USCGC ALLIGATOR (WPB-87) DRYDOCK AVAILABILITY 2012

USCGC ALLIGATOR (WPB 87372)

87 FOOT COASTAL PATROL BOAT (USCG)

SPECIFICATION FOR DRYDOCK REPAIRS

Developed By: Michael J Watson (Rev-1, 29NOV 2011)

TABLE OF CONTENTS

ivRevisions Record vConsolidated List of References viiiConsolidated List of Government-furnished Property xConsolidated List of Critical Inspection Items xiPrincipal Characteristics

1General Requirements

11WORK ITEM 1: Perform Ultrasonic Thickness Measurements (D)

14WORK ITEM 2: Perform Ultrasonic Thickness Measurements (O)

17WORK ITEM 3: Forepeak , Modify (EC 087-A-33) (D)

26WORK ITEM 4: Dirty Oil Tank, Clean and Inspect (D)

28WORK ITEM 5: Oily Water Tank, Clean and Inspect (D)

30WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect (D)

32WORK ITEM 7: Pilothouse Deck (Aluminum), Inspect , Preserve, and Renew Electrical Matting

35WORK ITEM 8: Depth Sounder, Capastic Fairing, Renew (O)

37WORK ITEM 9: Main Engine/Reduction Gear, Realign (O)

40WORK ITEM 10: Propulsion Shafts, Remove, Inspect, and Reinstall (D)

49WORK ITEM 11: Propulsion Shaft, Repair (O)

51WORK ITEM 12: Propulsion Shaft, Straighten (O)

53WORK ITEM 13: Intermediate Water-Lubricated Propulsion Shaft Bearing , Renew (O)

55WORK ITEM 14: Aft Water-Lubricated Propulsion Shaft Bearing , Renew (O)

57WORK ITEM 15: Intermediate Bearing Carrier, Renew (O)

58WORK ITEM 16: Aft Bearing Carrier, Renew (O)

59WORK ITEM 17: Stern Tube, Interior Surfaces , Preserve 100% (O)

61WORK ITEM 18: Stern Tube, Interior Surfaces , Repair (O)

63WORK ITEM 19: Propellers, Remove, Inspect, and Reinstall (D)

66WORK ITEM 20: Propeller, Minor Reconditioning and Repairs, Perform (O)

69WORK ITEM 21: Fathometer Transducer, Renew (D)

72WORK ITEM 22: Speed Log, Skin Valve Assembly, Clean and Inspect (D)

74WORK ITEM 23: Sea Water System (Sea Valves , Strainers, Piping), Clean, Inspect, and Repair (D)

77WORK ITEM 24: Rudder Assemblies, Remove, Inspect and Reinstall (D)

81WORK ITEM 25: RHIB Notch Skid Pads, Inspect (D)

83WORK ITEM 26: RHIB Notch Skid Pad Studs, Renew (O)

85WORK ITEM 27: Stern Launch Door, Remove, Inspect and Reinstall (D)

88WORK ITEM 28: Grey Water Holding Tank, Clean and Inspect (D)

90WORK ITEM 29: Sewage Holding Tank , Clean and Inspect (D)

92WORK ITEM 30: Grey Water Piping, Clean and Flush (D)

96WORK ITEM 31: Sewage Piping, Clean and Flush (D)

100WORK ITEM 32: U/W Body, Preserve (“100%”) (O)

103WORK ITEM 33: U/W Body, Preserve (“Partial – 33%”) (O)

107WORK ITEM 34: Cathodic Protection / Zincs, Renew (D)

109WORK ITEM 35: Drydocking (D)

114WORK ITEM 36: Temporary Services, Provide (D)

116WORK ITEM 37: Telephone Service, Provide (D)

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE
29NOV11
1

Corrected GFP list and removed unneeded referances.

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:

· MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

· Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

· Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws:: www.gpoaccess.gov The Government is aware of the following internet web links where contractors may procure commercial specifications:

· American Welding Society (AWS): http://www.awspubs.com/index.php

· ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

· NFPA: http://www.nfpa.org

· SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 085-001, Rev-, Tank CAPACITY - 95% Curves Coast Guard Drawing 87 WPB 085-010, Rev D , Docking Plan Coast Guard Drawing 87 WPB 085-012, Rev -, Lifting Cradle Coast Guard Drawing 87 WPB 085-11, Rev B, Lifting Slings Coast Guard Drawing 87 WPB 111-001, Rev E , Shell Expansion Coast Guard Drawing 87 WPB 131-002, Rev- , Forepeak Void New Watertight Flat Coast Guard Drawing 87 WPB 161-001, Rev C, Skeg Construction Coast Guard Drawing 87 WPB 163-001, Rev G , Sea Chest Details Coast Guard Drawing 87 WPB 163-1, Rev F, Sea Chest Details Coast Guard Drawing 87 WPB 165-001, Rev D, Transducer Details Coast Guard Drawing 87 WPB 182-001, Rev A, Main Engine and Generator Foundations Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details Coast Guard Drawing 87 WPB 245-002, Rev-, Propeller Details Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details Coast Guard Drawing 87 WPB 252-001, Rev D, Pilothouse Console Arrangement Coast Guard Drawing 87 WPB 252-002, Rev K, Alarm & Monitoring System Coast Guard Drawing 87 WPB 256-001, Rev U , Sea Water Cooling Piping Coast Guard Drawing 87 WPB 302-001, Rev P, Misc. Controls Wiring Diagram, sheets 1, 2, 3, 36, 39, & 42 Coast Guard Drawing 87 WPB 423-001, Rev T , Speed Log & Depth Sounder System Coast Guard Drawing 87 WPB 526-001, Rev H, Scuppers & Deck Drains Piping Coast Guard Drawing 87 WPB 529-001, Rev E, Bilge Piping Coast Guard Drawing 87 WPB 561-001, Rev H , Steering System Details Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details Coast Guard Drawing 87 WPB 581-002, Rev-, Anchor Handling & Hawse Pipe Details Coast Guard Drawing 87 WPB 583-001, Rev K, RHIB Deployment Structure Coast Guard Drawing 87 WPB 583-001, Rev P , RIB Deployment Structure Coast Guard Drawing 87 WPB 593-001, Rev K, Sewage Piping Coast Guard Drawing 87 WPB 601-001, Rev F; Outboard Profile And General Arrangement Coast Guard Drawing 87 WPB 601-001, Rev G , Outboard Profile And General Arrangement Coast Guard Drawing 87 WPB 635-001, Rev C, Linings and Insulation Plan & Details NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Change 1, Jun 2006, Coatings and Color Manual Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EL Coast Guard Technical Publication (TP) 4593B, Mar 2003, SWBS 562, Rudderstock Seal-Type EJ Coast Guard Technical Publication (TP) 4593C , Feb 2002, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.

Coast Guard Technical Publication (TP) E-424-0230, SWBS 424, June 2006, Electromagnetic Log User’s Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC STD SPEC 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6341 (SFLC STD SPEC 6341 ), Jan 2009, Install Interior Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), Jan 2009, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), Jan 2009, Provide Temporary Services Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary Hull Accesses

OTHER REFERENCES

American Bureau of Shipping (ABS), 2, Rules for Survey After Construction, 2008, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings ASTM International (ASTM) D 4138, 2007, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An) ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates ASTM International (ASTM), D3951, Re-approved 2004, Standard Practice for Commercial Packaging Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255 Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-Petrolatum Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections International Organization for Standardization (ISO), 484/2, First Edition, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of diameter between 0.80 and 2.50 m inclusive MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-DTL-15562, May 1996, Matting or Sheet, Floor Covering Insulating for High Voltage requirements MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application MIL-PRF-23236, Aug 2003, Coating Systems for Ship Structures MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited) MIL-STD-1687, Sep 1994, Thermal Spray Processes For Naval Ship Machinery Application MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2007, Brush-Off Blast Cleaning

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

9
Y
Alignment Kit
N/A
1 ea
5000.00
10
N
**Propeller shaft
NSN: 2010-01-458-9175
2 ea.
9,566.14
10
N
Type FSE Face (split)
PN: H75440-01-2-2

NSN: 5330-01-521-3559

2 ea.
1,995.07
10
N
Type FSE Seal (split)
PN: H75440-01-1-1

NSN: 2040-01-521-2654

2 ea.
4,070.35
10
N
Type FSE Seal Cup (split)
PN: H75440-01-1-3

NSN: 3120-01-521-2390

2 ea.
188.24
10
N
Type FSE O-Cord
PN: H75440-01-1-4

NSN: 3120-01-521-2268

2 ea.
252.84
10
N
Type FSE Emergency Seal
PN: H75440-01-3-6

NSN: 5330-01-521-4855

2 ea.
260.92
10
N
**Shaft Seal Bellow
PN: H75440-01-2-1

NSN: 5340-01-521-3573

2 ea.
270.45
10
N
*Compression Tool Assembly
N/A
1 ea.
200.00
10
N
*Alignment Kit
N/A
1 set
3,000.00
13
N
**Thordon bearing, Grade Orange

(5.5" OD x 4" ID x 7.87" (200mm) LG)

PN: F54615-02-8-1

NSN: 3120-21-914-2012

2 ea.
325.47
14
N
**Thordon bearing, Grade Orange

(5.5" OD x 4" ID x 11.41" (290mm) LG)

PN: F54615-02-8-0

NSN: 3120-21-914-2011

2 ea.
399.50
19
Y
**Starboard Propeller (RH)
PN: RH706-3350.00

NSN: 2010-01-457-0573

1 ea.
12,498.00
19
Y
**Port Propeller (LH)
PN: LH706-3350.00

NSN: 2010-01-459-0421

1 ea.
12,498.00
19
N
*Propeller Nut Wrench
N/A
1 ea
200.00
19
N
**Propeller Nut
NSN: 2010-01-458-9217
2 ea.
281.00
19
N
**Propeller Nut, Locking
NSN: 5310-01-458-9125
2 ea.
252.94
19
N
Anode, Propeller Nut
NSN: 5342-01-481-8403
2 ea.
272.00
21
N
*** Fathometer transducer, shallow water, 50-200 kHz
NSN: 5845-01-531-2648
1 ea.
441.70
22
Y
Doppler Speed Log Measurement Rod
NSN: 6605-01-470-1266
1 ea.
4645.09
24
Y
**Rudder Assembly, port
NSN: 2040-01-461-1944
1 ea.
2,000.00
24
Y
**Rudder Assembly, starboard
NSN: 2040-01-461-1943
1 ea.
2,000.00
24
N
Upper Roller Bearing
NSN: 3110-01-512-5534
2 ea.
244.62
24
N
Wartsila EL Seals Kit
NSN: 2040-01-565-9776
2 ea.
6300.00
35
Y
*Transducer Cover Plate
N/A
2 ea.
50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

1
Perform Ultrasonic Thickness Measurements (D)
24
Rudder Assemblies, Remove, Inspect and Reinstall (D)
35
Drydocking (D)

Principal Characteristics

PC_87_WPB_0909

87' WPB

Physical Characteristics

Length Overall
87'
Length between Perpendiculars
81' 7"
Depth
10' 11"
Maximum Beam
19.4'
Draft, Mean to Design Waterline
5' 9"
Height of Highest Projection
50.2'
Full Load Displacement
93.5 long tons
Minimum Operating Displacement
83.9 long tons
Displacement, Light Ship
77.9 long tons
Framing
Longitudinal
Bulkheads
Four watertight bulkheads located below the Main Deck
Anchor
40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset

Hull Characteristics

Hull/Main Weatherdeck Material
BS-4360, GR 43A Steel
Superstructure
5086 Aluminum

Machinery Characteristics

Main Propulsion
Two MTU 8V396TE94, sequential turbo-charged diesels
Reduction Gears
Two ZF Type BW 255
Propulsion Shaft
Two AQUAMET 22, 101.6mm
Shaft Diameter
4"
Shaft Seal
Two John Crane mechanical seals
Shaft Bearing, Intermediate
Thordon Elastomeric Bearing
Shaft Bearing, Aft
Thordon Elastomeric Bearing
Number of Propellers
2
Number of Blades
5
Diameter of Propeller
1040mm
Pitch
1230 mm fixed
Shaft RPM
828
Rudders
Two 316L Stainless Steel
Ship's Service Generators
Two Man Model D08241F01 diesel with Stanford 60KW Generator

Tank Capacities

3-9-1-F (Fuel Oil)
1402 gal
3-9-2-F (Fuel Oil)
1402 gal
3-12-2-F (Waste Oil)
86 gal
3-12-1-F (Oily Water)
86 gal
3-7-0-Q (Sewage Collection)
352 gal
3-7-1-Q (Grey Water)
52 gal
3-12-1-W (Fresh Water)
200 gal
3-12-2-W (Fresh Water)
200 gal

00000_PWB_0211_FLT

REC_0000_FLT_ Commercial Project @ Contractor’ Facility (0211) General Requirements

1. SCOPE

1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.

2. REFERENCES

Coast Guard Drawings None.

Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Other References ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.4 HW disposal. The Contractor is considered as the generator of all contract-generated hazardous wastes and shall use its facility’s EPA generator ID number for management, transportation, and disposal of said hazardous wastes. Ensure the following:

3.4.1 Contractor’s hazardous waste handlers shall comply with applicable requirements of 40 CFR 262.

3.4.2 All contract generated hazardous wastes shall be packaged in 49 CFR-compliant containers.

3.4.3 The designated wastes shall be disposed of at a state or Federally-approved and permitted HW TSDF.

3.4.4 Name of destination TSDF shall be submitted to the KO at the Arrival Conference.

3.5 Pre-surface preparation test coupon. In order to ensure production of required surface profile, the Contractor shall accomplish the following tasks, whenever abrasive-blasting is required in a work item that is deemed a ”critical-coated’ surface:

3.5.1 Coupon material and test set-up particulars.

3.5.1.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Ensure the following:

· The coupon shall be a new metal plate, of the same metal type and material properties as the vessel area to be blasted - steel or aluminum plate, as applicable, and shall have no existing anchor profile - other than the surface irregularities from the manufacturing process.

· The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot.

· For steel substrates, the coupon shall have the mill scale intact, and be in a Rust Grade "A" condition, in accordance with SSPC-VIS 1.

· The test coupon shall be affixed so as to not permit excessive movement during the performance test, but shall not be affixed to the vessel.

3.5.1.2 Ensure that the abrasive-blasting operation for the test coupon is conducted with the identical setup and parameters that will be used blasting the designated vessel surfaces – including, but not limited to:

· The abrasive media type and media size selected to achieve the anchor profile range, as specified in the applicable work items.

· Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).

· Delivery rate and pressure settings.

3.5.1.3 Blast a one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the work item, and perform an anchor profile test of the blasted surface in accordance with ASTM D4417, Method B or C. Notify the COTR in advance of the abrasive blasting operation test, to permit the witnessing of the test by the COTR. Submit a CFR documenting the results of the abrasive blasting operation test. The CFR shall include at a minimum, the following:

· Area of the vessel for which the verified setup will be used to abrasive blast.

· The selected abrasive media type and size.

· The nozzle size and type.

· The delivery rate and pressure.

· The test coupon starting properties (material type and surface conditions).

· The resultant anchor profile readings from the test (a minimum of 3 locations, separated by a minimum of 2 inches shall be recorded).

NOTES

1. A performance test of the abrasive blasting operations on a test coupon and measuring the resultant anchor profile prior to performing the abrasive blasting operation on the cutter is required. The test coupon will be used to evaluate the anchor profile produced by the equipment setup and selected abrasive media.

2. The reverse side of the test coupon may be used for the subsequent test, provided that the conditions in paragraph 3.5.1 (Coupon material and test set-up particulars) are met.

3. Ultra high pressure water jetting does not create an anchor profile and is exempt from the anchor profile test coupon check.

3.5.1.4 Repeat the abrasive blasting operation test in the following instances:

· The equipment setup, that was evaluated during the test coupon abrasive blasting performance test in paragraph 3.5.1 (Coupon material and test set-up particulars), has changed.

· The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.

· Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.

· The supplier of the abrasive blasting media changes, regardless if the new source for the media has the same specifications.

· When Directed by the COTR.

CAUTION!

Ensure that blast media from the performance test does not strike the vessel during the test.

3.6 Interim changes to SFLC Std Spec 0000. The Contractor shall be aware of the fact that the requirements of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:

“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:

· Ordinary low water mark on non-tidal rivers.

· At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp

4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).

Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (Frame References)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________ Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils

Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils

Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils

Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils

Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils Place Surface Profile Replica Tape Here Reading:__________ mils

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________ Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Reading:
_____ mils
_____ mils
_____ mils
_____ mils
_____ mils

Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):

_____ mils
_____ mils
_____ mils
_____ mils
_____ mils
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15

DATE
TEST LOCATIONS
CONDUCTIVITY

(microsiemens/cm)

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference): ___________________

SPOT
1
2
3
4
5

Overall Avg. DFT

ADJUSTMENTS

Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

SPOT
1
2
3
4
5

Overall Avg. DFT

ADJUSTMENTS

Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

SPOT
1
2
3
4
5

Overall Avg. DFT

ADJUSTMENTS

Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

11000 _JLW_1210_87WPB

WORK ITEM 1: Perform Ultrasonic Thickness Measurements (D)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 87 WPB 085-010, Rev D, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev E, Shell Expansion Coast Guard Publications None.

Other References None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

· 3.2 (UT measurements).

3.1.2 Technical Representative.

Not applicable.

3.1.3 Protective measures.

Not applicable.

3.1.4 Interferences.

3.1.4.1 If UT measurements cannot be obtained due to interferences, the Contractor shall submit a CFR that details all necessary interference removal/reinstallation work. After the KO has released a CR, remove the interferences and reinstall after completion of associated work.

3.2 UT measurements. The Contractor shall perform up to 250 UT measurements in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C. Create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit a CIR that contains the sketch and completed Table I.

4. NOTES

This section is not applicable to this work item.

Table I - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT #
STRAKE #
FWD/MID/AFT
ORIG PL
MEASURED PL
PERCENT
PLATE #
TOP/MID/BOT
THICKNESS
THICKNESS
WASTAGE

11001 _JLW_1210_87WPB

WORK ITEM 2: Perform Ultrasonic Thickness Measurements (O)

1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods, in 10 lots of 25 measurements.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 87 WPB 085-010, Rev D, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev E, Shell Expansion Coast Guard Publications None.

Other References None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

Not applicable.

3.1.2 Technical Representative.

Not applicable.

3.1.3 Protective measures.

Not applicable.

3.1.4.1 If UT measurements cannot be obtained due to interferences, the Contractor shall submit a CFR that details all necessary interference removal/reinstallation work. After the KO has released a CR, remove the interferences and reinstall after completion of associated work.

3.2 UT measurements. The Contractor shall perform up to 250 UT measurements in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C. Create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit a CFR that contains the sketch and completed Table I.

4. NOTES

This section is not applicable to this work item.

Table I - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT #
STRAKE #
FWD/MID/AFT
ORIG PL
MEASURED PL
PERCENT
PLATE #
TOP/MID/BOT
THICKNESS
THICKNESS
WASTAGE

11100_JLW_1110_87WPB

WORK ITEM 3: Forepeak , Modify (EC 087-A-33) (D)

1.1 Intent. This work item describes the requirements for the Contractor to modify and preserve the Forepeak (2-0-0-V), creating a sealed, lower forepeak void and a separate, upper forepeak compartment.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 87 WPB 111-001, Rev D, Shell Expansion Coast Guard Drawing 87 WPB 131-002, Rev-, Forepeak Void New Watertight Flat Coast Guard Drawing 87 WPB 252-001, Rev D, Pilothouse Console Arrangement Coast Guard Drawing 87 WPB 252-002, Rev K, Alarm & Monitoring System Coast Guard Drawing 87 WPB 302-001, Rev P, Misc. Controls Wiring Diagram, sheets 1, 2, 3, 36, 39, & 42 Coast Guard Drawing 87 WPB 529-001, Rev E, Bilge Piping Coast Guard Drawing 87 WPB 581-002, Rev-, Anchor Handling & Hawse Pipe Details Coast Guard Drawing 87 WPB 635-001, Rev C, Linings and Insulation Plan & Details Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Coast Guard Commandant Instruction (COMDTINST) M10360.3, Change 1, Jun 2006, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary Hull Accesses Other References ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method MIL-PRF-16173, Jan 1993, Corrosion Preventive Compound, Solvent Cutback, Cold Application

3. REQUIREMENTS

3.1 General.

3.1.1 Critical inspection report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraphs:

· 3.4 (Substrate inspection).

3.1.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:

· Anchor.

· Anchor chain.

· Anchor line.

· Anchor line drum.

· Anchor line holder.

· Anchor windlass.

· Anchor windlass hydraulic components (as applicable).

· Bulkhead insulation on aft side of bulkhead 2.

· Deck grating.

· Electric switches.

· False bulkheads.

· Float switches.

· Hydraulic piping.

· Ladder.

· Lights.

· Lockers.

· Racks.

· Bilge discharge check valve.

· Bilge overboard discharge valve.

· Electrical boxes (J-box).

· Wiring.

· Piping.

· Piping hangers.

3.1.3 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the bilge discharge valves, anchor windlass system, bilge pump, and Forepeak bilge level sensors and switches to demonstrate existing operational condition. Submit a CFR.

3.1.4 Temporary access openings. Due to limited access to work areas, the Contractor may, with express permission of the KO (via submission of a CFR), cut access holes to facilitate accomplishment of the work specified herein. Perform all work required to open and close the access openings in accordance with SFLC Std Spec 8636.

3.1.5 Surface preparation particulars. The Contractor shall prepare all bilge, bulkhead, overhead, and shell surfaces of the Forepeak Compartment, including structural members and the ladder; use the system specified for preparation for “Bilges, Cofferdams, and Forepeaks, Option 1”, in COMDTINST M10360.3. Appendix B (Cutter and Boat Interior Painting Systems).

3.2 Removals. The Contractor shall accomplish the following as shown on Coast Guard Drawing 87 WPB 131-002 and using Coast Guard Drawing 87 WPB 529-001 for guidance:

3.2.1 Crop out and retain for reuse the bilge overboard hull penetration with six-inch stainless steel insert.

3.2.2 Remove and discard the following:

· Bilge pump.

· Bilge pump discharge hose.

· Serrated deck grating.

· All deck grating support structures including the angle on bulkhead 2. See Figure 1 below.

· All stand offs and foundations located below the spray chine.

3.3 Preparation. The Contractor shall remove all water from the bilge and prepare all shell, bilge, and associated structural member surfaces; use the system specified for “Bilges, Cofferdams, and Forepeaks, Option I” (surface preparation only) in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems).

3.4 Substrate inspection. The Contractor shall perform a total of 75 thickness measurements of Forepeak surfaces, in locations designated by the Coast Guard Inspector. Submit CIR. The ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797. The report results shall additionally include, for each test point:

· Location.

· Original metal thickness.

· Measured metal thickness.

· Percent deterioration (calculation is based on the original metal thickness).

3.5 Electrical disconnections. The Contractor shall disconnect and retain for reuse the following; using Coast Guard drawings 87 WPB 252-001, 87 WPB 252-002 and 87 WPB 302-001 for guidance:

· Forepeak compartment high level alarm sensor circuit from the Engine Room Alarm Panel (C-FD1) to the bilge alarm float switch.

· Bilge high level alarm float switch and wire.

· Float switch and wire that operate the bilge pump in automatic mode.

· Forepeak bilge pump j-box.

Figure 1

3.6 Materials. The Contractor shall provide and install all items on the “Materials List” of Coast Guard Drawing 87 WPB 131-002.

3.7 Forepeak void modification. The Contractor shall construct and modify the lower forepeak void and bilge equipment system as shown on Coast Guard Drawing 87 WPB 131-002 and in accordance with Std Spec 0740_STD. All work performed in this work item shall be subject to the Coast Guard Inspector’s approval. Refer to Coast Guard Drawings 87 WPB 111-001, 87 WPB 252-001, 87 WPB 252-002, 87 WPB 302-001, 87 WPB 529-001, 87 WPB 581-002, and 87 WPB 635-001 for guidance. The Contractor shall accomplish the following:

3.7.1 Install both upper and lower drain plug inserts as shown on Coast Guard Drawing 87 WPB 131-002, elevation 26-B and 26-C.

3.7.2 Install four tank top support angles as shown on Coast Guard Drawing 87 WPB 131-002, View 14-A, Detail 14-C, Section 21-C and Section 23-C.

3.7.3 Install sounding tube brackets as shown on Coast Guard Drawing 87 WPB 131-002, Section 31-C.

3.7.4 Install sounding tube as shown on Coast Guard Drawing 87 WPB 131-002, Elevation 5-A, Section 31-C, and Note 12.

3.7.5 Fabricate the bilge well as shown on Coast Guard Drawing 87 WPB 131-002, View 11-C, View 19-A, Detail 21-A and Detail 23-A. Measurements are given in the Materials list.

3.7.6 Install wire standoff at location indicated on Figure 2.

Figure 2

3.7.7 Slightly bend the voids top plate to provide slope to match the contour of the spray chine as shown on Coast Guard Drawing 87 WPB 131-002, View 11-A, 19-A and Detail 21-A.

3.7.8 Weld the bilge well into the watertight flat as shown on Coast Guard Drawing 87 WPB 131-002 and Figure 3.

3.7.9 Install watertight flat as shown on Coast Guard Drawing 87 WPB 131-002.

NOTICE!

The plate may need to be cut to get it into the forepeak void.

3.7.10 Reuse the cropped, round portside hull plate to weld in place of the former portside through-hull overboard to make the compartment watertight.

3.7.11 Weld in the bilge pump through-hull overboard fitting and six-inch round stainless steel insert into starboard side as shown on Coast Guard Drawing 87 WPB 131-002 and Figure 3.

Figure 3

3.7.12 Weld the bilge pump float switch one-inch stainless steel(SS) angle iron support so that the float switch will be located inside the bilge pump well two inches above the bottom plate and six inches to the starboard side (centered) in the forward portion of the bilge well. Use the support bracket as a template for drilling holes for fasteners.

3.7.13 Weld one-inch SS angle iron mounting tab for high bilge alarm float switch support bracket so that the float switch will be located on bulkhead 2 at cutters centerline, two inches above the Forepeak deck. Use the support bracket as a template for drilling holes for fasteners.

3.7.14 Install the bilge pump into the bilge well and attach the discharge hose, check valve, bilge overboard discharge valve (2-1-1) and wiring to breaker (2-16-1)-24EP-M via the forepeak bilge pump NEMA-4 J-Box. This J-Box should be located a minimum of 18” above the forepeak deck, allowing pump installation without the need for splicing the electrical leads. See Figure 4.

3.7.15 Install the bilge pump float switch. See Figure 4.

Figure 4

3.7.16 Install the forepeak high level bilge alarm sensor on bulkhead 2, no more than two inches from the deck.

3.7.17 Wire the forepeak high level alarm to the Engine Room Alarm Panel (C-FD1). Ensure the parallel connected 1.2 ohm .5 watt resistor is installed as shown on Coast Guard Drawing 87 WPB 252-002.

3.7.18 Using the Anchor Line Drum as a template, mark locations for leveling studs.

3.7.19 Weld four 3/8” x 1 ¼” 316 stainless steel studs to the tank top as marked, and then install leveling nuts. At time of installation, place and level drum so it will be properly aligned with the pipe feeding the anchor line into the drum. Fasten securely in place as shown on Coast Guard drawings 87 WPB 131-002 and 87 WPB 581-002.

3.8 Compartment air test. The Contractor shall air test the forepeak void in accordance with Std Spec 0740_STD, Appendix C. Submit a CFR.

3.9 Preservation. The Contractor shall accomplish the following:

3.9.1 Void and top plate preservation.

3.9.1.1 Void internal surfaces. Completely fill the new void with a rust preventive compound conforming to MIL-PRF-16173, Grade 3, to coat all surfaces. Drain, collect, and dispose of remaining compound in accordance with all applicable Federal, state, and local regulations. Ensure that the coated surfaces are left exposed to the atmosphere, for 24 hours, to allow for adequate drying, before installing the void plug.

3.9.1.2 Top plate. Preserve the void top plate/flat, including all disturbed adjacent areas in accordance with Std Spec 0000_STD, paragraph titled “General preservation requirements, using the coating system specified for “Bilges, Cofferdams, and Forepeaks, Steel, Option II” in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Paint Systems). Select finish/top coat color to match existing adjacent surfaces.

3.9.2 Forepeak compartment preservation. Coat all bulkhead, overhead, and shell surfaces of the upper forepeak compartment, including associated structural members, and the ladder; use the system specified for “Bilges, Cofferdams, and Forepeaks, Option I” in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems). Select Light Gray (26373) as the top/finish coat color.

3.10 Operational test – final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove all disturbed anchor handling equipment and the Forepeak bilge pump, valves, switches and sensors to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.

3.11 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000_STD, paragraph titled “Preservation requirements – general”.

NOTICE!

Surfaces being preserved are considered “critical-coated surfaces”.

4. NOTES

4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.

11100_SteelWeld_0210_FLT REC_11100_Steel_FLT_87' WPB (ALL)(0511)

12300_JLW_1210_87WPB

WORK ITEM 4: Dirty Oil Tank, Clean and Inspect (D)

1.1 Intent. This work item describes the requirements for the Contractor to clean the following tank:

TYPE OF TANK
LOCATION
CAPACITY - 95%

(gallons) LOW SUCTION (gallons)

Dirty Oil
2-13-2-F
86

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 87 WPB 085-001, Rev-, Tank CAPACITY - 95% Curves Coast Guard Drawing 87 WPB 601-001, Rev G, Outboard Profile And General Arrangement Coast Guard Publications None.

Other References Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test by Coast Guard personnel of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.

3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.

3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.

3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:

· Tank structural condition.

· Inaccessible areas.

· Oily water tank - Tank Level Indicator (TLI) and/or float switch condition.

· Sounding tube and striker plate condition.

· Suction and discharge piping condition.

· Fastener material and condition (correct fastener material is stainless steel).

· Strainers – verify that strainers are not touching the hull or tank bhds.

3.5 Tank closing. The Contractor shall ensure that the tank(s)…

This is the start of the file's text. The full file is on GovTribe.

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .