FINAL_NMACC_II_Solicitation2016_7-21-16.pdf
PDF 690 KB Posted
- Attached to
- NATIONAL MULTIPLE AWARD CONSTRUCTION CONTRACT (NMACC) Federal contract opportunity
- Solicitation number
- HSCG47-16-R-3EFK01
About this file
HSCG47-16-R-3EFK01 NMACC Final Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| HSCG47-16-R-3EFK01_Amendment_0006.pdf | ||
| HSCG47-16-R-3EFK01_Amendment_0005.pdf | ||
| HSCG47-16-R-3EFK01_Amendment_0004.pdf | ||
| HSCG47-16-R-3EFK01_Amendment_0003.pdf | ||
| Factor_1_Rev8192016.pdf | ||
| HSCG47-16-R-3EFK01_Amendment_0002.pdf | ||
| TAC_FedContractors_JRF_QA_508c.pdf | ||
| Attachment__PPQ_RMACC.docx | DOCX document | |
| ATTACHMENT_J.1.docx | DOCX document | |
| HSCG47-16-R-3EFK01_Amendment_0001.pdf | ||
| SF1442_Page_1.pdf | ||
| NMACC_Draft_Section_M.pdf | ||
| Draft_NMACC_SolicitationAPR2016posting.pdf | ||
| NMACC_Solicitation2016pja.docx | DOCX document | |
| Current_NMACC_Incumbents.docx | DOCX document | |
| Draft_NMACC_Solicitation2016posting.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES COAST GUARD
REQUEST FOR PROPOSALS
INDEFINITE DELIVERY/INDEFINITE QUANTITY
DESIGN/BUILD NATIONAL MULTIPLE AWARD
CONSTRUCTION CONTRACT (NMACC)
AT
VARIOUS DEPARTMENT OF HOMELAND SECURITY (DHS)
FACILITIES THROUGHOUT THE
UNITED STATES AND TERRITORIES
NOTICE FOR FILING AGENCY PROTESTS
United States Coast Guard Ombudsman Program
It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the Government Accountability Office (GAO).
Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative Dispute Resolution (ADR) forum rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.
Informal Forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the Contracting Officer is unable to satisfy their concerns, interested parties are encouraged to contact the U.S. Coast Guard Ombudsman for Agency Protests. Under this informal process the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest to either the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program.
Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103(d) (2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted electronically to OPAP@uscg.mil and the Contracting Officer or by hand delivery to the Contracting Officer.
Election of Forum. After an interested party protests a Coast Guard procurement to the Contracting Officer or the Ombudsman, and while the protest is pending, the protester agrees not to file a protest with the GAO or other external forum. If the protest is filed with an external forum, the agency protest will be dismissed.
The Ombudsman Hotline telephone number is 202.372.3695.
https://www.acquisition.gov/far/index.html https://www.acquisition.gov/far/index.html mailto:OPAP@uscg.mil
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
HSCG4716R3EFK01
United States Coast Guard SILC Construction/Facilities Design & Construction Center 5505 Robin Hood Rd, Suite K Norfolk, VA
Department of Homeland Security National Multiple Award Construction Contracts (NMACC)
North American Industry Classification System Code (NAICS) 236220 Commercial and Institutional Building Construction Small Business Size Standard: $36.5M
The National Multiple Award Construction Contract is a full and open competition. It is anticipated that no more than eight National Multiple Award Indefinite Delivery Indefinite Delivery Indefinite Quantity (IDIQ) contracts will be awarded from this single solicitation.
Term of IDIQ Contracts: Base Year + Six Option Years
Two-Phase Design-Build Selection Procedures outlined in FAR Subpart 36.3 will be used for this procurement. Those offerors selected as most highly qualified during Phase One will receive the requirements and wage determination for a seed project as part of Phase Two. Site Visit information for the seed project will be provided during Phase Two.
The NMACC is being issued as a single solicitation. Proposal submission procedures are described in Section L.
SEE SECTION L
Pamela J. Argilan 757-852-3449
3 2:00 p.m.
7 August 2016
Phase I written proposals are due 7 September 2016 no later than 2:00 p.m.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
SECTION A
SOLICITATION/CONTRACT FORM
TABLE OF CONTENTS
(X) SECT DESCRIPTION PAGES
PART I – THE SCHEDULE
X A SOLICITATION/CONTRACT FORM 1-5
X B SUPPLIES OR SERVICES AND PRICES/COSTS 6
X C DESCRIPTION/SPECS/WORK STATEMENT 7-9
X D PACKAGING AND MARKING 10
X E INSPECTION AND ACCEPTANCE 11-13
X F DELIVERIES OR PERFORMANCE 14-17
X G CONTRACT ADMINISTRATION DATA 18
X H SPECIAL CONTRACT REQUIREMENTS 19-26
PART II – CONTRACT CLAUSES
X I CONTRACT CLAUSES 27-44
PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
X J LIST OF ATTACHMENTS 45-58
PART IV – REPRESENTATIONS AND INSTRUCTIONS
X K REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS 59-67
X L INSTRUCTIONS, CONDITIONS AND NOTICES TO
OFFEROR 68-76
X M EVALUATION FACTORS FOR AWARD 77-83
SECTION B
ITEM NO. SUPPLIES/SERVICES MAX QUANTITY MAX AMT
0001 BASE PERIOD
FFP
This is an Indefinite Delivery/Indefinite Quantity (IDIQ) Design/Build – Design/Bid/Build Multiple Award Construction Contract (MACC) covering the 50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, demolition, historical restoration and other construction consistent with the definition of construction in the Federal Acquisition Regulation (FAR) Part 2.
A seed task order will be issued concurrently with the award of the basic contract for the base period only to the contractor found to be the best value to the Government. All minimum guarantees will be met through issuance of a task order during the base period.
0002 1st OPTION PERIOD
FFP
This is an Indefinite Delivery/Indefinite Quantity (IDIQ) Design/Build – Design/Bid/Build Multiple Award Construction Contract (MACC) covering the 50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, demolition, historical restoration and other construction consistent with the definition of construction in the Federal Acquisition Regulation (FAR) Part 2.
0003 2nd OPTION PERIOD
This is an Indefinite Delivery/Indefinite Quantity (IDIQ) Design/Build – Design/Bid/Build Multiple Award Construction Contract (MACC) covering the 50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, 0004 3RD OPTION PERIOD
50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, 0005 4TH OPTION PERIOD
50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, 0006 5TH OPTION PERIOD
50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, 0007 6TH OPTION PERIOD
50 United States and its Territories including the Caribbean Islands for a period of 12 months. The scope of work includes, but is not limited to, general construction, marine construction, military housing construction, SECTION C
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C. 1 SCOPE OF WORK
The U.S. Department of Homeland Security (DHS), U.S. Coast Guard (USCG), Shore Infrastructure Logistics Center (SILC) Construction Contracting Office, has determined the need to re-procure the National Multiple Award Construction Contract (NMACC) Indefinite Delivery Indefinite Quantity (IDIQ) contract vehicle to perform construction services nationwide. This DHS enterprise-wide contract will meet a majority of the DHS infrastructure construction needs within the 50 United States and its Territories including the Caribbean Islands. The scope of work will include design-build and design-bid-build construction including for general construction, marine construction, military housing construction, demolition, historical restoration and other construction consistent with the definition of construction in the Federal Acquisition Regulation (FAR) Part 2. Task order limits will range from $4M to $100M and ordering authority will be available to any Department of Homeland Security components with appropriate warrant authority.
Some Task Orders, which require design and construction, may require stamped drawings or sketches to describe the new construction. In addition, the contractor may be responsible for obtaining all necessary permits. This contract is intended to provide prompt services on as needed basis at minimum administrative costs, and to ensure that the work will be performed in an expeditious and efficient manner within the budgetary limitations and performance time period as established for each task order. The contractor may be required to visit the proposed work site to establish, clarify, and define the scope of work of the individual requirement to prepare a detailed price proposal. Proposal due dates shall be identified in each Request for Task Order Proposal. This contract shall include all supervision, materials, labor, equipment, transportation, and disposal required to perform the work described in these specifications and Request for Task Order Proposal (RTOP). The Specifications governing all work to be ordered under this contract are contained within this solicitation. Additional specifications may be added for projects and will be issued for pricing prior to placement of a Task Order. Recognizing there may be substantive differences in state and local requirements for each project, the specifications for each task will be included with the RTOP.
No more than eight (8) contracts will be awarded as a result of this solicitation. The duration of the contract(s) is for one (1) year from the date of contract award with six (6) one-year option periods. Projects will have an estimated construction cost between $4,000,000.00 and $100,000,000.00. The aggregate capacity that the Government may order under all NMACC contracts is $1,500,000,000.00. The government guarantees a minimum award amount of $10,000.00 to each successful offeror over the full term of the contract, including option years.
C.2 APPLICABLE PUBLICATIONS
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. The contractor shall comply with all applicable federal, state, and local regulations and laws.
(a) ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS:
16 CFR 1303 Ban of Lead-Containing Paint and Certain Consumer Products Bearing Lead-Containing Paint
40 CFR 61 National Emission Standards for Asbestos
40 CFR 112 Oil Pollution Prevention
40 CFR 136-143 Water Programs
40 CFR 204 Noise Emission Standards for Construction
Equipment
40 CFR 260-279 Solid Waste Regulations
40 CFR 280-282 Underground Storage Tank Regulations
40 CFR 311-374 Worker Right-to-Know
40 CFR 761 Polychlorinated Biphenyls (PCBs)
Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions
(b) U.S. DEPARTMENT OF LABOR OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA) REGULATIONS:
29 CFR 1910 Worker Safety Requirements
29 CFR 1926.62 Lead
29 CFR 1926.1101 Asbestos
(c) U. S. DEPARTMENT OF TRANSPORTATION REGULATIONS:
49 CFR 100-199 Hazardous Materials Transportation, Handling, and Storage Regulations
(d) COMDTINST M5100.47 U.S. Coast Guard Safety and Environmental Health Manual
(e) COMDTIST M6260.16 U.S. Coast Guard Asbestos Exposure Control
Manual
C.3 REFERENCE STATUTES
The statutes listed below form a part of this specification to the extent referenced.
Clean Air Act (CAA) - (42 U.S.C. 7401 to 7642)
Clean Water Act (CWA)
Safe Drinking Water Act (SDWA)
Coastal Zone Management Act (CZMA)
Comprehensive Environmental Response, Compensation, and Liabilities Act (CERCLA)
- (42 U.S.C. 9601 to 9675)
Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA) - (7 U.S.C. 136 to 139y)
National Historic Preservation Act (NHPA)
Noise Control Act (NCA) - (42 USC 4901 to 4918)
Pollution Prevention Act (PPA) - (42 U.S.C. 13101 to 13109)
Resource Conservation and Recovery Act (RCRA) - (42 U.S.C. 6901 to 6991i)
Solid Waste Disposal Act (SWDA) - (42 U.S.C. 6901 to 6991i)
Toxic Substance Control Act (TSCA) - (15 U.S.C. 2601 to 2654)
Energy Independence and Security Act of 2007 (EISA)
Endangered Species Act (ESA)
Emergency Planning and Right-to-Know Act (EPCRA)
THIS AREA INTENTIONALLY LEFT BLANK
SECTION D
PACKAGING AND MARKING
D.1 - PACKAGING AND MARKING
(a) All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the Government. Preservation, packaging and packing shall be in accordance with standard practices for commercial packaging.
(b) Government personnel are not authorized to accept deliveries for the contractor, nor are they responsible for off-loading shipments. A contractor representative must be present to accept deliveries.
SECTION E
INSPECTION AND ACCEPTANCE CONSTRUCTION
E.1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements.
The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.
The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may--
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor;
or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction.
However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
E.2 DAILY REPORTING REQUIREMENT
The Contractor shall prepare and file a "Contractor's Daily Report", for each day of contract performance. Description must include task order numbers and work being performed. These reports shall be delivered to, or if directed, mailed to the Contracting Officer’s Representative on Fridays. The daily report shall include the name of Contractors and Subcontractors on-site, the number of workers and their labor categories employed on-site, the work being performed, the type of equipment on-site, any change order work being performed, and whether the work being performed is on schedule. Reports shall be numbered, dated and signed by the Contractor or his Project Manager. Failure to submit the daily reports could result in payments being withheld until such time as all daily reports are current.
E.3 FINAL INSPECTION
a. Contractor Self-Inspection. Prior to the completion date of each task order, the Contractor’s Quality Control Manager shall conduct a self-inspection of the site and document all items needing correction by means of a punch list. The corrected punch list shall be provided to the Contracting Officer’s Representative at the same time the pre-final inspection is requested. All punch list items must be corrected prior to requesting the pre-final inspection.
b. The Contractor and the Contracting Officer’s Representative will jointly conduct a pre-final inspection prior to requesting a final inspection. Any item needing correction shall be noted on the Pre-Final Inspection Punch List. Any discrepancies noted will be corrected prior to any final inspection. The Contracting Officer Representative may schedule more than one pre-final inspection if he determines it necessary.
c. When the Contractor is ready for final inspection, he will request final inspection in writing to the Contracting Officer and Contracting Officer’s Representative (COR). A copy of the Pre-Final Punch List shall be attached to this request with the corrective action taken noted. The final inspection will be requested at least 48 hours before the desired date.
d. The final inspection shall be performed with the Contractor by the COR, Contracting Officer, Safety Officer, and representatives of the using activity. Any discrepancies noted will be corrected within the time specified in each task order for the completion of work.
e. Prior to close-out and final payment of each task order, the following are required:
1. All submittals. To be submitted as required by each task order and may include product submittals, as-built drawings, manuals, etc.
2. All warranties. To be submitted with the request for Final Inspection.
3. Contractor’s Release: To be submitted with the Contractor’s final invoice.
SECTION F
DELIVERIES AND PERFORMANCE
F.1 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION
OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the time stated in each individual task order. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
F.2 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of (each task order will specify the amount of liquidated damages) for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F.4 52.211-13 TIME EXTENSIONS (SEP 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
F.5 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party.
The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.
F.6 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least TWENTY (20) percent of the total amount of work to be performed under the contract.
This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the contracting Officer determines that the reduction would be to advantage of the Government.
F.7 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government.
In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
F.8 52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted
(1) by an act of the Contracting Officer in the administration of this contract, or
(2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
F.9 FAIR OPPORTUNITY PROCEDURES
Task order competitions will be consistent with FAR 16.505 procedures.
F.10 TASK ORDER (TO)
(a) A task order is the contractual instrument issued by the Government to the Contractor to order work. The task order is issued upon agreement between the Government and the Contractor on the scope of work, performance time, and the fixed price for the work. The task order award will be the Notice-To-Proceed. Each individual task order becomes a fixed priced lump sum contract. Order for Supplies or Services Form, OF 347 will be issued for each task order.
(b) Orders placed under this indefinite delivery contract shall contain the following information:
(1) Date of order
(2) Contract number and order number
(3) Item number and scope of work
(4) Delivery or performance date
(5) Place of delivery or performance
(6) Packaging, packing, and shipping instructions
(7) Accounting and appropriation data
(8) Bonding requirements
(9) Any other pertinent information
(c) Modifications to task orders may be required due to differing site conditions, increased scope of work or a decreased scope of work. Modifications are issued pursuant to specific standard clauses contained in the basic contract. If a modification to a task order is required, the Contractor shall submit a detailed cost proposal to include at minimum the following:
material cost breakdown, labor rate breakdown, overhead, and profit.
(d) All task orders are subject to the terms and conditions of this contract. In the event of conflict between a task order and this contract, the contract shall control.
(e) In accordance with FAR 52.216-19, the minimum single order amount is $4,000,000.00 and the maximum single order amount is $100,000,000.00.
F.11 GUARANTEED MINIMUM AMOUNT
In accordance with FAR 52.216-22(b), the guaranteed minimum quantity of work the Government agrees to order during the life of the contract, including any options exercised is $10,000.00.
F.12 OVERALL CONTRACT MAXIMUM QUANTITY
The aggregate capacity that the Government may order under all NMACC contracts is $1,500,000,000.00.
F.13 CONTINUITY OF FACILITIES OPERATION
Schedule work to minimize interference with any on-site housing residents and the facilities normal operations. Notify the Contracting Officer and Project Manager 24 hours in advance of any shutdowns. Perform all on-site work between the hours of 7:00 AM and 5:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer.
F.14 RECYCLING AND DISPOSAL OF REFUSE
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposal shall be done in accordance with federal, state, and local laws and regulations.
SECTION G
CONTRACT ADMINISTRATION
DATA
G.1 INSTRUCTIONS FOR SUBMITTING MATERIAL APPROVALS
Submittals must be provided in sufficient time and in such sequence to avoid delays in the work. Test reports and certifications shall be submitted and approved prior to payment for the applicable item. Corrected O&M Manuals must be received by the Government prior to the Final Inspection. Materials, samples, drawings, etc., shall be submitted on the Government provided form.
G.2 AUTHORIZED REPRESENTATIVES OF THE CONTRACTING OFFICER
The Contracting Officer's Representative (COR) is the representative of the Contracting Officer for the purpose of day to day technical administration/inspection of all work under the contract. This includes, but is not limited to, administration of progress, approval of submittals, final inspection and providing technical assistance when required. The contractor is cautioned that in no instance is the COR authorized to approve any changes which will involve the quantity, quality, price or performance of the contract. CORs will be designated on individual task orders issued under the contract.
G.3 ADDRESS OF CORRESPONDENCE
All correspondence for the basic contract, unless otherwise specified, shall be directed to the following address:
(a) The address and telephone number of the principal Contracting Officer is:
U.S. Coast Guard
Facilities Design and Construction Center 5505 Robin Hood Rd., Suite K
Norfolk, Virginia 23513
Phone Number: (757) 852-3449
FAX: (757) 852-3495
Email: Pamela.j.argilan@uscg.mil
NOTE: All correspondence for individual Task Orders shall be addressed to the issuing contracting office and shall include the Contract Number and Task Order Number.
SECTION H
SPECIAL CONTRACT REQUIREMENTS
H.1 WORK OUTSIDE REGULAR WORK HOURS
If the contractor desires to perform work under this contract outside regular work hours or on Saturdays, Sundays or holidays, he shall apply, in writing, to the Contracting Officer no less than 10 calendar days prior to the planned start of such work. Regular work hours are, for the purpose of this clause, those hours the activity or Command where the work is to be performed normally works on a day-by-day basis. Application by the Contractor does not imply consent by the Government. Each application will be considered, and a decision made, on the potential benefit of permitting such work. Approval of a Contractor's application under this clause will be, unless otherwise agreed in writing, at no additional cost to the Government.
H.2 DRAWINGS AND OTHER DATA TO BECOME PROPERTY OF GOVERNMENT
All designs, drawings, specifications, notes and other works developed in the performance of this contract shall become the sole property of the Government and may be used on any other design or construction without additional compensation to the Contractor. The Government shall be considered the "person for whom the work was prepared" for the purpose of authorship in any copyrightable work under 17 U.S.C. 201(b). With respect thereto, the Contractor agrees not to assert or authorize others to assert any rights nor establish any claim under the design patent or copyright laws.
H.3 REQUIRED INSURANCE
The contractor shall procure and maintain insurance for each task order during the entire period of performance consistent with FAR 52.2228-5, HSAR 3052.228-70, and FAR 28.307, which states the following minimum amounts of liability:
(a) Workers’ Compensation and Employer’s Liability. Contractors are required to comply with applicable Federal and State worker’s compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)
(b) General Liability. (1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.
(c) Property damage liability insurance shall be required only in special circumstances as determined by the agency.
(c) Automobile Liability. The Contracting Officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contracting Officer shall require aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury other than passenger liability, and $200,000 per occurrence for property damage.
Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
(e) Vessel Liability. When contract performance involves use of vessels, Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance.
ATTENTION OFFEROR: IF A PROJECT INVOLVES WORK ON NAVIGABLE
WATERS, LONGSHOREMEN’S AND HARBORWORKER’S COMPENSATION ACT
(33 U.S.C. 901) MAY BE APLLICABLE.
H.4 VEHICLE PASSES
The Contractor shall obtain a temporary vehicle pass, if required at the DHS location where performance is to take place.
To obtain a temporary vehicle pass, the Contractor must have in his possession at the time of application, a current vehicle registration card for each vehicle he wishes to register, a current valid driver’s license for each operator, and proof of insurance covering each vehicle to be registered.
If the Contractor changes vehicles, or a new vehicle is used, a new vehicle pass will be needed.
CONTRACTOR'S SHALL NOT EXCHANGE VEHICLE PASSES
A violation of the Base Security Regulations or Motor Vehicle Regulations could result in the Contractor being barred from the base, and the contract terminated for default.
H.5 SIGNAL LIGHTS (FOR MARINE WORK ONLY)
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as approved by the Secretary of the Army and the Commandant, U.S. Coast Guard.
H.6 VOLATILE ORGANIC COMPOUNDS (VOC) COMPLIANCE PLAN
(a) Contractor's are required to comply with local VOC laws and regulations and shall have an acceptable VOC compliance plan. The plan shall demonstrate that the use of paints, solvents, adhesives and cleaners comply with local VOC laws and regulations governing VOC materials, and that all required permits have been obtained or will be obtained prior to starting work involving VOC's, in the air quality district in which the work will be performed.
(b) The compliance plan shall be submitted by the Contractor to the Contracting Officer within five calendar days after receipt of a Task order, and prior to the use of any "VOC" materials on the project site. The Government will approve or disapprove the Contractor's compliance plan within five calendar days after receipt. Should the Government reject the compliance plan, the Contractor shall resubmit a revised compliance plan within three calendar days after receipt of the rejection notification. Failure on the part of the Contractor to submit an acceptable "VOC" plan, shall not be grounds for a time extension to the performance period.
(c) An acceptable compliance plan shall contain, as a minimum:
(i) A listing of each material subject to restrictions in the air quality management district in question;
(ii) The rule governing its use;
(iii) A description of the actions which the Contractor will use to comply with the laws and regulations, and plans to report to the Contracting Officer any changes in the status of compliance during the life of the contract.
(iv) Alternatively, if no materials are subject to the restrictions in the air quality management district where the work will be performed, or if there are no restrictions, the compliance plan shall so state.
H.7 MISPLACED MATERIAL (FOR MARINE WORK ONLY)
Should the Contractor, during the progress of the work, lose, dump, throw overboard, sink, or misplace any material, plant, machinery, or appliance, which in the opinion of the Contracting Officer may be dangerous to or obstruct navigation, the Contractor shall recover and remove the same with the utmost dispatch. The Contractor shall give immediate notice, with description and location of such obstructions, to the Contracting Officer or inspector and when required shall mark or buoy such obstructions until the same are removed. Should he refuse, neglect, or delay compliance with the above requirements, such obstructions may be removed by the Contracting Officer, and the cost of such removal may be deducted from any money due or to become due the Contractor, or may be recovered under his bond. The liability of the Contractor for the removal of a vessel wrecked or sunk without fault or negligence shall be limited to that provided in Section 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et seq).
H.8 WAGE RATES
Applicable Construction Wage Rate Requirements are in effect at the time of issuance of a Task Order and will apply. Contractors will be provided with the wage determination prior to issuance of a task order for pricing purposes. If crafts or trades are required in the performance of this project for which no wage is listed in the Department of Labor Wage Decision, the Contracting Officer shall be notified in writing.
H.9 CERTIFICATION OF PAYMENTS-RELEASE OF CLAIM
The Contractor, prior to receiving a progress or final payment under this contract, shall submit to the Contracting Officer a certification that the Contractor has made payment from proceeds of prior payments, or that he will make timely payment from the proceeds of the progress or final payment then due him, to his subcontractors and suppliers in accordance with his contractual arrangements. The Contractor shall submit to the Contracting Officer, together with his request for final payment, a properly executed Contractor's Release, DHS form 700-3.
Failure to submit this completed release shall result in delay of final payment.
H.10 SUBCONTRACT DATA
The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be done before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flow-down" contract clauses have been included in his contract in accordance with FAR Clause 52.222-11. The Prime Contractors will be given copies of Form SF 1413 after award of a contract. Completing this form creates no contractual relationship between subcontractors and the Government.
H.11 CONTRACTOR SECURITY REQUIREMENTS
At the Pre-construction Conference [or prior to beginning work on any task order], the Contractor shall provide a list of all on-site personnel, including sub-contractors (including second and third-tier subcontractors) and suppliers, to the Contracting Officer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the Coast Guard facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard facility.
Contractor personnel shall have photo identification at all times while working on Coast Guard facilities. Contractors shall provide the COR with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, etc...) and provide the company name, delivery person, and phone number of the firm(s) making deliveries.
Otherwise access to the Coast Guard facility may be denied. Special security provisions may apply to some task orders. Employees may be required to submit to a background check and be United States citizens.
H.12 REAL ID ACT OF 2005
The Real ID Act of 2005 established minimum security standards for license issuance and production and prohibits Federal agencies from accepting for certain purposes driver's licenses and identification cards from states not meeting the Act's minimum standards. To this purpose there are five states that are not in compliance with the Act nor have they received an extension to come into compliance with the act. Those states are Illinois, Minnesota, Missouri, New Mexico and Washington State.
Anyone under this contract, to include subcontractors, who holds a driver's license from any of states without approved licenses and require access to a military facility will be required to provide identification other than a driver's license to gain access. It is the responsibility of the Contractor to ensure that they are in accordance with the Real ID Act and any other requirements for base access. For the states of Washington and Minnesota an enhanced driver's license is acceptable to gain access. Other forms of identification that are acceptable for military facility access are included as an attachment to this modification.
Further information on the Real ID Act can be found here:
http://www.dhs.gov/real-id-enforcement-brie…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .