Amendment_2_Questions_CGC_RESOLUTE.docx
DOCX document 25 KB Posted
- Attached to
- CGC RESOLUTE (WMEC-620) DRYDOCK REPAIRS
- Solicitation number
- HSCG80-13-Q-P45B18
About this file
Amendment A00002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_4_Questions_CGC_RESOLUTE.docx | DOCX document | |
| RESOLUTE_DD_Large_FY13_Spec_Rev-2.pdf | ||
| RESOLUTE_AMEND_3.pdf | ||
| 627-WMEC_152_1_1_-_G_Aircastle_repairs.pdf | ||
| 627-WMEC_581_1_1_-_A_Anchor_chain_fair_lead.pdf | ||
| SPEC_Rev-1_RESOLUTE_DD_FY13.pdf | ||
| Amendment_1_Questions.docx | DOCX document | |
| Spec_RESOLUTE_Rev-0.doc | DOC document | |
| Performance_Questionnaire_based_on_CPARS_Template.docx | DOCX document | |
| RFQ_PDF_RFQ_HSCG80-13-Q-P45B18_Date_4-25-13_Posted.pdf | ||
| Blank_IGE_Rev-0.xls | XLS spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDIQ MASTER PAGE 62 OF __
USCGC RESOLUTE,
Solicitation: HSCG80-13-Q-P45B18
SF 30, Block 14 Continuation Page
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE |
OF PAGES
2. AMENDMENT/MODIFICATION
A00002
3. EFFECTIVE DATE
May 7, 2013
4. REQUISITION/PURCHASE REQ. NO.
2113803P45B18
5. PROJECT NO.
6. ISSUED BY CODE:
Commander (MECPL) Surface Forces Logistics Center 300 East Main Street, Suite 550 Norfolk, VA 23510-9111
7. ADMINISTERED BY CODE:
8. NAME AND ADDRESS OF CONTRACTOR (No, street, county, state and Zip Code)
CODE: FACILITY CODE:
9a. AMENDMENT OF SOLICITATION NO.
HSCG80-13-Q-P45B18 CGC RESOLUTE (WMEC-620)
9b. DATED (SEE ITEM 11) April 25, 2013
10a. MODIFICATION OF CONTRACT NO.
10b. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENT OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning one copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (IF REQUIRED)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO DESCRIBED IN ITEM 14.
A. This change order is issued pursuant to: (Specify authority) The changes set forth in Item 14 are made in the contract order no in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation data, etc.) set forth in Item 14 pursuant to the authority of FAR 43.103(b).
C. This supplemental agreement is entered into in pursuant to authority of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _1____ copy to the issuing office.
14. Description of amendment/modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
USCGC RESOLUTE (WMEC-620)
Solicitation HSCG80-13-Q-P45B18
1. The purpose of this amendment is to answer questions received from potential offerors. See the following continuation page to view the questions and answers. See attached drawings.
2. The solicitation’s closing date is remains May 17, 2013 at 2:00 p.m. EST.
3. All other terms and conditions remain unchanged.
15A. NAME AND TITLE OF SIGNER (Type/Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type/Print) Tara M. Holloway
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
BY____________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
STANDARD FORM 30
QUESTION: Work Item 26, Titled “Aircastle Superstructure Supports, Repair” Paragraph 3.2.2.
Paragraph 3.2.2, specifies as follows: "Box beam, renew. Crop and renew up to 10 square feet of box beam as shown on Coast Guard Drawing 627 WMEC 152-001 as designated by the Coast Guard inspector."
627 WMEC 152-001, Sheet 1, Elevation 4-E/1 depicts 4" x 4" Box Girders.
Is this what the paragraph is referring to?
If yes, how is the contractor to replace 10 sf on a 4" by 4" x 10.2# steel square tube?
Why don't we specify 1 lf of 4" x 4" x 12.2# steel square tube per commercial sizing?"
If no, what sheet and what elevation depicts the desired repair component?
Please provide additional reference depicting the desired repair.
ANSWER: The desired repair location is shown on 4-E/1 of the 627 WMEC 152-001. See attached drawing with callouts. The area is a void made of plate steel. Corrosion on both sides was due to no drain plug installed or corrosion preventative "float coat" performed.
QUESTION: Work Item 26, “Aircastle Superstructure Supports, Repair” Paragraph 3.4.1.
Are the existing "Box Girders" presently preserved with a rust preventative compound?
Is the contractor correct to assume that each "Box Girder" will require steaming out to a gas free safe for hot work condition?
Is the contractor correct to assume that a low point drain and high point vent bossed plugs are installed on each of the 8 "Box Girders" shown on the CG Drawing provided?
ANSWER: See the attached drawing. The drain plugs shown in the drawings do not exist. They will need to be installed for the void on both sides. Corrosion on both sides was due to no drain plug installed or corrosion preventative "float coat" performed.
QUESTION: Work Item 25, Titled “Aft Vestibule Deck, Repair & Joiner Door, Renew” Paragraph 3.2.4
Paragraph 3.2.4 Deck plate, renew; Reads as "The Contractor shall crop and renew up to six square feet of deck drain as designated by the Coast Guard inspector as shown on Coast Guard Drawing 627 WMEC 131-001. Verify the exact material to be renewed with the Coast Guard inspector prior to cropping."
Is the intent to replace deck plate and not deck drain?
Is there a deck drain in-way-of the intended repair?
ANSWER: The word deck should have been removed. The intent is to replace the deck. There is no deck drain in the vicinity of the repair.
QUESTION: Work Item 27, Titled “Aircastle Superstructure Supports, Repair” Paragraph 3.2.2.
Section 8-C of the provided reference is the "Fairlead".
All other structure shown on Plan 6-D and sections of 6-D is support for the "Fairlead".
Is the contractor correct to interpret the only component to renew is that shown in Section 8-C of reference provided?
Please provide a source for the casting.
Has the CG considered weld build-up of the existing casting?
ANSWER: See Attached marked up drawing for anchor chain fairlead.
QUESTION: Work Item 28, Titled “Bilge T-Bars, Renew” Paragraph 3.3.
Is the intent of the item to replace a total of 20 lf of stringer or three (3) whole twenty (20) foot stringers, for a total of 60 lf?
ANSWER:
The intent of the item is to replace 20 lf of stringer.
(End of Questions and Answers)
File details come from the government source that posted it. Updated .