Intermediate and Depot Level Maintenance Services (IDLMS) Blount Island Command Navy Support Management Branch Questions and Answers M6700419R0007 The following Q&A are from site visit 21 Nov 2018 Q1) Is this going to be a bast value?
A1) Yes, FAR part 12 and 13 procedures Q2) Is a SOW for Job Order 1 going to be available?
A2) Yes it will be posted today 21 Nov 2018.
The following questions were submitted today 27 Nov 2018:
Q) Because of the nature of this first JO which hinges on the entire BOA is it possible to get more clarity on a couple of items specifically:
| 1. | Which Table and Line item in the 009-32 would you like for the contractors to work to? | |
| a. | The paint system is a cost driver | |
| b. | The method of surface preparation is a cost driver | |
| c. | Item a. also applies to the touch-up of interior spaces |
2. Which table and line in 009-12 would you like for the contractors to work to?
| 3. | How can we get access to the references? | |
| a. | The references may clear up questions 1 and 2 however it may not depending on how up to date the drawing is to current marine practices and /or FY19 CH 3 NSI. |
4. Is access tomorrow following the same procedure as last week?
A) Sir, I will have to defer to Mr. Fish regarding questions 1 and 2. References will be provided on a CD for each Company attending. Access is the same for tomorrow.