Solicitation M6740020Q0087 Amendment questions and answers.pdf

PDF 143 KB Posted

Attached to
Uninterruptible Power Supply (UPS) Removal and Replacement
Solicitation number
M6740020Q0087
Issued by

About this file

This document provides answers to questions regarding solicitation M6740020Q0087 for the uninterruptible power supply (UPS) removal and replacement project at Building 480, Marine Corps Base Camp Foster in Okinawa, Japan. The solicitation requires contractors to engineer, furnish, install, test, and commission a new scalable UPS system between 200-600 kilo volt amperes to replace two existing 750 kVA UPS units. Contractors must also remove, recycle, and dispose of the current UPS components and 540V battery system, and maximize reuse of existing panels when feasible. The response due date was extended to September 22, 2020. The performance work statement was clarified to replace rather than reuse the existing batteries. The project must be completed within 180 days of award and conducted during standard business hours with provisions for typhoon conditions.

View the file

Other files

File Type Posted
M6740020Q0087 Amendment 3.pdf PDF
Okinawa Service Report.pdf PDF
M6740020Q0087 Amendment 1.docx DOCX document
Attachment_1_480_UPS_Removal_and_replacement.xlsx XLSX spreadsheet
Attachment_6_Feeder_Schedule.pdf PDF
Attachment_3_Electrical_floor_plan_CROP.pdf PDF
M6740020Q0087.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide answ ers to questions submitted regarding the solicitation, extend the solicitation due date and modify the PWS. A service report for the UPS has been attached to Beta.SAM.Gov. See summary of changes for details

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X M6740020Q0087

X 9B. DATED (SEE ITEM 11)

17-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0002

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Sep-2020

CODE

MCIPAC REGIONAL CONTRACTING OFFICE

MCB CAMP S.D. BUTLER

OKINAWA 904-0100

M67400 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

M6740020Q0087

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 16-Sep-2020 08:00 AM to 22-Sep-2020 10:00 AM.

The following have been added by full text:

QUESTIONS AND ANSWERS

Solicitation M67400-20-Q-0087

UNINTERRUPTIBLE POWER SUPPLY REPLACEMENT TO INCLUDE INSTALLATION

Questions and Answers (Q&A) Number RFQ Section: Page #, Paragraph # Questions and Answers

1 Page 5, PWS para 3.2.1 Q: The current data center load is approximately 150 kVA and a scalable UPS is required to meet possible future data center requirements. – Is 600 kVA a specific requirement, or just an approximate number for growth? If space and cost benefits can be proven could the system be designed to scale to 500 kVA 500 kW instead?

A: Section 3.2.1 requests the contractor design a solution for “a UPS that is scalable from approximately 200 kilo volt amperes (kVA) to 600 kVA. Your design should support a load between 200-600 kVA and be scalable if more capacity is required.

2 Page 5, PWS para 3.2.1 Q: PWS section 3.2.1 states: “The contractor shall provide a 3-phase, 480 volts alternating current (VAC) redundant and scalable UPS which is capable of providing uninterrupted 3-phase, 480 VAC power in the event of a power failure for a minimum of 30 minutes. (Battery run time will be dependent on the actual data center load and the number of battery strings. For example, if power fails and the two UPS devices are supplying 50% of the 150 kVA load a 200 kVA UPS would only be handling a 75 kVA load. If one UPS fails during this same situation the 200 kVA UPS will be running and maximum load and will need additional batteries to sustain a 30 minute run time.) -- Can you clarify at what load you need 30 min, and is that while redundancy is available or when redundancy is lost?

A: Each UPS needs to independently support a load of 200 kVA for 30 minutes.

3 Page 5, PWS para 3.2.2 Q: PWS section 3.2.2 states: “Utilize and reuse the existing 540 volt direct current (VDC) valve regulated lead acid (VRLA) battery components. Contractor shall reuse existing electrical wiring, maintenance panels, power distribution panels and electrical circuit breakers when feasible. -- Is it the Government’s intention to reuse the batteries themselves? The batteries would need to be reconfigured for use with the new UPS. Since the existing batteries have used a portion of their usable life already, any additional batteries added in order to meet runtime and system requirements would be limited to the remaining useful life of the existing batteries as well, thereby limiting the value of the newly purchased equipment.

A: PWS section 3.2.2 and 3.2.4 has been modified the Government is requesting a solution to replace the existing batteries.

4 N/A Q: When were the existing batteries replaced? In other words, how old/new are the existing batteries?

A: That information is not available. See question and answer # 3.

5 Page 5, para 3.2.2 Q: Is there a requirement to use VRLA batteries, or would Lithium Ion (L-Ion) batteries be acceptable? Lithium Ion batteries have a much longer useful life and smaller footprint than VRLA.

A: PWS section 3.2.2 and 3.2.4 has been modified the Government is requesting a solution to replace the existing batteries.

6 Page 5, PWS 3.2.9 Q: UPS commissioning shall be performed by UPS manufacturer authorized personnel. – What level of testing and commissioning is required?

A: OEM recommended testing/commissioning.

7 Page 6, PWS, Para 5.3 Q: A preventive, predictive, and corrective maintenance plan. – What is required in this plan?

A: Recommended preventative maintenance for the system.

8 Solicitation page 1 section 8 Q: Can the solicitation due date be extended?

A: Solicitation due date has been extended until 10:00 am JST 22 September, 2020

9 N/A Q: Power Frequency:

Specification for the UPS replacement does not specify it is 60Hz, But during the site visit, we capture that some of the switchgear was rated at 60Hz. So kindly confirm the understanding that it is 60Hz system.

A: Yes, the system is 60Hz.

10 N/A Q: Generator and ATS Specification. How fast can the generator start up time and ATS activated time? Please provide us existing Generators Specifications and ATS Specifications for us to verify the starting capabilities. Also provide the time taken for the Genset to start and ATS to switch in case of any mains failure for us to understand the timing chart for this purpose.

A:Generator and ATS specifications are not available. Generator start time is 8-10 minutes. The UPS requirement is for each side (A/B) to support 200 kVA for 30 minutes.

11 N/A Q: For us to provide a UPS Room layout in AutoCAD, we would require your existing room layout in CAD format and this will be further modified to include the modified UPS room layout.

A: Only a pdf of the floor plan is available.

12 Page4, PWS Para 3.1.1 Q: Project replacement includes only UPS-A & UPS-B Cable connection from UPS-A to Input –A (2) Cable connection from UPS-A to Output –A (3) and similarly for UPS-B Input- A and Output –A Panel (Similarly for UPS-B) will not be included in the scope of replacement and considering to use back the existing Input –A and Output –A Panel.

A: The government will accept solutions that re-use or replace the panels.

13 Page 5, PWS para 3.2.2 Q: Solicitation says two paragraphs which states different information.

One mentions the customer wants to use back existing VRLA battery and another mentions that the customer wants to change to new one. Our proposal is Flywheel solution and remove whole 540VDC back up battery system.

A: PWS section 3.2.2 and 3.2.4 has been corrected and modified. See question and answer # 3.

14 N/A Q: What kinds of inspection / functional test should be done after installation by offeror?

Is there any standard test protocol for US Marine Corps that needs to be fulfilled? Please provide the same :-

a. 100% load test

b. load back shall it be provided by customer or offeror.

c. High voltage power cable withstand voltage test

d. Standard test list A: Testing shall be in accordance with OEM guidelines.

15 PWS para 3.2.5 Q: Replacement schedule: Our understanding is to remove existing UPS- A , install new UPS, Test & commission and put the new Unit –A in operation and then followed by UPS-B. Kindly confirm if our understanding is correct. Is there any working time limit during weekend at site?

A: Work shall be conducted during business hours specified in the PWS section 2.3. Any exception will need to be coordinated with the COR and will require justification.

16 N/A Q: Current Mains input situation at site

a. Number of faults, recorded in the system during the last few years.

b. How many time the mains failure happen, duration of failure. Is there any fault history data that would be useful to study as reference?

A: Emergency repairs were conducted on the UPS approx. 1 year ago. A service report from the contractor who performed the repair has been provided (“Okinawa Service Report”).

17 N/A Q: Battery disposal. Is it necessary to submit a manifest certificate for battery disposal?

A: Batteries can be disposed of through the Base environmental office. Coordination will be conducted through COR.

18 N/A Q: Floor material of UPS room. When we install new UPSs in the UPS room, we need to anchor the equipment on the floor. Is there any management rule to anchor on the floor?

A: Equipment can be anchored to the floor and any damage from removed equipment will need to be returned to existing condition.

19 N/A Q: Storage of incoming equipment. Is there any additional room (rain shield and protected environment) at your site for storage of the new equipment before installation?

A: environmentally controlled on-site storage is available.

20 Page 6, PWS para 8.1 Q: Warranty. Would you explain about a transferable warranty described in item 8.1 of solicitation?

A: Contractor shall provide 1 year warranty on the installation and any transferable equipment warranties from the OEM.

21 N/A Q: Is there any factory acceptance visit or witness test at the manufacturing company before shipping? The cost for such visit of US Marine corps should it be borne by Offeror will US Marine Corps take care of such (travelling , boarding and lodging ) costs. ?

A: Contractor shall test in accordance with OEM recommendations. Please include testing/commissioning procedures in your proposal.

22 Page 6, PWS para 6.1 Q: Item 6.1 in the solicitation says that offerors must complete all tasks within 180 days after awards. We have assumed 1 week for drawing approval (UPS Unit, work plan including loading and unloading and safety plan) during the project duration to meet within this time limit of 180 days. Kindly confirm if this is sufficient.

A: Please allow 2 weeks for drawing approval. At this moment the current completion time of 180 days is considered sufficient.

23 N/A Q: Past budget record of the existing UPS system. Would you disclose the budget of the existing UPS system, especially break down of the existing UPS-A, VRLA system (A1 to A5 and BD), UPS-B and VRLA (B1 to B5 and BD).

A: Budget information cannot be provided.

24 Solicitation page 3 Q: Inspection and acceptance. Requirement for inspection at destination of CLIN0001 and CLIN0002 (page 4 in the solicitation) mean be done both at Camp Foster in Okinawa. Is our understanding correct?

A: This is correct.

The following have been modified:

PERFORMANCE WORK STATEMENT

INSTALLATION DESCRIPTION

UNINTERRUPTIBLE POWER SUPPLY (UPS) REMOVAL AND REPLACEMENT AT BLDG 480, CAMP

FOSTER, OKINAWA, JAPAN

1. BACKGROUND

1.1 This requirement is for the US Marine Corps Base Camp Foster, Telecommunications Office G-6 Bldg 480 located in Okinawa, Japan. The current Uninterruptible Power Supply (UPS) components were installed in 2003 and the manufacturer no longer produces the Series 600 UPS. UPS components are at the 17 year mark of the expected 20 year life cycle and needs to be replaced.

1.2 SCOPE OF WORK AND OBJECTIVE

1.2.1 Engineer, furnish, install, and test a new UPS system; and remove, recycle, and dispose of the current components. Contractors shall provide a solution to replace the two (2) existing 750 kVA, Liebert Series 600 UPS with a new, scalable, and appropriately sized UPS that meets the requirements specified in section 3.2 of this PWS.

The contractor shall be responsible for providing training to the customer in proper operation and user maintenance of the new UPS.

2.1 Place of Performance: Marine Corps Base Camp Foster, Okinawa, Japan.

2.2 Project duration: All tasks must be completed within 180 days after award

2.3 Hour of Operation: Monday thru Friday, 0800 - 1630 hours.

2.3.1 Typhoon Conditions. Japan-based military installations close when Tropical Cyclone Condition of Readiness 1C (TCCOR 1C or TC-1C) is declared by Military Weather Station authorities. The Contractor will be required to depart military bases, remain indoors, and monitor radio/television to determine when the TCCOR changes to TCCOR SW (Storm Watch) or TCCOR AC (All Clear). When TCCOR SW is declared by Military Weather Station authorities, the Contractor shall restart the service within 2 hours. If that occurs after normal business hours, services shall begin the next normal workday at 7:30am.

3. GENERAL REQUIREMENTS

3.1.1 The contractor shall provide a technical plan outlining their proposed UPS and installation requirements for approval by the Government at time of award. The contractor’s plan shall include all work required to install the UPS up to the point of connecting to Bldg. 480’s power panels. The government shall provide the electricians that connect the UPS to the power panels while the contractor’s installers are present to trouble shoot and verify the UPS is properly working.

3.1.2 Provide a removal and proposed installation drawing.

3.1.3 Provide an approved safety plan to remove the existing UPS in compliance with Occupational Safety and Health Administration (OSHA), United States Marine Corps (USMC), FEAD and GF orders of instruction.

3.1.4 Provide as-builts in AutoCad format. This work requires the compliance and adherence to OSHA, Universal Fire Code (UFC), Department of the Navy (DON), FEAD, USMC and GF regulations and orders of instructions.

3.1.5 The contractor shall provide authorized or certified personnel from the UPS manufacturer to perform commissioning of the components and conduct training for G-6 and GF major labor contractors in the in proper operation and user maintenance of the UPS.

3.1.6 The contractor shall provide all required safety items such as signs, barricades and temporary coverings for exposed electrical panels and work space.

3.1.7 The contractor shall return all walls and floors damaged during installation to original condition.

3.2 SPECIFIC TASKS

3.2.1 Replace the current UPS with a UPS that is scalable from approximately 200 kilo volt amperes (kVA) to 600 kVA. The current data center load is approximately 150 kVA and a scalable UPS is required to meet possible future data center requirements. The contractor shall provide a 3-phase, 480 volts alternating current (VAC) redundant and scalable UPS which is capable of providing uninterrupted 3-phase, 480 VAC power in the event of a power failure for a minimum of 30 minutes. (Battery run time will be dependent on the actual data center load and the number of battery strings. For example, if power fails and the two UPS devices are supplying 50% of the 150 kVA load a 200 kVA UPS would only be handling a 75 kVA load. If one UPS fails during this same situation the 200 kVA UPS will be running and maximum load and will need additional batteries to sustain a 30 minute run time.) The redundant UPS shall be capable of supporting the entire data center load in the event of a UPS or bypass power failure in the alternate unit. For example, UPS side A is down for maintenance and is placed in by-pass. A power failure occurs and by-pass voltage is lost on side A. Automatically UPS side B must handle the entire data center load. This is an intrinsic part of the existing design of the data center and the UPS replacement must be capable of any in-rush currents that occur in a power failure situation.

3.2.2 The Contractor shall propose a solution to replace the existing 540 volt direct current (VDC) valve regulated lead acid (VRLA) battery components. Contractor shall reuse existing electrical wiring, maintenance panels, power distribution panels and electrical circuit breakers when feasible.

3.2.3 Dismantle the current UPS and properly dispose of components. Recyclable materials with be staged on pallets to be picked up by the USG recycling team. All other material shall be properly disposed of by the contractor.

3.2.4 Provide a plan to isolate (LOTO), de-install and remove the existing UPS and 540 volt direct current (VDC) back-up battery system from building 480 room 124 (see attachment 2 for floor plan) and maximize re-use of the existing maintenance bypass and other power distribution panels.

3.2.5 Perform work to minimize any impact to operations. Removal of the UPS shall be phased allowing for backup power to be provided at all times to the equipment in the data center. Any power work that has the potential to affect operations shall be done on the weekend and scheduled in advance with the Government Representative.

3.2.6 The contractor shall conduct operational and user maintenance training for personnel identified by Garrison Facilities Operations and Maintenance and G-6 Operations. Personnel attending training may need prerequisite training or skills for operation or maintenance on this equipment, contractor shall identify these requirements if they apply. The Government Representative will coordinate with the contractor to arrange a time and place for conducing training as required.

3.2.7 The UPS solution shall have an optional in rack air conditioning system, if available. If in rack cooling is not available the contractor shall also replace the two CRAC units serving the UPS.

3.2.8 UPS shall include and meet the whole building design concepts for UPS components at the following link;

https://www.wbdg.org/ffc/dod/supplemental-technical-criteria/tsewg-tp-19

3.2.9 UPS commissioning shall be performed by UPS manufacturer authorized personnel.

5. DELIVERABLES. The following documentation is required as deliverables before project completion

5.1 Manufacturer’s technical manuals and operations and user guides.

5.2 UPS with as-built drawings for Bldg. 480 electrical drawing and one line drawings as required to replace Garrison Facilities Electrical Shop drawings.

5.3 A preventive, predictive, and corrective maintenance plan.

6. SCHEDULING

6.1 After award, Contractor shall coordinate with the assigned MCB G6 Government Representative to schedule the work a minimum of thirty (30) days prior to the start of work. All tasks must be completed within 180 days after award.

7. AUTHORIZED GOVERNMENT REPRESENTATIVE

7.1 The G-6 Government Representative for this project will be Entered at Time of Award.

8. WARRANTY

8.1 The contractor shall provide a transferable warranty in accordance with commercial industry standards for the installed equipment.

8.2 The contractor shall provide a minimum of 12 months workmanship and labor warranties in accordance with commercial industry standards.

8.3 The manufacturer and their authorized contractor shall provide warranty and recall information and terms and length of warranty on critical items. Additionally the contractor shall include a list of recommended spare parts in the quote for approval by maintenance personnel and the G-6 Government Representative.

9. SPECIAL INSTRUCTIONS AND ADMINISTRATIVE INFORMATION

9.1 Non-Personal Services. The incidental services under this requirement are non-personal services contract. The contractor bears responsibility to manage its employees and guard against any actions that could be characterized as personal services as defined in FAR 37.104, or which convey the perception that personal services are being delivered.

No provisions are implied nor provided in this contract for any benefits such as medical care, retirement, or worker’s compensation, other than those incorporated through enumerated clauses.

9.2 Identification of Contractor Personnel and Equipment. In accordance with DFARS 211.106, contractor personnel performing non-personal services on DoD installations or other government facilities shall ensure that they are readily identifiable as contractor employees (including subcontractors and consultants). All contractor employees shall comply with the following at all times:

9.2.1 Telephone Identification. Identify themselves as contractor personnel at the onset of every telephone call made from a Government telephone or any other phone if the call is made in support of Government-related requirements and activities.

9.2.2 Recorded Messages. Identify themselves as contractor personnel in all recorded messages including those, which are heard by callers attempting to contact contractor employees via answering machines or voicemail.

9.2.3 Meetings, Conferences and Events. Identify themselves as contractor personnel at the onset of every meeting, conference or any other gathering attended in support of any Government related requirements or activities.

9.2.4 Correspondence. Identify themselves as contractor personnel on any correspondence, documents, or reports accomplished or sent in support of any service provision to the Government, including, but not limited to, correspondence sent via the U.S. Mail, facsimile, or electronic mail (email) inclusive of out-of-office replies.

9.2.5 Personal and Corporate Identification. Wear or display contractor provided nametags, badges or attire which display, at a minimum, the name of the contractor and their respective company.

9.3 Designated Third Country Nationals (DTCN). Persons from certain countries are considered DTCN and are generally restricted from entering Marine Corps Bases Japan (MCBJ) Camps, Air Stations, or facilities. A listing of DTCN countries and other related information regarding this policy can be found in USFJ Instruction 31-204 (Designated Third Country Nationals), which can be made available upon request.

9.3.1 Hazardous Materials and Safety. The Contractor and its subcontractors shall comply with all applicable laws, including Public Law 91-596 (Occupational Safety and Health Administration (OSHA)) and DOD Directive 4715.1E, Environmental, Safety, and Occupational Health (ESOH)). Contractor personnel performing services on a DOD installation shall participate in local Voluntary Protection Programs (VPP). Information on the VPP is available at http://www.osha.gov/dcsp/vpp/index.html

10. INSTALLATION ACCESS AND PERSONNEL CREDENTIALING

10.1 Motor Vehicles. Vehicle licensing, registration, and insurance requirements must all be conducted in accordance with host nation law, USFJ Instruction 31-205, and applicable local installation policies.

10.2 Registration/Permits. Vehicle registration on Okinawa, Japan is conducted with the Provost Marshal via the Joint Services Vehicle Registration Office (JSVRO) at Bldg 5638, Marine Corps Base, Camp Butler. Information may be obtained at JSVRO website at: https://www.mcbbutler.marines.mil/Base-Information/Vehicle-Registration/, or by calling +81-(0)98-970-7481.

10.2.1 Registration Termination. Vehicle permits will expire upon termination date of this contract/order, expiration of an individual base pass or DBIDS ID, expiration of vehicle inspection sticker, or termination of their employment (whichever occurs first). Permits issued to individuals who overstay any of these authorized dates become void and invalid.

10.2.2 Insurance. Vehicle permitting procedures require that all vehicles, personal or corporate, must be properly inspected and insured in accordance with Japanese Compulsory Insurance (JCI) requirements. Additionally, for SOFA status personnel and U.S. corporate vehicles, the Contractor or SOFA status individual is required to procure and maintain, during the entire period of performance under this contract, the following minimum insurance on each vehicle used by the Contactor at the work site:

Automobile Property Damage Insurance Amount: ¥30,000,000 (or U.S. Dollar equivalents) Bodily Injury Insurance Amount: ¥30,000,000 Yen (or U.S. Dollar equivalents)

Prior to the commencement of work, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance for any and all corporate vehicles to be used. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the laws of the state in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

10.2.3 Road Laws. All personnel operating motor vehicles under this contract/order are subject to U.S. military installation regulations and Japanese Road Laws. Failure of the contractor, its employees, or its sub-contractors, to comply, may result in revocation of driving privileges or other legal action.

10.2.4 Vehicle Disposal. Personnel protected under the Status of Forces Agreement (SOFA) are required by regulation to properly dispose of vehicles prior to departure from Japan. For individuals performing under this contract, the contractor may be held financially liable for vehicles abandoned, or vehicles not disposed of properly, in accordance with vehicle regulations as agreed with the Government of Japan.

10.2.5 Personnel Access / Credentialing. Access to local installations is inherently required to accomplish specified tasks under this contract/order. The contractor shall therefore ensure all necessary actions are taken to obtain such access by its personnel in time to affect access in accordance with the requirements of this PWS and POP. Failure to complete such actions in a timely manner, some of which may occur prior to the POP or individual mobilization/relocation to the place of performance, shall not constitute excusable delay. Upon request, the Contracting Officer will provide a ‘check-in’ sheet that summarizes required actions.

10.2.5.1 Base Passes and/or Defense Biometrics IDentification System (DBIDS) cards. Personnel that do not qualify for CAC require an alternate credential for installation access, as governed by Marine Corps Installations Pacific Order 5512.2, which can be provided upon request. The process to request access requires approval from the Contracting Officer in an access request letter.

10.2.5.2 Return and/or Disposal of Access Credentials. The contractor’s employees shall return to the applicable issuing office all base passes, DBIDS cards, and/or CAC, immediately upon termination of employment or completion of this contract and certification of receipt shall be obtained and submitted to the Contracting Officer.

The Contractor shall submit a listing of employees terminated under this contract to the Contracting Officer within seven (7) days of the effective date of termination.

10.2.5.3 Status of Forces Agreement. Possession of a CAC or other credential does not, alone, determine the legal status of personnel performing under this contract. Additionally, unless specifically identified on the CAC, the credential does not necessarily authorize logistical support privileges such as commissary/exchange access. The individual status of personnel performing under this contract, and the privileges authorized, are governed in accordance with United States Force Japan Instructions (predominantly USFJI 64-100), applicable credentialing regulations, and the information prescribed via DFARS clauses regarding Contractor Personnel in Japan, as contained herein.

10.6 Security Requirement.All information pertaining to this project will be marked UNCLASSIFIED, FOR OFFICIAL USE ONLY. Background checks will be performed by the vendor and provided to the government upon contract award.

11. Quality Control and Quality Assurance. In accordance with FAR part 46, and the respective enumerated clauses incorporated in this contract/order, the contactor is reminded that the government may conduct Quality Assurance actions, inspect the Contractor’s Quality Control Plan and records, and take remedial actions as necessary, at any time through the duration of this contract/order.

12. DEFINITIONS

12.1. Contracting Officer (KO). The KO is the only person who can bind, limited to the extent of the authority delegated by the head of the agency, the United States Government to a contract that is greater than the Micro- Purchase threshold. The KO enters into, administers, or terminates contracts and makes related determinations and findings.

13. ATTACHMENTS

(1)UPS components list

(2) Electrical Floor Plan

(3) Electrical Floor Plan Cropped

(4) One-Line Drawings

(5) One-Line Drawings Cropped

(6) UPS Feeder Schedule

End of PWS.

(End of Summary of Changes)