Exhibit_B_RAAF-IDIQ_Part_A_CDRLs.docx

DOCX document 300 KB Posted

Attached to
P-8A Airframe and Engine Depot Maintenance Competition Federal contract opportunity
Solicitation number
N00019-15-R-2004
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

Exhibit B

View the file

Other files for this federal contract opportunity

Other files attached to P-8A Airframe and Engine Depot Maintenance Competition, newest first.
File Type Posted
Attachment_12_DD254Rev_001.pdf PDF
Att_L-9_Prime_Contractor_Tech_Directives_FFP.xlsx XLSX spreadsheet
Att_L-9_Prime_Contractor_Tech_Directives_FFP_Amendment_0007.xlsx XLSX spreadsheet
Att_L-9_Prime_Contractor_Tech_Directives_FFP_Amendment_0006.xlsx XLSX spreadsheet
Exhibit_D_RAAF-OY1_Part_A_CDRLs.docx DOCX document
Exhibit_L_NAVY-OY5_Part_A_CDRLs.docx DOCX document
Exhibit_Z_RAAF-OY3_Part_B_CDRLs.docx DOCX document
Exhibit_AL_FMS-OY2_Part_B_CDRLs.docx DOCX document
Exhibit_AH_FMS-OY1_Part_B_CDRLs.docx DOCX document
Exhibit_AA_NAVY-OY4_Part_B_CDRLs.docx DOCX document
Exhibit_M_RAAF-OY5_Part_A_CDRLs.docx DOCX document
Exhibit_AQ_FMS-OY4_Part_B_CDRLs.docx DOCX document
Exhibit_S_NAVY-IDIQ_Part_B_CDRLs.docx DOCX document
Exhibit_W_NAVY-OY2_Part_B_CDRLs.docx DOCX document
Exhibit_AB_RAAF-OY4_Part_B_CDRLs.docx DOCX document
Exhibit_AS_FMS-OY5_Part_B_CDRLs.docx DOCX document
Exhibit_E_NAVY-OY2_Part_A_CDRLs.docx DOCX document
Question_306_for_posting.docx DOCX document
Q_287-295_for_posting.pdf PDF
Att_L-5_Price_Matrix_Amendment_2.xlsx XLSX spreadsheet
Att_L-7_Prime_Contractor_Cost_Summary_FFP_Amendment_2.xlsx XLSX spreadsheet
USN_Engine_EGTM_Trend_Summary.pdf PDF
Q_255-284_for_posting.pdf PDF
Att_L-5_Price_Matrix_Amendment_1.xlsx XLSX spreadsheet
Exhibit_V_RAAF-OY1_Part_B_CDRLs.pdf PDF
Exhibit_Z_RAAF-OY3_Part_B_CDRLs.pdf PDF
Exhibit_M_RAAF-OY5_Part_A_CDRLs.pdf PDF
Exhibit_K_RAAF-OY4_Part_A_CDRLs.pdf PDF
Exhibit_U_NAVY-OY1_Part_B_CDRLs.pdf PDF
Exhibit_F_RAAF-OY2_Part_A_CDRLs.pdf PDF
Exhibit_W_NAVY-OY2_Part_B_CDRLs.pdf PDF
Exhibit_C_NAVY-OY1_Part_A_CDRLs.pdf PDF
Exhibit_AD_RAAF-OY5_Part_B_CDRLs.pdf PDF
Exhibit_AC_NAVY-OY5_Part_B_CDRLs.docx DOCX document
Exhibit_S_NAVY-IDIQ_Part_B_CDRLs.docx DOCX document
Attachment_16_DD_Form_1921.xls XLS spreadsheet
Attachment_1__P-8A_SOW.docx DOCX document
Exhibit_M_RAAF-OY5_Part_A_CDRLs.docx DOCX document
Att_L-2_Vol_2_T-1_SB_Goals_Combined.xlsx XLSX spreadsheet
Exhibit_T_RAAF-IDIQ_Part_B_CDRLs.docx DOCX document
Attachment_10_DD_Form_1921-5.xlsx XLSX spreadsheet
Exhibit_N_NAVY-OY6_Part_A_CDRLs.docx DOCX document
Attachment_11_Engine_Part_Condition_Assessment_Template.docx DOCX document
Exhibit_AA_NAVY-OY4_Part_B_CDRLs.docx DOCX document
N00019-15-R-2004.pdf PDF
Exhibit_F_RAAF-OY2_Part_A_CDRLs.docx DOCX document
Att_L-9_Prime_Contractor_Tech_Directives_FFP.xlsx XLSX spreadsheet
Att_L-1_Vol_1_ES_Tables_Combined.xlsx XLSX spreadsheet
Exhibit_V_RAAF-OY1_Part_B_CDRLs.docx DOCX document
Exhibit_C_NAVY-OY1_Part_A_CDRLs.docx DOCX document
Show all 50

P-8A Airframe and Engine Depot Maintenance Competition has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Data Requirements List (DD 1423’s) for

Airframe Depot Maintenance of United States Navy P-8A Poseidon Aircraft

Exhibit B Contract Data Requirements List (DD 1423’s) 18 May 2016

EXHIBIT B – IDIQ CDRLs (RAAF)

DIN TITLE SUBTITLE

B001RESERVED
B002RESERVED
B003RESERVED
B004RESERVED
B005RESERVED
B006RESERVED
B007RESERVED
B008RESERVED
B009Scientific and Technical ReportsRAAF Structural Alteration Report
B00ARESERVED
B00BScientific and Technical ReportsRAAF Aircraft Mishap Damage Report
B00CRESERVED
B00DScientific and Technical ReportsRAAF Depot/In-field Completion Report
B00ERESERVED
B00FEngineering Services Memorandum (ESM)RAAF Aircraft Field Assessment Report
B00GRESERVED
B00HQuality Deficiency ReportRAAF Deficiency Reporting
B00JScientific and Technical ReportsRAAF Impact Assessment Report
B00KRESERVED
B00LScientific and Technical ReportsRAAF Initial Assessment Report
B00MRESERVED
B00NRESERVED
B00PInternal Contractor Technical DataRAAF Utilization Approval of Used, Rebuilt,ReportRAAF Overhauled Parts
B00QOver and Above Status ReportRAAF Status Report
B00RSustainment Functional Cost-Hour ReportRAAF Contractor Cost Data Reporting
B00SCost Data Summary ReportContractor Cost Data Reporting (CCDR)
B00TContractor Work Breakdown StructureCWBS Dictionary

CONTRACT DATA REQUIREMENTS LIST

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

TDP

TM

OTHER

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B001

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

B002

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B003

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B004

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B005

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Derick Diaz P-8A Aircraft Systems IPTL

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B006

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B007

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B008

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B009
Scientific and Technical Report
RAAF Structural Alteration Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80711A (See Block 16)
SOW 3.6, 3.8, 4.1.4.6, 4.2.2, 5.3.4.4, 6.4,
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Items to be included in the report are as follows (if applicable):

· Technical description of the completed assessment and repair including Aircraft BUNO, component serial number and location during repair, induction date, repair type, repair work, other.

· List of nomenclature/part number(s)/material used in the repair

· Contractor labor codes/titles and associated hours as well as days for repair

· Applicable weight and balance information

· Certificates of compliance or completion

· Other applicable items or remarks of note

· FAA Form 337 / FAA Form 8130-3 (as required)

· Aircraft Inventory Record (AIR) OPNAV 4790/111 (MRO)

· Acceptance Test results (as required)

BLOCK 8: Government comments will be provided to the contractor NLT 30 days after receipt of contractor submittal. Revised contractor submittal shall be provided within 30 days after receipt of Government comments.

BLOCKS 12 & 13: Due NLT 15 days following Government acceptance of aircraft.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail..

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

TDP

TM

OTHER

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00A

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
1
of
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00B
Scientific and Technical Reports
RAAF Aircraft Mishap Damage Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80711A (See Block 16)
SOW 8.15
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
N/A
D
N/A
ASREQ
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Report shall include the following:

· Identify and report nature of mishap

· Provide information necessary to complete mishap data report specified in OPNAV Instruction 3750.6 series (worksheet)

· Estimated material cost to repair damage

· Estimated labor hours and other direct costs to repair the aircraft

· Estimated date to make aircraft serviceable

BLOCK 12: Due 6 hours after aircraft mishap and the Contractor shall report by phone any accident or incident to COR/TPOC.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00C

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr

16. REMARKS

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00D
Scientific and Technical Reports
RAAF Depot/In-Field Completion Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80711A (See Block 16)
SOW 3.6, 4.1.5.1, 4.1.5.3, 4.2.2, 4.3,4.4, 5.3.4.1, 6.4, 8.20
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
N/A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Contractor format is acceptable. Report shall contain:

1. Complete list of all maintenance performed on the aircraft while at Depot facility or In-field.

2. FAA Form 337 / FAA Form 8130-3 (as required)

3. All warranty documentation, if applicable.

4. Government/Commercial log book, entries.

5. Weight and Balance Documentation, IAW NA 01-1B-50 as required.

6. All over & above completed.

7. Noted but Not Corrected (NBNC)

8. Parts Required Report (PRR)

BLOCKS 12 & 13: Report due at the time of government acceptance of aircraft.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail..

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00E

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr
16. REMARKS
See Block 16

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00F
Engineering Services Memorandum (ESM)
RAAF Aircraft Field Assessment /Repair Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80748 (See Block 16)
SOW 4.2.1, 6.1
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
N/A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Deliver in a Microsoft Office format (2010 or later); such as, Excel or Access.

Report shall include:

· Date of submittal

· Aircraft Assessment Date

· Component Serial Number

· Aircraft BUNO

· Shipping Activity (FRC/MALS)

· Primary failure item nomenclature

· Primary failure item part number

· Primary failure item failure mode

· Major Structural Repairs

· All temporary structural repairs

· Need for proposed work

· Description of findings/comments (including major discrepancies/work to be performed and resulting benefits)

· Estimated cost/BOE for engineering, materials and equipment and/or services with FAR required proposal supporting documentation and information

· GFE required

· Estimated turn-around time (TAT) and completion date

· Signature/Title

BLOCKS 12 & 13: Due within 4 working days after assessment personnel arrival at the aircraft site, unless significant damage requires further negotiation.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00G

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr
16. REMARKS
See Block 16

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

QCIC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00H
Quality Deficiency Report
RAAF Deficiency Reporting
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-QCIC-80736 (See Block 16)
SOW 8.14
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
N/A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Deliver in a Microsoft Office format (2010 or later); such as, Word, Excel or Access.

The investigation Report should include, at a minimum, the following data:

· Identify and report deficiency of item

· Identify and report the cause of deficiency for that item

· Recommendations to the Government to alleviate future failures of item

· Manufacture’s recommendations for the correction of deficiency

· Information from the following reports submitted against defective items manufactured, repaired, or overhauled by the Contractor or a Sub-Contractor including vendor parts issued through the On-Site Storeroom:

a. Product Quality Deficiency Report (PQDR)

b. Engineering Investigation (EI)

c. Material Deficiency Report (MDR)

d. Acceptance Inspection Deficiency Report (AIDR)

e. Aircraft Deficiency Report (ADR)

f. Hazardous Material Report (HMR)

g. Technical Publication Deficiency Report (TPDR)

BLOCK 12: Due 30 days after investigation request

BLOCK 13: Due monthly to arrive at PMA-290 NLT the last day of the month, until investigation completion.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00J
Scientific and Technical Report
RAAF Delay Notification Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80711A (See Block 16)
SOW 3.5, 4.1.3
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: The Contractor shall deliver an initial Delay Notification Report detailing estimated TAT following completion of the initial inspection/assessment.

The Contractor shall utilize the established Delay Notification Process. This process uses the DNF to document delays during modification or maintenance activity. The DNF details changes in the delivery schedule (TAT) associated with excusable delays as outlined in FAR 52.249-14, including contractor caused delays, duration-based delays, and hours-based delays as calculated per Attachment 7.

The Delay Notification shall include: the relevant contractor Notification Form (DNF) and a technical narrative describing the causes of the impact with relevant backup documentation as follows:

-Funding Related Delays: Contract Letter submitted in accordance with FAR 52.249-14 to request additional funding and any subsequent letters related to work delays or stoppages.

-Parts and GFM Related Delays: Based upon scheduled start date from associated work ticket.

-Warranty Claims - Contract Letter submitted to document warranty claims on GFE/GFM

Continued next page

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

A. CONTRACT LINE ITEM NO.

B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD

16. REMARKS (Continued) (B00J)

Late Contract Changes - Contract Letters and Contract Modifications to document changes or late award of additional scope.

-Contractor Caused Delays -Contractor will provide relevant documentation to explain the reason for delay. No TAT relief will be granted for these delays.

BLOCK 12: First submission will be within 10 days of discovering delays to the original established TAT as determined by the Initial Impacted Assessment , based upon Estimate at Complete (EAC), of the aircraft. Extensions may be requested pending completion of the AEPD Inspections.

BLOCK 13: Subsequent submissions will be as required, but not to exceed monthly, with a Final Impact Assessment submitted within 30 Days of DD250 of the aircraft. The final impact assessment shall include Over and Above related delays. The contractor will provide all over and above completed documented in CDRL B00Q, Over and Above (O&A) Status Report. TAT extensions shall be granted based upon the total number of O&A Hours negotiated. The final impact assessment will also include a summary of all duration based delays.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00K

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr
16. REMARKS
See Block 16

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

MISC

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00L
Scientific and Technical Report
RAAF Initial Assessment Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-MISC-80711A (See Block 16)
SOW 3.3, 4.1.2,
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
A
D
N/A
ASREQ
Reg
Repr
16. REMARKS
See Block 16

BLOCK 4: Contractor format acceptable The Contractor shall deliver the following information for each aircraft: contract number, delivery order number, bureau number, contractual induction date, actual induction date, O&A hours expended to date, O&A hours estimated at completion, contractual delivery date, estimated delivery date, schedule impacts (with a narrative to explain reason for impacts), proposed material cost, number of DRs negotiated, number of DRs to be negotiated, total DRs, list of major discrepancies, and list of minor discrepancies.

BLOCK 8: Government comments will be provided to the contractor NLT 30 days after receipt of contractor submittal. Revised contractor submittal shall be provided within 30 days after receipt of Government comments.

BLOCK 12: The Contractor shall deliver the report no later than 10 days after the completion of AEPD look phase.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:

X

D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00M

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr
16. REMARKS
See Block 16

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
D. SYSTEM|ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00N

4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
Reg
Repr
16. REMARKS
See Block 16

RESERVED

15. Total

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
Page
1
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget. Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract|PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
0037
B
TDP

TM

OTHER

SESS

X

D. SYSTEM|ITEM

E. CONTRACT/PR NO.
F. CONTRACTOR
P-8A Poseidon Depot Maintenance-Airframe
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B00P
Internal Contractor Technical Data Report
RAAF Utilization Approval of Used, Rebuilt, Overhauled Parts
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED TOTAL PRICE

DI-SESS-81309A (See Block 16)
SOW 8.11.1
PMA-290
7. DD 250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION

LT

ASREQ
See Block 16

b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
a. ADDRESSEE
DRAFT
FINAL
A
D
N/A
See Block 16
Reg
Repr
16. REMARKS
See Block 16
1
1

BLOCK 4: Items to be included in the report are as follows (if applicable):

· Approved FAA Form 8130-3

· Complete set of all maintenance, inspection, and service usage records including accumulated cycles / hours and operators

· Service life remaining for any life-limited part

BLOCK 8: Government comments will be provided to the contractor NLT 30 days after receipt of contractor submittal. Revised contractor submittal shall be provided within 30 days after receipt of Government comments.

BLOCKS 12 & 13: Due NLT 15 days following Government acceptance of each engine.

BLOCK 14: All deliverables shall be delivered via the AMRDEC website along with 1 CD ROM to the MPRA Library. If the AMRDEC is not available, the Contractor shall ensure the delivery of electronic media via CD ROM to the PMA-290 Data Manager sent via overnight mail.

15. Total

1
1
G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE

Don Griffin P-8A Airframe Commercial Depot IPT Lead

Donnie LaRocco

DD FORM 1423-1, JUN 90 (EG)
Previous editions are obsolete
1
of
of
1
Pages

Form Approved

(1 Data Item)

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding thus burden estimate or any other aspect of this collection o f information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington,…