16_T_3108_Amd_03-all_with_RFIs.pdf

PDF 44 KB Posted

Attached to
Portable Boiler System, Joint Base Pearl Harbor-Hickam, Hawaii
Solicitation number
N0060416T3108
Issued by

About this file

Amd 0003 with RFIs

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Last revised: 7/23/14

AMENDMENT 0003 – Revised Salient Characteristics. All other terms and conditions remain unchanged.

This is a COMBINED SYNOPSIS/SOLICITATION for commercial items prepared in accordance with the information in FAR Subpart 12.6, using Simplified Acquisition Procedures for Certain Commercial Items found at FAR 13.5, as supplemented with the additional information included in this notice. This announcement constitutes the only solicitation;

a written solicitation will not be issued. PAPER COPIES OF THIS SOLICITATION WILL NOT BE AVAILABLE. This combined synopsis/solicitation SHALL be posted on both FEDBIZOPPS and NECO (https://www.neco.navy.mil/).

The RFQ number is N00604-16-T-3086. This solicitation documents and incorporates provisions and clauses in effect through FAC 2005-87 and DFARS Publication Notice 20160325. It is the responsibility of the contractor to be familiar with the applicable clauses and provisions. The clauses may be accessed in full text at these addresses:

https://www.acquisition.gov/far/ and http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html.

The NAICS code is 332410 and the Small Business Standard is 750 Employees. This proposed contract action is 100% set aside for small business concerns, therefore, manufacturers of the boilers must also be small business concerns. The Small Business Office concurs with the set-aside decision.

The Government is seeking New Equipment ONLY; NO remanufactured, refurbished, or "gray market" items. All items must be covered by the manufacturer's warranty.

The NAVSUP FLC Regional Contracting Department Pearl Harbor requests quotes from qualified sources capable of providing:

Description QTY Unit of Issue Extended Total

0001 Portable Boiler System 1 Each $___________ See Attachment 1 for “or equal” requirements.

FOB Destination to:

NAVFAC Hawaii Building 44 Joint Base Pearl Harbor-Hickam, Pearl Harbor, Hawaii

Delivery: 10 Weeks After Date of Contract, FOB Destination

Quotes are to be submitted with drawings and specifications in sufficient detail to allow for a comprehensive evaluation to ensure that the portable boiler system meets or exceeds the salient characteristics stated in Attachment 1. If you do not submit drawings and specifications that are in sufficient detail to allow for a comprehensive evaluation, your quote will be evaluated Unacceptable. Please be advised that if your submissions are not clear, your quote may be evaluated Unacceptable.

Basis for Award: Lowest Price Technically Acceptable (LPTA)

The Government intends to award a contract action resulting from this synopsis-solicitation to the responsible offeror whose quote, conforming to this solicitation, is evaluated to be the lowest priced technically acceptable (LPTA) quote. The Government also intends to award a contract action on initial quotes without conducting discussions, however, the Government reserves the right to conduct discussions, if deemed necessary, with the offerors that submitted the most highly rated quotes, price and technical considered.

The ratings for the technical factors shall be Acceptable or Unacceptable. The following factors shall be used to evaluate quotes. Experience and Past Performance are the technical factors.

Factor 1 – Meets or Exceeds Technical Criteria

Factor 2 - Past Performance (no less than Satisfactory/Acceptable performance ratings)

AMENDMENT 0003. Areas of revision are annotated with a line in the right side margin.

1. Plant Equipment: The MSPT unit shall be configured within the WABASH or EQUAL trailer with the following equipment:

(a) Packaged Boiler room, Apache Model 8-5-400-S150 or equal, 80 HP, 150 PSI with powerflame full modulating propane burners. Boiler will operate at 10 PSI to 125 PSI. Maximum 80 HP, ASME Section 1 construction, LPG propane gas fired, powerflame forced draft burner, dual motorized gas valves, ASME CSD-1 compliant; full modulation, primary & secondary flame failure, equipped with a float type primary and probe type secondary (Manual reset) low water cutoff (LWCO), Minimum 8" steam pressure gauge, low-fire hold, operating limit control, modulating control, high limit control, minimum 4 inch, 250 lb. flanged steam outlet, 4 inch, 250 lb.

OS&Y steam stop valve, 1-1/4 inch feed-stop and check valve assembly, 1-1/4 inch quick and slow blowdown valves. Electrical requirements: 240 volt/60 Hz/3 phase with emergency shutdown disconnect switch outside of trailer as required by ASME CSD-1. Water softener is not required.

(b) Tank, Feedwater System: ATLANTIC packaged feedwater system or equal, minimum 100 gallon duplex feedwater tank, 100 gallon receiver capacity, stainless steel, receiver, 3 inch boxed tube stand, 16 inch manway, 2 inch perforated stainless steel diffuser tube (tank heater assembly), chemical injection quill, solenoid make-up valve assembly, dual GRUNDFOS feedwater pumps, one standby, NEMA-1 Control panel, Motor Starter, Fuses, Control Transformer hand-off-auto selector switch for each pump, running indicator lights for each pump, pump selector switch with pump indication light; 22 gauge stainless steel jacket with 2 inch insulation, SPIRAX-SARCO steam temperature control valve assembly. Electrical requirements: 240 volt/60Hz/3 phase.

(c) Chemical Feed Unit: HELWIG 50 gallon chemical feed system or EQUAL, Poly/steel vertical receiver, 50 USG capacity, plastic hinged lid assembly, agitator assembly, piston pump. Electrical requirements: 120 volt/60Hz/single phase.

(d) Sampling Sink: Stainless steel with drain.

(e) Blowdown Separator: PENN A34B or EQUAL, 4 inch drain, 4 inch vent, 2 inch inlet, STERLCO drain tempering assembly.

(f) Gas Vaporizer: Algas-DF LPG Electric Vaporizer, 80 gph capacity, 7.2 MMBtu, 160 Kg/Hour or equal.

(g) Interior Lighting, Vapor-tight Fixtures: Ceiling, 200w max, 120v.

(h) Associated pressure safety controls as required by ASME CSD-1 AND ANSI specifications.

(i) Associated electrical panels and disconnects: 480/60/3, 240/60/3, 120/60/1

(j) Operators Desk: a writing platform to log in the boiler check and conditions.

(k) Fresh water hose bib

(l) 120V GFCI electrical receptacle

(m) Fresh air exhaust fan

(n) Burner combustion air louvers

(o) Liquefied propane to be fed into the trailer, which will pass throught the varporizer and then to the boiler.

(p) provide vaporized propane connection to the exterior of the trailer.

(q) Return condensate coming back to the trailer is not required.

(r) Emissions/noise limitations are to be based on factory recommendations.

1. The van trailer is listed as 35'. This is a non-standard van trailer length but 53' is a standard length.

I just wanted to confirm that this was not a misprint.

ANSWER: 40 FT MAXIMUM.

2. Am I correct in assuming that you will be feeding liquefied propane into the trailer, which will pass through the vaporizer, and then to the boiler?

ANSWER: YES.

a. Will the vaporized propane need to feed any other equipment besides the portable boiler system?

ANSWER: NO

b. IE Do you want a vaporized propane connection on the exterior of the trailer?

ANSWER: YES

3. Do you know what percentage of condensate return will be coming back to the trailer?

ANSWER: RETURN CONDENSATE NOT REQUIRED.

4. Do you know what pressure the boiler itself will operate at? This is necessary to correctly size the Spirax Sarco steam valve for pre-heating the feedwater.

ANSWER: YES. 10 PSI TO 125 PSI.

5. I noticed that a water softener was not included in the specification. A water softener is normally considered necessary to prevent the boiler from being fouled. Is this something you would be interested in?

ANSWER: NO, A WATER SOFTENER IS NOT REQUIRED.

6. Are they any emissions/NOx limitations that the burner will need to adhere to?

ANSWER: EMMISSIONS AND NOISE LIMITATIONS ARE TO BE BASED ON FACTORY

RECOMMENDATIONS.

7. Would you consider an ISO shipping container mounted to a chassis rather than a van trailer? This would result in a higher quality unit for NAVFAC due to structural limitations of van trailers. It would also present better lashing options for protection against seismic disturbances.

ANSWER: NO, PLEASE PROVIDE TRAILER AS SPECIFIED.

8. Will you require a technician to visit NAVFAC for training and/or commissioning?

ANSWER: CONTRACTOR SHALL PROVIDE FOR OPERATIONAL TESTING AT DESTINATION.

9. The specification calls for an Apache Model 8-5-400-S150 boiler with a Powerflame burner. It does not state or equal as it does on some of the other equipment. Does that mean than we cannot bid a similar boiler from another manufacturer with the same specifications as this boiler or is it required that we bid this boiler only?

ANSWER: “OR EQUAL” WAS INADVERTENTLY OMITTED. PLEASE SEE REVISED SALIENT

CHARACTERISTICS.

2. MOBILE TRAILER: The MSPT unit shell consists of a new WABASH Freight Pro Dry Van Trailer or EQUAL;

Maximum: length 40’, height 10’, width 9’; tandem axle; air service brakes; lighting system that meets DOT requirements; road operable; equipped with a 4 foot by 6 foot 8 inch side door with ladder (street side).

3. OPERATING & MAINTENANCE MANUALS: Three (3) sets of manuals with general arrangement, Piping and Instrumentation Diagram (P & ID), and electrical drawings at time of delivery.

4. Contractor to provide operational testing of the boilers at destination.

5. SPARE PARTS: 90 day boiler service kit to support unit operation.

AND

Factor 3 – Price.

Submission Requirements and Evaluation:

Factor 1 –Submit specifications and drawings for the portable boiler system that clearly show that your product meets or exceeds the salient characteristics stated in Attachment 1. If you do not submit drawings and specifications in sufficient detail to allow for a comprehensive evaluation, your quote will be evaluated Unacceptable.

Factor 1 - Experience

Rating Description

Acceptable (A) Product clearly meets or exceeds the minimum specifications.

Unacceptable (U) Product does not clearly meet the minimum specifications.

Factor 2 – Do not submit past performance information. The Government will access the Past Performance Information Retrieval System (PPIRS) to obtain past performance information on your firm’s performance record for the delivery of water storage tanks, utilizing the DUNS number obtained from the Systems for Award Management (SAM) website. If no past performance information is available, Factor 2 will be evaluated Neutral, which is considered Acceptable. If your firm has less than Satisfactory performance evaluations in PPIRS, you may submit acceptable explanations for the ratings for the Government’s consideration. Acceptable explanations will result in an Acceptable rating for Past Performance.

Factor 2 – Past Performance

Ratings Description

Acceptable (A) Based on the performance records, the Government has a reasonable expectation that the quoter will successfully deliver the water storage tanks or the quoter’s performance record is unknown (see definition below).

Unacceptable (U) Based on the performance records, the Government has no reasonable expectation that the quoter will be able to successfully deliver the water storage tanks.

Unknown (UNK) In the case of a quoter without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the quoter may not be evaluated favorably or unfavorably on past performance. Therefore, the quoter shall be determined to have Unknown past performance. In the context of acceptability/unacceptability, Unknown shall be considered ‘Acceptable.”

In order to be evaluated overall Acceptable, a rating of Acceptable shall be obtained for both Factors 1 and 2. If either one or both are rated Unacceptable, the entire technical quote will be rated Unacceptable and will be removed from further consideration for award.

Price. The Government will evaluate all prices received from the lowest to the highest. Price shall include shipping to Building 44, JBPHH, Hawaii.

The Government will take the five lowest quotes received and evaluate the corresponding technical factors for acceptability.

Should the Government identify one quote that represents the lowest priced technically acceptable quote, the Government may make an award as long as the total evaluated price can be determined fair and reasonable. Should there be no technically acceptable quote among the first five lowest quotes, the Government will evaluate the next five lowest quotes for technical acceptability. The Government will continue this method of evaluation until a quote is evaluated to be the lowest priced technically acceptable quote with a reasonable price.

Award will only be made to a firm that is determined to be responsible in accordance with FAR Part 9.

Submission Requirements: By submission of a quote, the quoter agrees to all requirements contained in this solicitation.

Offerors shall include with their quotes the following, as well as any additional information and certifications with reference to the provisions contained herein:

1) A price for CLIN 0001.

2) Submission of specifications and drawings documenting that the portable boiler system meets or exceeds the salient characteristics stated in Attachment 1. Failure to submit specifications and drawings will render a quote Unacceptable.

3) Point of contact name, phone number, and email address. CAGE and DUNS numbers. Business size.

Discount payment terms, if any.

4) A completed copy of 52.212-3 and its ALT I (Attachment 2). If the quoter has completed the annual representations and certification electronically via the System for Award Management (SAM) Web Site, the quoter shall only complete paragraph (b) of this provision. If the quoter fails to submit a completed Attachment 2, the quote may be evaluated Unacceptable.

5) A completed copy of FAR 52.209-11, (Attachment 3). If the quoter fails to submit a completed Attachment 3, the quote may be evaluated Unacceptable.

6) A completed copy of FAR 52.204-20, (Attachment 4). If the quoter fails to submit a completed Attachment 4, the quote may be evaluated Unacceptable

Payment will be made by NAVFAC Hawaii Comptroller office via EFT.

Responsibility and Inspection: Unless otherwise specified in the order, the supplier is responsible for the performance of all inspection requirements and quality control prior to shipping of the tanks. The Government will retain the right to inspect and accept the tanks at destination.

The following FAR provision and clauses are applicable to this procurement:

52.203-3 Gratuities 52.203-6 with Alt I Restrictions on Subcontractor Sales to the Gov't 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards 52.204-7 System for Award Management 52.204-13 SAM Maintenance 52.204-16 Commercial and Government Entity Code Reporting 52.204-18 Commercial and Government Entity Code Maintenance 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations—Representation 52.209-5 Certification Regarding Responsibility Matters 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or

Proposed for Debarment 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations 52.211-6 Brand Name or Equal 52.212-1 Instructions to Offerors - Commercial Items 52.212-3 and its ALT I, Offeror Representations and Certifications - Commercial Items 52.212-4 Contract Terms and Conditions - Commercial Items 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders – Commercial Items 52.219-6 Notice of Total Small Business Set-Aside 52.219-8 Utilization of Small Business Concerns 52.219-14 Limitations on Subcontracting 52.219-28 Post Award Small Business Program Representation 52.222-3 Convict Labor

52.222-19 Child Labor—Cooperation with Authorities and Remedies 52.222-21 Prohibition of Segregated Facilities 52.222-22 Previous Contracts and Compliance Reports 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran--Reps and Certs 52.222-26 Equal Opportunity 52.222-35 Equal Opportunity for Veterans 52.222-36 Affirmative Action for Workers with Disabilities 52.222-37 Employment Reports on Disabled Veterans 52.222-40 Notification of Employee Rights Under the National Labor Relations Act 52.222-50 Combating Trafficking in Persons 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving 52.225-13 Restriction on Foreign Purchases 52.232-33 Payment by Electronic Funds Transfer – SAM 52.232-39 Unenforceability of Unauthorized Obligations 52.232-40 Providing Accelerated Payments to Small Business Subcontractors 52.233-2 Service of Protest 52.233-3 Protest After Award 52.233-4 Applicable Law for Breach of Contract Claim 52.247-34 FOB Destination 52.252-1 Solicitation Provisions Incorporated by Reference 52.252-2 Clauses Incorporated by Reference

Quoters are reminded to include a completed copy of 52.212-3 and its ALT I with quotes. All clauses shall be incorporated by reference in the order. Additional contract terms and conditions applicable to this procurement are:

252.203-7000 Requirements Relating To Compensation of Former DoD Officials 252.203-7002 Requirement to Inform Employees of Whistleblower Rights 252.203-7005 Representation Relating To Compensation of Former DoD Officials 252.203-7996 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements —

Representation (Dev 2016-O0003) 252.203-7997 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements (Dev

2016-O0003) 252.204-7003 Control of Government Personnel Work Product 252.204-7004 Alt A System for Award Management 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls 252.204-7011 Alternative Line Item Structure 252.204-7012 Safeguarding of Unclassified Controlled Technical Information 252.204-7015 Disclosure of Information To Litigation Support Contractors 252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State

Sponsor of Terrorism 252.211-7003 Item Identification & Valuation 252.213-7000 Notice to Prospective Suppliers on Use of PPIRS-SR in Past Performance Evaluations 252.222-7007 Representation Regarding Combating Trafficking in Persons 252.223-7008 Prohibition of Hexavalent Chromium 252.225-7035 Buy American Act-Free Trade Agreements-Balance of Payments Program Certificate 252.225-7036 Buy American Act-Free Trade Agreements-Balance of Payments Program 252.225-7002 Qualifying Country Sources as Subcontractors 252.225-7048 Export-Controlled Items 252.232-7010 Levies On Contract Payments 252.243-7002 Requests for Equitable Adjustment 252.244-7000 Subcontracts For Commercial Items And Commercial Components (DoD Contracts) 252.247-7023 Transportation of Supplies by Sea

This announcement will close at 10:00AM HST on June 29, 2016. Quotes must be received via email to norine.horikawa@navy.mil by this time and date to be considered responsive. Questions shall be submitted to Norine

Horikawa via email at norine.horikawa@navy.mil by 10:00AM HST on June 23, 2016. Oral communications are not acceptable in response to this notice. All responsible sources may submit a quote which shall be considered by the agency.

System for Award Management (SAM). Quoters must be registered in the SAM database to be considered for award.

Registration is free and can be completed on-line at http://www.sam.gov/.

Attachments (Attachments 2 through 4 are combined in one PDF file) Attachment 1 Salient Characteristics, Amendment 0003 Attachment 2 FAR 52.212-3 and ALT 1 Attachment 3 FAR 52.209-11 Attachment 4 FAR 52.204-20

******* End of Combined Synopsis/Solicitation ********