH
105 ft 06 in
DRAFT FULL LOAD (mean) 30 ft 06 in ABL
GROSS TONNAGE
43758 TONS (Registered)
MAXIMUM DISPLACEMENT
41470 TONS
ESTIMATED ARRIVAL DRAFT
24 ft 00 in Fwd, 25 ft 03 in Mid
26 ft 06 in Aft
AIR DRAFT WITH MAST DOWN
160 ft 0 in ABL
THIS SPECIFICATION CONSISTS OF THE FOLLOWING PAGES
INDEX
PAGES 3 THRU 6
LIST OF References
PAGES 7 THRU 18
LIST OF GFM
PAGES 19 THRU
WORK ITEMS
PAGES 0001-1 THRU 1004-13
Notes
WORK ITEM INDEX
USNS ROBERT E. PEARY (T-AKE 5)
SECTION 0000
GENERAL REQUIREMENTS
NOT SEPARATELY PRICED (NSP) REQUIREMENTS
Rev Date Intent, Scope, General Requirements, 17 Dec 14 and Definitions
Technical and Manufacturer’s Representatives
17 Dec 14 Approach, Berth, and Mooring Requirements
17 Dec 14 Testing and Quality Assurance
17 Dec 14 Electrical Safety Procedure Requirements
17 Dec 14 Heavy Weather Plan
Cold Weather Plan
CATEGORY “A” WORK ITEMS
Furnish Office for Overhaul Management Team (OMT) 17 Dec 14 Furnish General Services
Telephone Services
Project Planning and Production Status
Monitoring Reports
Preparation of Weight and Moment Report
Integrated Logistics and GFM Support Requirements 17 Dec 14 Fire Protection and Ship’s Safety Program
17 Dec 14 Handling Ship’s Stores
Delivery and Redelivery of the Vessel
Shipboard Access and Security
Gas Free Certificates
Clean and Gas Free Tanks, Voids, Cofferdams and Spaces
Dock Trials and Sea Trials
Hazardous Waste Disposal at a Contractor’s 17 Dec 14 Facility 0024 Physical Security at Private Contractor’s 17 Dec 14 Facility
CATEGORY “B” WORK ITEMS
0025 Physical Security Force Bravo 17 Dec 14 Continuation of Services
SECTION 0100
HULL STRUCTURE
0100 Port and STBD FWD Crane Boom Rest Repair 14 Feb 15
Roller Chock Replacement (TA 136) 17 Dec 14 Bridge Wing Canopy Installation (TA 240) 17 Dec 14 0110 Preservation of House 17 Dec 14 Replacement of Chain Fairlead 15 Dec 14 Preservation of RAS Station King Posts 17 Dec 14 Preservation of Lifeboat and Rescue Boat Davits 07 Aug 14 Preservation of Cargo Cranes
15 Dec 14 0115 Install Deck Drain 02 Level (TA 303) 15 Dec 14 0116 Modify Exterior Deck Grating and Ladder 19 Dec 14
Preservation
SECTION 0200
PROPULSION MACHINERY
MDG #1 Splash Oil and Test Circuit Modification 26 Sep 14
(TA 381)
SACOS UPS Upgrade Mod (TA 352)
07 Jul 14
SECTION 0300
ELECTRICAL
HV Switchboard Cleaning and Inspection 10 Dec 14 Install Hour Meters on Cargo Cranes (TA 211) 10 Dec 14 0303 PLC Survey 10 Dec 14
0304 HV Jumper Cable Replacement (TA 428) 10 Dec 14
0305 IMECO HVAC SY Support (TA 319) 10 Dec 14 0306 Accommodation Ladder Winch Upgrade (TA 372) 17 Dec 14 0307 IMECO Chillers SY Support
05 Jan 15
0375 Cargo Holds 1-6 Lighting Switch Install (TA 246) 27 Jan 15
SECTION 0400
COMMUNICATION AND NAVIGATION AIDS
AIS-DGPS Renewal
10 Dec 14 0402 3 cm and 10 cm Radar Monitoring System 18 Mar 15
Antenna Preventative Maintenance
Searchlight Installation (TA 239)
11 Dec 14 SRD-500 Doppler Speed Log Replacement
16 Dec 14 0409 Communication Suite Groom - Limited 15 Dec 14 0415 Upgrade of CCTV System of Flight Deck to DVR 10 Dec 14
(TA 346)
0416 VMS/ECDIS Upgrade (TA 224/347) 19 Dec 14
0440 AWS Speaker Upgrade (TA 389) 19 Dec 14
SECTION 0500
AUXILIARY MACHINERY SYSTEMS
Deckhouse Weather Deck Drain Piping Renewal
10 Dec 14 0508 Distiller Plate Cleaning
29 Dec 14
LTFW Cooler Cleaning 10 Dec 14 0510 MAG Sprinkler Sys Check Valve Internals Removal 10 Dec 14
Fire Extinguisher in Galley Installation (TA 382) 10 Dec 14 Counter Measure Wash Down Piping Replacement 15 Dec 14
(TA-420)
Bow Thruster Lube Oil Piping Modification (TA 291)10 Dec 14 0515 Sewage piping Repair 23 Jan 15
HP Air Union Replacement 10 Dec 14 Open and Inspect Air Receivers and Hydro HP 10 Dec 14
Air Flask
0521 Firemain Isolation Valve Installation (TA 367) 17 Dec 14 0524 Install MARPOL Fuel Samplers (TA 377) 10 Dec 14 0530 Ballast Tank TLIs 17 Dec 14
SECTION 0600
OUTFIT, FURNISHINGS and HABITABILITY
Galley Equipment Calibration
Replace Mess Passageway Decking With PRC 10 Dec 14 0604 Chief Mate Office Modification 17 Feb 15
0605MILDAT Office Modification 17 Feb 15
Lifeboat and Rescue Boat Release Hook Upgrade 10 Dec 14
(TA 376)
Deck Tile Replace and PRC Install
10 Dec 14 0628 Machinery and HVAC Insulation Repairs 30 Dec 14
0673 Second Deck Cargo Hold #6 Bulk Stowage Cabinet 17 Dec 14
Space Modifications (TA 364)
SECTION 0800
HEATING, VENTILATION and AIR CONDITIONING
Galley Exhaust Duct Cleaning
Laundry Exhaust Duct Cleaning
SECTION 0900
DRYDOCKING
Dry-Docking and Undocking Vessel
Polish Bow Thruster Propeller-Inspect Seals
10 Dec 14 Propeller Shaft and Stern Tube Inspection
10 Dec 14 Stern Tube Seal Inspection
Underwater Hull Cleaning and Painting
Freeboard Cleaning and Painting
11 Dec 14 Renew Seachest, Rope Guard, & Bow Thruster Zincs 11 Dec 14 Inspect and Repair Cathodic Protection
Overhaul Sea Valves
Anchor and Anchor Chain Ranging (TA 326)
11 Dec 14 Bilge Keels Repair 11 Dec 14 Renew Waster Pieces
0916 Central Sea Water 30 Inch Waster Piece 11 Dec 14
Mod (TA 290)
SECTION 1000
UNREP GEAR
1001 ASD Fan Motor Overhaul
20 Dec 14
UNREP Hauling Winch Clutch Cooling Fan Electric 11 Dec 14
Motor Bearing Replacement 1003 Sliding Block Rubber Bumpers
20 Dec 14 1004 High Pressure Air Relief Valve Calibration 17 Dec 14
DRAWING /REFERENCE INDEX
USNS ROBERT E. PEARY (T-AKE 5)
| Work Item |
| Reference |
| Drawing/Reference Title |
| 001 |
| 2.1 |
| MSC 803-7081122, Military Sealift Command General Technical Requirements (GTR's) |
| 003 |
| 2.1 |
| Mil STD Mil-DTL-28628D, dtd July 1991; Camels |
| 003 |
| 2.2 |
| Mil STD Mil-F-29248, dtd 21 November 1986; Fenders, Marine, Foam Filled, Netless |
| 003 |
| 2.3 |
| MSC Drawing 802-8387206, General Arrangement Plan |
| 003 |
| 2.4 |
| NAVSEA 835-7489033, Rev C, Mooring Analysis |
| 004 |
| 2.1 |
| Mil-I-45208, (Series), Inspection Systems |
| 005 |
| 2.1 |
| High Voltage Awareness Instruction Guide PowerPoint Presentation |
| 005 |
| 2.2 |
| High Voltage Awareness PowerPoint Presentation |
| 005 |
| 2.3 |
| MSC Safety Management System Procedure 2.1-004-All, Lock-out/ Tag-out |
| 005 |
| 2.4 |
| MSC Safety Management System Procedure 2.1-016-AKE, High Voltage System |
| 005 |
| 2.6 |
| NFPA 70E Standard for Electrical Safety Requirements for Employee Workplaces |
| 006 |
| 2.1.1 |
| MSC Drawing 835-8388070, Trim and Stability Booklet |
| 007 |
| 2.1 |
| MSC Drawing 835-8388070, Trim and Stability Booklet |
| 011 |
| 2.1.1 |
| NAVSEA 802-8387206, General Arrangement |
| 011 |
| 2.1.2 |
| MSC Chemical Treatment Handbook |
| 015 |
| 2.1 |
| DOD Security Manual for Safeguarding Classified Information, DOD Manual 5220.22-M |
| 016 |
| 2.1 |
| NFPA 312, Standard for Fire Protection of Vessels During Construction, Repair and Lay-Up |
| 016 |
| 2.2 |
| NFPA 51B, Standard for Fire Prevention in use of Cutting and Welding Processes |
| 018 |
| 2.1 |
| NAVMED P-5010-6, Manual of Naval Preventive Medicine, Chapter 6, Water Supply Afloat |
| 019 |
| 2.1 |
| COMSCINST 5530.3D, MSC Shipboard AT/FP Program |
| 021 |
| 2.1.1 |
| MSC Dwg 801-8387182, Capacity Plan |
| 021 |
| 2.1.2 |
| MSC Dwg 835-8388070, Trim and Stability Booklet |
| 023 |
| 2.1.1 |
| Resource Conservation and Recovery Act (RCRA) as Amended |
| 023 |
| 2.1.3 |
| Applicable Uniform Hazard Waste Manifest Form |
| 023 |
| 2.1.4 |
| Test Methods for Evaluating Solid Waste, Physical/Chemical Methods; EPA Document, SW-846: The Official compendium of analytical and sampling methods that have been evaluated and approved for use in complying with the RCRA regulations. |
| 023 |
| 2.1.5 |
| OPNAVINST 5090.1C |
| 100 |
| 2.1.1 |
| MSC Dwg 085-7488875 Rev K, Scantling Plan Deck and Profile |
| 100 |
| 2.1.2 |
| MSC Dwg, 085-7488876 Rev H, Scantling Plan Sections |
| 100 |
| 2.1.3 |
| MSC Dwg, 635-7489024 Rev J, Insulation Details 02 Level |
| 100 |
| 2.1.4 |
| MSC Dwg, 100-7489121 Rev D, T-AKE Standard Welding Details |
| 110 |
| 2.2 |
| Steel Structures Painting Council, System and Specifications, Volume 2, Eight Edition. |
| 110 |
| 2.3 |
| SSPC SP11, Power Cleaning to Bare Metal |
| 111 |
| 2.1 |
| NAVSEA Dwg 582-7488906, Rev H, T-AKE 1 Class Mooring Arrangement Fwd Plan |
| 111 |
| 2.2 |
| NAVSEA Dwg 100-7489051, Rev E, Forecastle (FS Zone) |
| 111 |
| 2.3 |
| NASSCO ECN 90 (for Dwg 471-321-1749) |
| 112 |
| 2.1 |
| Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. |
| 112 |
| 2.2 |
| Steel Structures Painting Council, System and Specifications, Volume 2, Eight Edition. |
| 112 |
| 2.3 |
| SSPC SP11, Power Cleaning to Bare Metal |
| 113 |
| 2.1 |
| Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. |
| 113 |
| 2.2 |
| Steel Structures Painting Council, System and Specifications, Volume 2, Eight Edition. |
| 113 |
| 2.3 |
| SSPC SP11, Power Cleaning to Bare Metal |
| 114 |
| 2.1 |
| Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. |
| 114 |
| 2.2 |
| Steel Structures Painting Council, System and Specifications, Volume 2, Eight Edition. |
| 114 |
| 2.3 |
| SSPC SP11, Power Cleaning to Bare Metal |
| 116 |
| 2.5 |
| Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. |
| 116 |
| 2.1 |
| Steel Structures Painting Council, System and Specifications, Volume 2, Eight Edition. |
| 116 |
| 2.1 |
| SSPC SP11, Power Cleaning to Bare Metal |
| 202 |
| 2.1 |
| FME PROCEDURE M12702096 – INSTRUCTIONS, INSTALLATION, AND TAKE UPGRADE. |
| 202 |
| 2.2 |
| FME PROCEDURE M12701960 - PROCEDURE, PRE & POST COMMISSIONING SAFETY CHECKS. |
| 202 |
| 2.3 |
| FME DWG M12702099 - ASSEMBLIES, EXTENSION SACOS CABLE, T-AKE UPGRADE |
| 202 |
| 2.4 |
| FME DWG M12702240 - TEST JUNCTION BOX, T-AKE UPGRADE |
| 202 |
| 2.5 |
| FME DWG M12702248 - TEST JUNCTION BOX |
| 202 |
| 2.6 |
| FME DWG M12702249 - CABLE, 12 METER |
| 202 |
| 2.7 |
| FME DWG M12702250 - CABLE 17 METER |
| 202 |
| 2.8 |
| FME DWG 10570989 - INTERCONNECT DIAGRAM, ENGINE CONTROL SYSTEM, T-AKE UPGRADE |
| 202 |
| 2.9 |
| FME DWG 10570990 - ELECTRICAL SCHEMATIC, ALARM PRE-PROCESSING SYSTEM, T-AKE UPGRADE |
| 202 |
| 2.10 |
| FME DWG 10570991 - ELECTRICAL SCHEMATIC, SAFETY SYSTEM, T-AKE UPGRADE |
| 202 |
| 2.11 |
| FME DWG 10570992 - CABLE LIST, T-AKE UPGRADE |
| 202 |
| 2.12 |
| FME DWG 10570993 - CABLING ELECTRICAL UNITS ON ENGINE, T-AKE UPGRADE |
| 202 |
| 2.13 |
| FME DWG 10570994 - ELECTRICAL SCHEMATIC, ENGINE CONTROL SYSTEM, T-AKE UPGRADE |
| 202 |
| 2.14 |
| NAVSEA DWG 802-7488866 Rev N, SRD GENERAL ARRANGEMENT, SHT 7. |
| 203 |
| 2.1 |
| Technical Manual T9233-CF-IMC-(010 to 150): Diesel Engine, Main Power Generation; Models 48/60 8L & 9L |
| 203 |
| 2.2 |
| FME Dwg. No. M12702280,Rev. Preliminary; T-AKE UPS Upgrade Instructions |
| 301 |
| 2.1 |
| Technical Manual Generator, Synchronous, 6600 V, 60 Hz, Including Generator Excitation Control Panel - T9235-AK-MMC-010 |
| 301 |
| 2.2 |
| Technical Manual T-AKE Propulsion Control System - T9235-AN-MMC-010 |
| 301 |
| 2.3 |
| Technical Manual Transformers, Propulsion, Type THT 12HN 7M2N - T9235-AM-MMC-010 |
| 302 |
| 2.1 |
| MSC Technical Manual No. TG811-BL-MMC-010, Boom Crane, Electro-Hydraulic, Model EB270-87-47. |
| 302 |
| 2.2 |
| Institute for Electrical and Electronic Engineers (IEEE) Standard 45, Recommended Practice for Electric Installations on Shipboard. |
| 304 |
| 2.1 |
| T-AKE Notice 5.PDF. |
| 304 |
| 2.2 |
| Coleman Cable Specification F4T027 |
| 304 |
| 2.3 |
| TB StaKon Straight Terminal Specification |
| 304 |
| 2.4 |
| TB StaKon Flag Terminal Specification |
| 305 |
| 2.1.1 |
| Dwg. No. 8393719rC: IHVACR Upgrade T-AKE Class 2-9 |
| 305 |
| 2.1.2 |
| Dwg. No. 897-000228r-: T-AKE 5 Installation Plan Details |
| 305 |
| 2.1.3 |
| 31108 M1M2 Guards Example rA |
| 305 |
| 2.1.4 |
| 31108 M4M5 Catwalk Example rA |
| 305 |
| 2.1.5 |
| 31108 Mounting Bracket 2xVSD Distributed System Example rC |
| 305 |
| 2.1.6 |
| T-AKE 1 Installation Process Booklet |
| 305 |
| 2.1.7 |
| Ceiling opening drawing |
| 306 |
| 2.1 |
| MSC Drawing 320-8494686: Lewis & Clark Class (T-AKE 1 thru 7) Accommodation Ladder Electric Winch Upgrade |
| 306 |
| 2.2 |
| Fassmer Technical Manual for Accommodation Ladder Plant 13,16m (T-AKE 1 Class) |
| 307 |
| 2.1.1 |
| Dwg. No. 8393719rC: IHVACR Upgrade T-AKE Class 2-9 |
| 307 |
| 2.1.2 |
| Dwg. No. 897-000228r-: T-AKE 5 Installation Plan Details |
| 307 |
| 2.1.3 |
| T-AKE Rigging Booklet.pdf |
| 307 |
| 2.1.4 |
| T-AKE Installation Process Booklet.pdf |
| 375 |
| 2.1 |
| MSC Drawing No. 94421-331-8391417; T-AKE 1 CLASS CARGO HOLD LIGHT SWITCH – LIGHTING REMOVAL |
| 375 |
| 2.2 |
| MSC Drawing No. 94421-331-8391418; T-AKE 1 CLASS CARGO HOLD LIGHT SWITCH – LIGHTING INSTALLATION |
| 375 |
| 2.3 |
| MSC Drawing No. 94421-331-7488809, Selected Record Drawing BWD Cargo and Miscellaneous Spaces Lighting |
| 401 |
| 2.1 |
| SPERRY MARINE MSO113-E15-1497 REV E (Proprietary) |
| 401 |
| 2.2 |
| SPERRY MARINE MX-512 DGPS, MS0411-5003890 REV.- |
| 401 |
| 2.3 |
| SAAB R5 AIS TECHNICAL INSTALL & OPS MANUAL (Provided with new contractor furnished system) |
| 401 |
| 2.4 |
| SIMRAD MX-612 DGPS TECHNICAL INSTALL & OPS MANUAL (Provided with new contractor furnished system) |
| 405 |
| 2.1 |
| Antenna Legend sheet Dated April 2010 |
| 405 |
| 2.2 |
| Whip Antenna Maintenance PMS 4411/023, U10 |
| 405 |
| 2.3 |
| Dipole Antenna Maintenance PMS |
| 407 |
| 2.1 |
| 800-8389949 Searchlight Install Guidance Drawing |
| 407 |
| 2.2 |
| 320-7488777 T-AKE Electrical one line drawing |
| 408 |
| 2.1 |
| Furuno DS-60 Doppler Speed Log Service Manual |
| 408 |
| 2.2 |
| DS-661 Gate valve and DS-631 Transducer installation instruction |
| 408 |
| 2.3 |
| Sperry SRD-500 DSL service manual (Proprietary) |
| 408 |
| 2.4 |
| SRD-500 AS-Built installation drawing for USNS Matthew Perry |
| 409 |
| 2.1 |
| AN/USQ-155 Manufacturer’s Technical Manual |
| 409 |
| 2.2 |
| SAMMS Planned Maintenance Task Code 3435-E621 |
| 409 |
| 2.3 |
| U.S. Navy Preventative Maintenance System: |
2.3.1
MIP 4416/510_2W-1/M
2.3.2
MIP 4416/510_S-1
2.3.3 MIP 4411/019 MRCS R-1 and Q-1
| 409 |
| 2.4 |
| RF-5800 Technical manual |
| 409 |
| 2.5 |
| AN/URN-25 TACAN Technical manual |
| 409 |
| 2.6 |
| AN/SYQ-26 NAVMACS II Technical manual |
| 409 |
| 2.7 |
| OA-9277 Multicoupler Technical manual |
| 415 |
| 2.1 |
| Pelco DX4104 Series Digital Video Recorder Specification Sheet |
| 416 |
| 2.1 |
| MSC Drawing No. 423-7488815, Block Wiring Diagram, Integrated Bridge and Navigation System |
| 416 |
| 2.2 |
| Manual: T9AKE-ABS2 - Navigational Integrated Bridge System (ABS stamped approved manual for each ship) |
| 440 |
| 2.1 |
| MSC Drawing 440-8495671 Audible Warning System Speaker |
Upgrade.
| 507 |
| 2.1 |
| MSC Drawing. 802-7488866, General Arrangement |
| 508 |
| 2.1 |
| NAVSEA DWG No. 256-8498829 Rev -, Central Seawater Cooling System Diagram |
| 508 |
| 2.2 |
| NAVSEA Dwg No. 532-8387192 Rev - (NASSCO Dwg 471-342-7108, Diesel Gen High Temp Freshwater Cooling System Diagram |
Tech Manual T9531-AU-MMC-010, Distillers, Aqua Chem Model Number. SPD35-53TPD, Serial Number...: SP06-19327.
| 509 |
| 2.1 |
| NAVSEA DWG No. 256-8498829 Rev -, Central Seawater Cooling System Diagram |
| 509 |
| 2.2 |
| NAVSEA Dwg No. 532-8498855 Rev - (NASSCO Dwg 471-342-7107, Low Temperature Freshwater Cooling System Diagram |
| 509 |
| 2.3 |
| Tech Manual T9532-AZ-MMC-010, Heat Exchangers, Plate/Frame Type Central Low Temp Fresh Water |
NAVSEA Drawing NO. 471-342-7104 REV D; “CARGO HOLD SPRINKLING SYSTEM DIAGRAM
NAVSEA Drawing 801-8193670, Rev A, SRD Fire Control Plan (T-AKE 5).
| 513 |
| 2.1 |
| MSC Standard Item No. 043, revised 02 April 1993, “Cleaning and Gas Freeing Tanks and Spaces”. |
| 513 |
| 2.2 |
| COMSCINST 4750.2C, Preservation Instruction for MSC Ships. |
| 513 |
| 2.3 |
| NAVSEA Drawing 523-7488761 Revision C {NASSCO drawing No. 471- 342-7155}, Counter Measure Wash Down System. |
| 514 |
| 2.1 |
| NAVSEA Dwg 556-7488740, Hydraulic Piping systems Diagram |
| 514 |
| 2.2 |
| MSC Dwg 556-8390670, Bow Thruster Lube Oil System Mod |
| 514 |
| 2.3 |
| T9568-A2-MMC-010, Bow Thruster Installation Manual, Type TT2200 |
| 514 |
| 2.4 |
| MSC General Technical Requirements (GTR) Dwg 803-7081122 |
| 514 |
| 2.5 |
| DWG 505-7488748, Flushing Criteria and Guidelines |
| 515 |
| 2.1.1 |
| NAVSEA Tech Manual T9593-DC-MMC-010, Marine Sanitation Device and Vacuum Collection, Holding and Transfer System for T-AKE |
| 515 |
| 2.1.2 |
| NAVSEA Dwg No. 528-7488743, Vacuum Sewage and Plumbing Drains System Diagram |
| 518 |
| 2.1 |
| NAVSEA 551-7488862, Rev G, Selected Record Drawing, T-AKE Class, High Pressure Air System Diagram |
| 518 |
| 2.2 |
| MSC Standard Drawing 803-7081122, Military Sealift Command General Technical Requirements (GTRs) |
| 518 |
| 2.3 |
| MSC SMS Procedure 2.1-004-All, Tagout/Lockout |
| 518 |
| 2.4 |
| NAVSEA Drawing No. 505-7488748 T-AKE 1 Class Flushing Procedures |
| 518 |
| 2.5 |
| MSC Drawing 631-7488891, T-AKE Class, Paint Schedule |
| 521 |
| 2.1 |
| NAVSEA Drawing No. 521-8498844 Rev -, Firemain System Diagram |
| 521 |
| 2.2 |
| NAVSEA Drawing No. 802-8498848 Rev -, General Arrangement |
| 521 |
| 2.3 |
| NAVSEA Drawing No. 635-7489072 Rev B, Insulation Schedule Pipe and Vent |
| 524 |
| 2.1 |
| MSC DWG No. 540-8393689, Rev Orig, Install Fuel Oil Drip Sampler |
| 524 |
| 2.2 |
| MSC DWG No. 541-84988847 Fuel Fill, Transfer and Purification System Diagram |
| 524 |
| 2.3 |
| MSC DWG No. 541-8498824 Cargo Fuel Systems Diagram |
| 606 |
| 2.1 |
| Technical Manual TS800-AE-MMC-010, Life Boat with Winch and Davit, Fassmer Type CL-C 11.5 |
| 606 |
| 2.2 |
| Technical Manual T9583-A8-MMC-010, Boat, Rescue With Davit and Winches |
| 606 |
| 2.3 |
| IMO MSC.1/Circ.1206, Measures to Prevent Accidents with Lifeboats |
| 606 |
| 2.4 |
| IMO MSC.1/Circ.1277 Interim Recommendation On Conditions for Authorization of Service Providers for Lifeboats, Launching Appliances and On Load Release Gear |
MSC Drawing No. 651-8392583, Second Deck Cargo Hold No. 6 Bulk Stowage and Cabinet Space Modifications
| 673 |
| 2.2 |
| MSC Drawing No. 802-7488866, Selected Record Drawing, General Arrangement |
| 673 |
| 2.3 |
| NAVSEA Dwg. 631-7488891 Rev. J; Paint Schedule |
| 673 |
| 2.4 |
| NAVSEA Dwg. 631-7489177 Rev. B; Non-skid Arrangement |
| 673 |
| 2.5 |
| MSC Standard Drawing 803-7061122, General Technical Requirements |
| 673 |
| 2.6 |
| MSC Standard Drawing 803-7080803, Computer Aided Designed (CAD) Drawing Standard |
| 801 |
| 2.1.1 |
| MSCLANT Standard Item No 14, Cleaning Galley Range Exhaust Ducts, Revised 2 April 1993 |
| 801 |
| 2.1.2 |
| NAVSEA 512-7488750 Rev F HVAC Diagram Accommodation Spaces (Sheets 1,12, and 17 Only) |
| 801 |
| 2.1.3 |
| MSC Dwg 500-8194018 HVAC System Mods (Sheet 3) |
| 801 |
| 2.1.4 |
| MSC Dwg 500-8194022 Scullery, Fast Serve Line, and Duty Mess HVAC Mods (Sheet 3) |
| 802 |
| 2.1 |
| MSC Standard Item No. 15 Cleaning Ventilation Systems (Revised 2 April 1993) |
| 802 |
| 2.2 |
| MSC Standard Items No. 16 Cleaning Ventilation Filter Screens (Revised 2 April 1993) |
| 802 |
| 2.3 |
| NAVSEA 512-7488750, Rev D, HVAC Diagram Accommodation Spaces |
| 901 |
| 2.1 |
| Trim & Stability Booklet, Dwg. 801-8388070 Rev-. |
| 901 |
| 2.2 |
| Docking Plan, Dwg. 801-8387195 Rev - |
| 901 |
| 2.3 |
| Capacity Plan, Dwg 801-8387182 Rev -. |
| 901 |
| 2.4 |
| Safety Certification Program for Dry-docking Facilities and Shipbuilding Ways for U.S. Navy Ships, MIL-STD 1625C(SH) |
| 901 |
| 2.5 |
| COMSC Instruction 9997.1A, Dry dock Standards for MSC Ship Availabilities |
| 902 |
| 2.1 |
| T/M T9568-A2-MMC-01A, Bow Thruster Installation Manual, Type TT2200 |
| 903 |
| 2.1.1 |
| NAVSEA Dwg 243-7488962 Rev F, Shaft Arrangement |
| 903 |
| 2.1.2 |
| T/M T9243-AZ-MMC-010 Fixed Pitch Propeller and Shafting with Bearings Model W084836780 |
| 903 |
| 2.1.3 |
| T/M T9561-BR-MMC-010 Steering Gear Rotary Vane, Model # RV 2150-3, and Shorthorn Rudder |
| 903 |
| 2.1.4 |
| Wartsila Dwg W084837233 Rev E, Assy Sterntube |
| 903 |
| 2.1.5 |
| Bot Groninger Dwg 1.1262/1/1 A1, Rudder Project Arrangement |
| 903 |
| 2.1.6 |
| Bot Groninger Dwg 3.1265/1.1 A3, Rudder Trunk Summary |
| 903 |
| 2.1.7 |
| Bot Groninger Dwg 2.1263/1.1 A3, Rudder Cone Coupling |
| 903 |
| 2.1.8 |
| Bot Groningen Dwg 2.1264/1.1 A3, Rudder Hydraulic Nut Summary |
| 903 |
| 2.1.9 |
| Wartsila Dwg W084827066, Assy Propeller Cap |
| 903 |
| 2.1.10 |
| Wartsila Dwg W084836779, Propeller Boss |
| 903 |
| 2.1.11 |
| Wartsila Dwg W084838596, Assy Propeller Hydraulic Nut |
| 903 |
| 2.1.12 |
| NASSCO Dwg 471-351-4984, Rope Guard Installation |
| 903 |
| 2.1.13 |
| Wartsila Dwg W084837232, Arrangement Shafting |
| 903 |
| 2.1.14 |
| Wartsila Dwg W007420313, Round Nut Locking |
| 903 |
| 2.1.15 |
| Wartsila Dwg 9AK30410AS3, Shaft Flange-9FC6-58 AS3 |
| 903 |
| 2.1.16 |
| T-AKE 1 Class Tail Shaft Optical Alignment- In Place Machining Support |
| 903 |
| 2.1.17 |
| T-AKE 1 Class Propeller Shafting- Static Bearing Reaction |
| 904 |
| 2.1 |
| TECHNICAL MANUAL T9243-AX-MMC-010, SHAFT SEAL, STERN TUBE, TYPE MD FOR USNS LEWIS AND CLARK (T-AKE 1) CLASS, INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS |
| 904 |
| 2.2 |
| WARTSILA LIPS Drawing H74985-01 Rev(C), GA of 750 MOD 712 Type MD Seal |
| 905 |
| 2.1.1 |
| MSC Standard Item 90, Underwater Hull Recoat 5 Year Ablative |
| 905 |
| 2.1.2 |
| NAVSEA Dwg. 603-7488868, Paint Lines and Draft Marks |
| 905 |
| 2.1.3 |
| Surface Preparation Standard SSPC-SP-12/NACE 5, Surface Preparation and cleaning of Metals by Water Jetting Prior to Coating. |
| 905 |
| 2.1.4 |
| PPG-PMC MSC Handbook (onboard ship) |
| 906 |
| 2.1.1 |
| Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. |
| 906 |
| 2.1.2 |
| Steel Structures Painting Council, Systems and Specifications, Volume 2, Eighth Edition |
| 906 |
| 2.1.3 |
| SSPC-PA 2, Measurement of Dry Coating Thickness with Magnetic Gages |
| 906 |
| 2.1.4 |
| SSPC-VIS-3 Visual Standard for Power and Hand Tool Cleaned Steel |
| 906 |
| 2.1.5 |
| Surface Conductivity Testing Procedure “Cell Retrieval Method Bresle Patch ISO 8502-6 |
| 906 |
| 2.1.6 |
| SSPC SP11, Power cleaning to Bare Metal |
| 906 |
| 2.1.7 |
| Surface Preparation Standard SSPC-SP-12/NACE 5, Surface Preparation and cleaning of Metals by Water Jetting Prior to Coating |
| 906 |
| 2.1.8 |
| PPG-PMC MSC Handbook |
| 906 |
| 2.1.9 |
| NAVSEA Dwg. 603-7488868, Paint Lines and Draft Marks |
| 909 |
| 2.1 |
| T/M T9633-AS-MMC-010, Cathodic Protection System Impressed Current |
| 910 |
| 2.1 |
| MSC Drawing 801-8387195 Rev -, Docking Plan |
| 910 |
| 2.2 |
| T/M T6435-CN-MMC-010, T-AKE Motor Operated Valves With Actuators |
| 910 |
| 2.3 |
| Sea Valves Status Spreadsheet |
| 911 |
| 2.1.1 |
| Surface Preparation Specifications, Steel Structures Painting Council Volume 2. |
| 911 |
| 2.1.2 |
| MSC Paint Handbook |
| 911 |
| 2.1.3 |
| NAVSEA Dwg. 631-7488891 Rev G, Paint Schedule |
| 911 |
| 2.1.4 |
| NAVSEA DWG. 581-7489016 Rev B, Anchor Handling Arrangement and Details |
| 913 |
| 2.1 |
| NASSCO Drawing No. 471-321-0004 Bilge Keel Rev A Bilge Keel Revision A |
| 913 |
| 2.2 |
| NASSCO Drawing No. 7489133 Rev B Bilge Keel & Hold Double Bottoms (BK Zone) |
| 914 |
| 2.1.1 |
| MSC Drawing No. 256-8386781 Rev (-), Central Seawater Cooling System Diagram |
| 914 |
| 2.1.2 |
| MSC Drawing No. 256-8386767 Rev (-), Auxiliary Seawater System Diagram |
| 914 |
| 2.1.3 |
| MSC Drawing No. 521-8386793 Rev (-), Firemain System Diagram |
| 914 |
| 2.1.4 |
| MSC Drawing No. 529-8386769 Rev (-), Ballast System Diagram |
| 914 |
| 2.1.5 |
| MSC Drawing No. 531-8386786 Rev (-), Distilling Plant System Diagram |
| 914 |
| 2.1.6 |
| NASSCO Dwg 73-87-441 |
| 916 |
| 2.1 |
| MSC Dwg 256-8498829 Rev -, Central Seawater Cooling System Diagram |
| 916 |
| 2.2 |
| MSC DWG 256-8390559, Rev -Central Seawater 30 Inch Waster Piece Mod |
| 1001 |
| 2.1 |
| NAVSEA DWG 5210545, Standard Painting Procedures for UNREP Equipment. |
| 1001 |
| 2.2 |
| MSCLANT Std. Item N0 54 “Recondition Motors, Squirrel Cage (AC) Services.” Latest revision |
| 1002 |
| 2.1 |
| NAVSEA Technical Manual S813-AD-MMA-010 Winch, Electric |
Hydraulic, Double-Drum, Hauling, Inhaul-Outhaul MK 4 MODS 1 and 2 (Aboard Ship)
| 1002 |
| 2.2 |
| MSCLANT Std Item No. 54 “Recondition Motors, Squirrel Cage (AC) Services” (latest revision). Shipyard will remove one side of the bearing shield from motor bearing if bearings are shielded on both sides |
| 1002 |
| 2.3 |
| NAVSEA Drawing 5210545, Standard Painting Procedures for UNREP Equipment |
NAVSEA DWG SK-08-18-14, Bumper, Transfer Head
| 1003 |
| 2.2 |
| NAVSEA DWG 5210545, Standard Painting Procedures for UNREP Equipment |
| 1004 |
| 2.1 |
| NAVSEA DWG 6243102, HP Air Relief Valve |
| 1004 |
| 2.2 |
| NAVSEA Dwg. No. 5210545, Standard Painting Procedures for UNREP Equipment |
GOVERNMENT FURNISHED MATERIAL (GFM) LISTING
USNS ROBERT E. PEARY (T-AKE 5)
| Work Item |
| GFM-Nomenclature |
Qty