Attachment 12 QUALITY ASSURANCE SURVEILLANCE PLAN
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 12
QUALITY ASSURANCE SURVEILLANCE PLAN
AIRCRAFT MAINTENANCE
AND
TECHNICAL SUPPORT SERVICES
FOR THE UNITED STATES MARINE CORPS
MARINE FIGHTER ATTACK TRAINING SQUADRON (VMFAT-101)
LOCATED AT
MARINE CORPS AIR STATION, MIRAMAR, CA
1. Purpose. This Quality Assurance Surveillance Plan (QASP) has been developed to provide the standard of surveillance for monitoring the contractor's performance in maintenance and technical support services of the F/A-18 A/B/C/D T/M/S aircraft located at VMFAT-101, MCAS, Miramar, CA. The Contracting Officer will appoint the Aviation Logistics Department Head for 3rd MAW as the Contracting Officer's Representative (COR) for this contract. The Contracting Officer shall appoint additional CORs as required to monitor and manage day-to-day activities. All COR's will be certified in accordance with prescribed policies and directives. Each COR will use this QASP to ensure the standards of the contract being met.
2. Performance Standards. The QASP provides a systematic method to evaluate the service the Contractor is required to furnish. The COR will assess the Contractor's performance to ensure the Contractor is performing up to the specified standards. The performance standards for this performance work statement are stated in the Performance Requirements Summary (PRS) included in this QASP. The standards are subjective for this requirement.
3. Management and Oversight. The QASP is based on the premise that the Contractor and not the Government, is responsible for the management and any Quality Control action required to meet the terms of the contract. The performance requirements recognize that the Contractor is not a perfect manager and that unforeseen requirements and uncontrollable problems do occur. Good management and use of an adequate Quality Control Plan will allow the Contractor to operate within specific performance requirements. QASPs are designed to be objective, fair, and consistent in evaluating Contractor performance against the provided standards. The contractor's quality control plan will be reviewed and approved prior to contract award.
4. Acceptable Quality Levels (AQLs). AQLs have been established in the Performance Requirement Summary (PRS) and provide performance standards that the Contractor will meet in performing the contract. In the event the Contractor does not meet the established AQLs, the Contracting Officer has the right to exercise the negative incentives stated in this QASP.
5. Primary Method of Surveillance/Evaluation. The COR will perform evaluation based on using one of the various methods outline in the PRS Table included in this QASP. The following methods may be incorporated into the PRS to monitor contract performance:
100% inspection: Inspection where specific characteristics of every performance unit are examined and tested to determine conformance with requirements.
Random inspection/Contract Discrepancy Inspections (COI): Sampling method in which each unit of the population has an equal chance of being selected.
Customer Surveys and Feedback: A review method where customers and end users are surveyed to provide input on specific service levels.
6. Substandard Performance. If any of the performance requirements do not meet the AQL set forth in the PRS table, the COR shall document the discrepancy(s) and shall notify the Contracting Officer promptly. The Contracting Officer will then take the appropriate action with the contractor to remedy the substandard performance. When the performance is below the AQL standard, the Government may implement increased surveillance and/or Contractor reporting, as well as, documentation in the Contractor's Performance Assessment Reporting System (CPARS).
7. Notification. The COR will notify the Contracting Officer, in writing, of unacceptable quality levels. The Contracting Officer will promptly provide written notification of discrepancies on a monthly basis, or immediately if the situation significantly affects the well-being of the project. The Contractor will be given the opportunity to respond, in writing, to each discrepancy.
8. Response. The Contractor shall provide a written response to the cause and the corrective action to prevent recurrence within 45 working days after receipt of Contracting Officer’s notification. The Contractor shall cite specific quality assurance program procedures or new procedures instituted to prevent recurrence.
9. Records. The COR will maintain contract surveillance files as directed by the Contracting Officer. Surveillance files will include, at a minimum, the following documentation for this IDIQ contract:
a. COR designation and appointment letters.
b. A copy of the contract and all contract modifications.
c. QASP, Quality Control Plan, and any other monitoring tools, checklists, etc.
d. All correspondence including KO notifications and the Contractor's response.
e. Contractor reports, i.e., training plans, course outlines, maintenance training, anomalies, etc.
f. Monthly evidence of satisfactory performance provided by Maintenance Material Control officer.
g. Evidence of cost/price monitoring: copies of certified invoiced tracked against each contract line item.
h. Overtime (OT) authorizations and tracking.
| i. | Other Direct Costs (ODCs) authorizations and tracking. |
| j. | Quarterly technical reviews. |
k. Surveillance reports and a summary of the surveillance logs prepared by the COR and submitted to the KO annually.
I. Copies of deficiency reports that may be submitted in support of unacceptable performance identified during the performance period by the COR, or when there is a significant change in the assessment in one or more evaluation areas.
m. Annual in-progress reviews conducted and entered into CPARS.
10. Ratings. The following criteria will be used for performance evaluations: Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory. Upward or downward arrows may be used to indicate an improving or worsening trend insufficient to change to the assessment status.
a. Exceptional. Indicates performance clearly exceeds contractual requirements.
There were no problems requiring corrective action.
b. Very Good. Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the task and sub-task being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
c. Satisfactory. Indicates performance clearly meets contractual requirements.
The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.
d. Marginal. Indicates performance meets contractual requirements. The area of evaluation contains one or more serious problems for which corrective actions have not yet been identified, appear only marginally effective, or have not been fully implemented.
e. Unsatisfactory. Indicates the contractor is in danger of not being able to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains one or more serious problems for which the corrective actions appear ineffective.
11. Documentation. Documentation used and referenced to perform surveillance will consist of monthly reports, contractor plans and procedures, schedules, customer feedback and contract data requirements.
a. Recording Observations. Surveillance Logs will be used to record information on scheduled observations and deficiencies noted. Each observation is recorded on the log. The documents then become a formal record for reference. The Contractor is to be told each time that a deficiency is found during scheduled observations. The COR makes a notation on the Surveillance Log of the date and time the deficiency was discovered, then, the COR asks a contractor task leader to initial the notation, documenting notification of the deficiency only.
b. Potential Unacceptable Performance. The COR must identify the specific service that is unacceptable and the possible causes, and ask a number of questions which if answered, are intended to pinpoint the source of the problem.
c. Documenting Unacceptable Performance. The COR should make every attempt to resolve the problem with the contractor. The original log and the attempted solution (along with an evaluation of results) shall be forwarded to the Contracting Officer through the COR.
Based on the severity of the discrepancy and the success of the solution, the COR will notify the Contracting Officer. The Contractor shall complete a response to the unacceptable condition if requested by the Contracting Officer.
12. Taking Action.
a. The COR may evaluate the contractor's performance and document any noncompliance, and report it to the Contracting Officer may take action against the contractor for an unacceptable rating.
b. When the contractor's performance is unacceptable and a formal action is indicated, the COR will determine what action is appropriate for the specific circumstances and make a recommendation to the Contracting Officer.
13. Documentation. The COR shall retain a copy of all inspection schedules and surveillance activity logs during the course of the contract, and shall forward them for inclusion in the contract file at the end of the surveillance period. However, when a specific service becomes unsatisfactory during a surveillance period, the inspection documentation supporting the contract discrepancy report shall be forwarded to the Contracting Officer at the earliest opportunity.
14. PERFORMANCE REQUIREMENTS SUMMARY (PRS). The primary measure of performance the Government will use in determining the effectiveness of the Aircraft Maintenance shall be directly reflected in personnel experience levels maintained, coordination with squadron and Aircraft Maintenance Officer (AMO); record keeping, contractor’s ability to maintain Quality Contract Performance (QCP) requirements; and meeting safety regulations/directives. The Acceptable Quality Levels (AQL) for each performance requirement objective is provided in the chart below:
| TASK |
| PERFORMANCE OBJECTIVE |
| PERFORMANCE STANDARDS |
| FREQUENCY |
| ACCEPTABLE QUALITY LEVEL (AQL) |
| SURVEILLANCE METHOD |
| 1 |
| Meet Technician Qualifications and Performance Requirements |
| Provide all required personnel with qualifications for all scheduled performance periods to ensure no adverse impact on the mission |
| Contract Award and Continual |
| 90% |
| COR Inspection approval of resumes, certifications and feedback, 100% inspection. |
1A
| Monitor performance to ensure technicians compliance with requirements and standards |
| Ongoing |
| 100% |
| Planned Inspections |
| 2 |
| Coordination with the Squadron AMO |
| Attend meetings, Maintain and update procedures as changes occur. Coordinate with the Maintenance Officer on scheduling and workload. |
| As required |
| 95% |
| COR Feedback |
| 3 |
| Contractor Quality Control Program |
| Provide, maintain, and enforce Contractor QCP |
| As required |
| 95% |
| Planned Inspection |
| 4 |
| Safety |
| Abide by all applicable safety regulations including those detailed in CNAFINST and OSHA instructions. |
| Ongoing 100% of time |
| 100% |
| Random Inspection |
| 5 |
| Aircraft Maintenance |
| Accomplishing all assigned scheduled and unscheduled organizational and intermediate level maintenance identified herein and in the squadron’s Monthly Maintenance Plan. |
| Ongoing 100% of time |
| 100% |
| Planned Inspection |
5A
| All contractor technician work shall be performed in accordance with the applicable Navy, Marine Corps and Manufacturers technical manuals and directives; in accordance with CNAFINST 4790.2 series, Maintenance Instructions Manuals (MIMs); Manufacturers publications; and local squadron processes and procedures. |
| Ongoing 100% of time |
| 100% |
| Planned Inspection |
5B
| Contractor technician shall certify completion of maintenance and airworthiness of the aircraft through the use of Navy Aviation Logistics Command Information System (NALCOMIS) |
| 100% of time |
| 100% |
| 100% Inspection |
| TASK |
| PERFORMANCE OBJECTIVE |
| PERFORMANCE STANDARDS |
| FREQUENCY |
| ACCEPTABLE QUALITY LEVEL (AQL) |
| SURVEILLANCE METHOD |
5C
| The Contractor technicians shall ensure where decisions on airworthiness are questioned, the appropriate Quality Assurance Representative is responsible for making the final decision. |
| 100% of time |
| 100% |
| As Required |
| 6 |
| Aircraft Services |
| The Contractor shall provide services to include but not be limited to, and subsystem warm-up/check out to insure proper installation of the installed system. |
| As Required |
| 100% |
| Planned Inspection |
6A
| The Contractor technicians shall ensure that they meet all qualifications and currency requirements set forth in OPNV 3710.1 Series. |
| 100% of time |
| 100% |
| Planned Inspection |
6B
| The Contractor technicians shall ensure that they maintain the required proficiency in all required qualifications and licenses |
| 100% of time |
| 100% |
| Planned Inspection |
| 7 |
| Support Equipment |
| Contractor shall perform dispatch of SE to the flight line and surrounding hangar areas in support of flight maintenance functions as required. |
| As required |
| 100% |
| Planned Inspection |
| 8 |
| Transient or Deployed Aircraft |
| Upon approval of the AMO or COR, the Contractor shall deploy to other sites as required for the purpose of maintaining and/or repairing aircraft. |
| As required |
| 100% |
| None Required. |
| 9 |
| Crash Recovery and Repair |
| When directed by the AMO or COR, the contractor shall assist in the recovery of crashed aircraft. |
| As required |
| 100% |
| 100% Inspection |
| 10 |
| Maintenance Tracking and Recordkeeping |
| The Contractor shall complete all forms required for compliance of work performed by contractor technicians within this contract in accordance with the OPNAVINST 4790.2 Series |
| As required |
| 100% |
| Planned Inspection |
10A
| Contractor shall keep track of all work conducted via (NALCOMIS) |
| Ongoing 100% of time |
| 100% |
| Planned Inspection |
10B
| Material deficiencies and operational hazards will be reported to the MO/QAO in accordance with OPNAV Instruction 4790.2 Series. |
| As required |
| 100% |
| Planned Inspection |
| TASK |
| PERFORMANCE OBJECTIVE |
| PERFORMANCE STANDARDS |
| FREQUENCY |
| ACCEPTABLE QUALITY LEVEL (AQL) |
| SURVEILLANCE METHOD |
10C
| The contractor shall report to the Government AQR any inadequate or deficient technical or engineering data. |
| As required |
| 100% |
| Planned Inspection |
| 11 |
| Technical Directives and Bulletins |
| When directed by the MO or COR, the contractor shall be responsible for tracking and performing organization level maintenance technical directives and bulletin. |
| As required |
| 100% |
| Planned Inspection |
11A
| Upon completion of the directives/bulletins, the contractor shall report compliance through the NALCOMIS/3-M system. |
| As required |
| 100% |
| Planned Inspection |
| 12 |
| Destructive Weather Protection |
| The contractor technicians shall be responsible for the securing of any assigned aircraft in accordance with the applicable aircraft MIMs. This includes turning the aircraft into the wind as the wind shifts and securing the aircraft. |
| As Directed |
| 100% |
| 100% Inspection |
| 13 |
| Tool Accountability and Inventory |
| All PPE, maintenance and tool control will be followed in accordance with CNAFINST 4790.2 |
| Ongoing 100% of time |
| 100% |
| Team Lead |
13A
| The Contractor shall be liable for any missing tools or equipment should a government investigation find that the Contractor employee conducted theft or was negligent. |
| Ongoing |
| 100% |
| Ongoing Inspection |
| 14 |
| Project Manager Responsibilities |
| The Project Manager shall be responsible for the overall management of the performance of this contract |
| Continuous |
| 100% |
| COR Feedback |
14A
| The Project Manager shall provide supervisory oversight for all technicians/mechanics and maintenance operations included in this contract. |
| Continuous |
| 100% |
| COR Feedback |
14B
| The Project Manager shall perform all management actions associated with his/her employees to include investigations and reports arising from any qualify defect notices. |
| As Required |
| 100% |
| 100% Inspection |
14C
| The Project Manager shall be responsible for coordinating work space assignments, scheduled work hours, and shift work with the COR and respective AMOs and MMCOs. |
| Continuous |
| 90% |
| COR Feedback |
| TASK |
| PERFORMANCE OBJECTIVE |
| PERFORMANCE STANDARDS |
| FREQUENCY |
| ACCEPTABLE QUALITY LEVEL (AQL) |
| SURVEILLANCE METHOD |
14D
| Ensure contractor technicians are capable of performing all the above tasks without direct governmental supervision. |
| Continuous |
| 100% |
| Ongoing Inspections |
14E
| Ensure that at a time of Destructive Weather, and at the direction of AMO or COR, that all maintenance technicians properly evacuate the area, to include proper reporting to squadron on technician accountability and safety during evacuation. Must be familiar with Squadron Destructive Weather Plan and Procedures if published. |
| Continuous |
| 100% |
| 100% Inspection |