Replace Main Service Electrical Switchgear at U. S. Coast Guard Training Center, Yorktown, VA
Solicitation number
HSCG47-15-R-3EFK10
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
Amendment_No._0007.pdf PDF
Amendment_No._0006.pdf PDF
6327535_J A-Obvius_System_Redacted.pdf PDF
Amendment_No._0005.pdf PDF
Amendment_No._0004.pdf PDF
Amendment_No._0003.pdf PDF
Amendment_No._0002.pdf PDF
Amendment_No._0001.pdf PDF
Past_Performance_Questionaire.pdf PDF
Drawings.pdf PDF
Specifications.pdf PDF
Wage_Decision.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTICE FOR FILING AGENCY PROTESTS

United States Coast Guard Ombudsman Program

It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the Government Accountability Office (GAO).

Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative Dispute Resolution (ADR) forum rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.

Informal Forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the Contracting Officer is unable to satisfy their concerns, interested parties are encouraged to contact the U.S. Coast Guard Ombudsman for Agency Protests. Under this informal process the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).

Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest to either the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program. Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103(d) (2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely protests must be filed within the period specified in FAR 33.103(e).

Formal protests filed under the OPAP program should be submitted to:

COMMANDANT (CG-9131)

U S COAST GUARD

OMBUDSMAN PROGRAM FOR AGENCY PROTESTS

2100 2ND ST SW STOP 7112

WASHINGTON DC 20593-7112

The Ombudsman Hotline telephone number is 202.372.3695.

SOLICITATION, OFFER, 1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

AND AWARD SEALED BID (IFB)

(Construction, Alteration, or Repair) HSCG47-15-R-3EFK10 NEGOTIATED (RFP) 6/16/15 1 of 37 IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

HSCG47-15-C-3EFK10 2115415PFY013 6327535

7. ISSUED BY CODE : 8. ADDRESS OFFER TO

CONTRACTING DIVISION, USCG CONTRACTING DIVISION, USCG

FACILITIES DESIGN & CONSTRUCTION CENTER FACILITIES DESIGN & CONSTRUCTION CENTER

5505 ROBIN HOOD ROAD, SUITE K 5505 ROBIN HOOD ROAD, SUITE K

NORFOLK, VIRGINIA 23513-2431 NORFOLK, VIRGINIA 23513-2431

9. FOR INFORMATION A. NAME B. TELEPHONE NO. (include area code) (NO COLLECT CALLS)

CALL: Dannetta Townsend, Contracting Officer (757) 852-3407 FAX (757) 852-3495

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder”.

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

REPLACE MAIN SERVICE ELECTRICAL SWITCHGEAR AT U.S. COAST GUARD TRAINING

CENTER, YORKTOWN, VA

Provide all materials, labor, equipment, services, and all operations necessary to perform all work in accordance with applicable clauses, provisions, special contract requirements, specifications and drawings, and evaluation factors as set forth in Section A, Page 3.

THIS IS AN ECONIMICALLY DISADVANTAGED WOMEN-OWNED SMALL BUSINESS (EDWOSB) SET-ASIDE.

NAICS CODE: 238210 SIZE STANDARD: $15 MILLION

***PLEASE SEE SECTION H.9 AND H.12 FOR EDWOSB SPECIAL CONTRACT REQUIREMENTS FOR OFFERORS AND SECTION M, EVALUATION FACTORS FOR AWARD.

CAUTION TO OFFERORS: Offerors are urged to visit the site and take such steps as may be reasonably necessary to ascertain the nature and exact location of the work. Failure to visit the site for this purpose does not relieve offerors from the responsibility for estimating properly the difficulty or cost of successfully performing the work.

11. The Contractor shall begin performance within 14 calendar days and complete it within 224 calendar days after receiving.

award, notice to proceed. This performance period is mandatory, negotiable. (See SECTION F ) 12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? 12B. CALENDAR DAYS (If “Yes”, indicate within how many calendar days after award in Item 12B.) 14 YES NO Performance and Payment bonds must be approved prior to commencement of work (See Section I)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Proposals in original and one copy to perform the work required are due at the place specified in Item 8 by 2:00 PM. (hour) local time July 16, 2015 (date).

If this is a sealed bid solicitation, offers, will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required. (See Section I)

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA NSN 7540-01-155-3212 1442-102 FAR (48 CFR) 53.235-1(d)

OFFER (Must be fully completed by offeror) HSCG47-15-R-3EFK10 PAGE 2 OF 37

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

DUNS NUMBER: (Must be filled in)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if the offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum re-quirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SECTION B

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20B. SIGNATURE 20C. OFFER DATE (Type or print)

AWARD (To be completed by Government)

21. ITEM ACCEPTED:

CONTRACT COMPLETION DATE:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

(4 COPIES UNLESS OTHERWISE SPECIFIED) 27 10 U.S.C.2304(c) ( 5 ) 41 U.S.C.253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING DIVISION, USCG

U.S. COAST GUARD FINANCE CENTER

FACILITIES DESIGN & CONSTRUCTION CENTER 1430A KRISTINA WAY

5505 ROBIN HOOD ROAD, SUITE K CHESAPEAKE, VA 23326

NORFOLK, VA 23513-2431

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this 29. AWARD (Contractor is not required to sign this document.) Your offer document and return 1 copies to issuing office.) Contractor agrees on this solicitation is hereby accepted as to the items listed. This award con-to furnish and deliver all items or perform all work requirements identified summates the contract, which consists of (a) the Government solicitation and on this form and any continuation sheets for the consideration stated in this your offer, and (b) this contract award. No further contractual document is contract. The rights and obligations of the parties to this contract shall be necessary.

governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print) TO SIGN (Type or print)

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA 31C. AWARD

DATE

BY

GPO : 1985 O - 469-796 STANDARD FORM 1442 BACK (REV.4-85)

HSCG47-15-R-3EFK10

SECTION A

SOLICITATION/CONTRACT FORM

TABLE OF CONTENTS

(X) SECT DESCRIPTION PAGES(S)

PART I – THE SCHEDULE

X A SOLICITATION/CONTRACT FORM 1-3

X B SUPPLIES OR SERVICES AND PRICES/COSTS 4

X C DESCRIPTION/SPECS/WORK STATEMENT 5

X D PACKAGING AND MARKING 6

X E INSPECTION AND ACCEPTANCE 7

X F DELIVERIES OR PERFORMANCE 8-9

X G CONTRACT ADMINISTRATION DATA 10

X H SPECIAL CONTRACT REQUIREMENTS 11-17

PART II – CONTRACT CLAUSES

X I CONTRACT CLAUSES 18-26

PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

X J LIST OF ATTACHMENTS 27

PART IV – REPRESENTATIONS AND INSTRUCTIONS

X K REPRESENTATIONS, CERTIFICATIONS AND OTHER

STATEMENTS OF OFFERORS

28-32

X L INSTRUCTIONS, CONDITIONS AND NOTICES TO

OFFERORS

33-35

X M EVALUATION FACTORS FOR AWARD 36-37

The estimated cost of this project ranges between $500,000 and $1,000,000.

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Replace Main Service Electrical Switchgear at United States Coast Guard Training Center (TRACEN) Yorktown, Virginia. All work shall be in accordance with the Specification No. 6327535 and Drawing Nos.

3-174-1 through 3-174-16.

BASE ITEM:

Provide all materials, labor, equipment, services, and all operations necessary to Replace Main Service Electrical Switchgear at United States Coast Guard Training Center (TRACEN) Yorktown, Virginia.

BASE ITEM $

NOTE 1: The Base Item shall be deemed to include all costs required for the specified work to be completed in accordance with the drawings and specifications.

SECTION C

DESCRIPTION/SPECIFICATIONS

SEE SECTION "J".

SECTION D

PACKAGING AND MARKING

SECTION "D" IS NOT APPLICABLE.

SECTION E

INSPECTION AND ACCEPTANCE

E.1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not--

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may--

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

SECTION F

DELIVERIES OR PERFORMANCE

F.1 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)

(a) The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date of award, (b) prosecute the work diligently, and (c) complete the entire work ready for use within 224 calendar days after award for the Base Item.

F.2 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $438.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

F.3 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer.

If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

F.4 52.242-14 SUSPENSION OF WORK (APR 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted

(1) by an act of the Contracting Officer in the administration of this contract, or

(2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed—

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

SECTION G

CONTRACT ADMINISTRATION DATA

G.1. INSTRUCTIONS FOR SUBMITTING MATERIAL APPROVALS

Materials, samples, drawings, etc., shall be submitted on "Material Approval Request" form. Schedule submittals to expedite Project, and deliver to the COR at TRACEN Yorktown Facilities Engineering.

Coordinate submission of related items.

G.2. AUTHORIZED REPRESENTATIVES OF THE CONTRACTING OFFICER

Ms. Jeanine Wong is the Contracting Officer's Representative for the purpose of day-to-day technical administration/inspection of all work under the contract. This includes, but is not limited to, administration of progress, approval of submittals, final inspection and providing technical assistance when required.

The contractor is cautioned that in no instance is the above named person authorized to approve any changes which will involve the quantity, quality, price or performance of the contract.

TBD is the representative of the Contracting Officer for the purpose of inspection of work under the contract. The Contractor is cautioned that in no instance are the above named people authorized to approve any changes, which will involve the quantity, quality, price, or performance of the contract.

Mrs. Dannetta Townsend of the Contracting Division, U.S. Coast Guard, Facilities Design & Construction Center, 5505 Robin Hood Road, Suite K, Norfolk, VA 23513-2431, telephone number (757) 852-3407, is the Contracting Officer's Administrator/Negotiator for this contract. All matters related to performance of this contract shall be coordinated through her.

SECTION H

SPECIAL CONTRACT REQUIREMENTS

H.1 52.246-21 WARRANTY OF CONSTRUCTION (APR 1984)

a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of—

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause.

The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall—

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

H.2 PRICING OF ADJUSTMENTS

When costs are a factor in any determination of a contract price adjustment pursuant to the Changes Clause or any other provision of this contract, such costs shall be in accordance with the contract cost principles and procedures in Part 31 of the Federal Acquisition Regulations, as applicable, which are in effect on the date of this contract.

H.3 WORK OUTSIDE REGULAR WORK HOURS

See Specification Section 01 11 00, Part 1, Paragraph 1.7.

H.4 SAFETY AND HEALTH

(a) The Contractor shall take all reasonable safety and health measures in performing under this contract and shall, to the extent set forth in the Schedule of the contract, submit a safety plan and a health plan for the Contracting Officer's approval. The Contractor is subject to (i) all applicable Federal, state and local laws, regulations, ordinances, codes and orders relating to safety and health in effect on the date of this contract; (ii) shall comply with all pertinent provisions of the latest version of the U. S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of this contract;

and (iii) shall comply with the Safety and Health Standards, specifications and issuances, reporting requirements, and provisions as set forth in the Schedule of the contract.

(b) Further, the Contractor shall take or cause to be taken such other safety and health measures as the Contracting Officer shall direct. To the extent that the Contractor is entitled to an equitable adjustment under the terms and conditions of this contract, or any other obligations of the parties, such equitable adjustment shall be determined pursuant to the procedures of the clause of this contract entitled "Changes"; provided, that no adjustment shall be made under this clause for any change for which an equitable adjustment is expressly provided under any other provision of this contract.

(c) The Contractor shall immediately notify and promptly report to the Contracting Officer or his representative, any accident or incident or exposure resulting in fatality, disabling occupational injury or occupational disease or contamination of property beyond stated acceptable threshold limits set forth in the Schedule of the contract, or property loss of $10,000 or more arising out of work performed under this contract; provided, however, the Contractor will not be required to include in any report an expression of opinion as to the fault or negligence of any employee. In addition, the Contractor shall comply with any illness, incident and injury experience reporting requirement set forth in the Schedule of the contract. The Contractor will investigate all such work related incidents or accidents to persons and property to the extent necessary to positively conclude what cause or causes resulted in said accident or incident, and furnish the Contracting Officer with a report, in such form as the Contracting Officer may require, of the investigative findings, together with proposed and/or completed corrective actions.

(d) (1) The Contracting Officer may, from time to time, notify the Contractor in writing of any noncompliance with the provisions of this clause and may specify corrective actions to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action.

(2) If the Contractor fails or refuses to institute prompt corrective action in accordance with (d)(1) above, the Contracting Officer may invoke the provisions of the clause in the contract entitled "Stop Work", or may invoke whatever other rights are available to the Government under the terms and conditions of this contract or at common law, to remedy such failure or refusal to institute prompt corrective action.

(e) The Contractor (or subcontractor or supplier) shall cause the substance of this clause including this paragraph (e) and any applicable Schedule Provisions, with appropriate changes of designations of the parties to be inserted in subcontracts of every tier which: (i) Amount to $1,000,000 or more unless the Contracting Officer makes a written determination that this is not required; (ii) require construction, repair, or alteration in excess of $10,000; or (iii) the Contractor, regardless of dollar amount, determines that hazardous materials or operations are involved.

(f) The Contractor agrees that authorized Government representatives of the Contracting Officer shall have access to and the right to examine the sites or areas where work under this contract is being performed to determine the adequacy of the Contractor's safety and health measures under this clause.

H.5 WAGE RATES

If crafts or trades are required in the performance of this project for which no wage is listed in the Department of Labor Wage Decision (See Section J), the Contracting Officer shall be notified in writing.

No work in unlisted crafts or trades will be permitted until a wage has been negotiated between the Contracting Officer and the Contractor.

H.6. REQUIRED INSURANCE

The contractor shall procure and maintain insurance during the entire period of his performance under this contract, in accordance with Federal Acquisition Regulation Clause No. 52.228-5, entitled “INSURANCE - WORK ON A GOVERNMENT INSTALLATION”. (See Section I) FAR 28.307-2 states the following minimum amounts of liability:

(a) Workers’ Compensation and Employer’s Liability. Contractors are required to comply with applicable Federal and State worker’s compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)

(b) General Liability. (1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence (2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.

(c) Automobile Liability. The Contracting Officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contracting Officer shall require aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel Liability. When contract performance involves use of vessels, Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance.

(f) Prior to commencement of work hereunder, the contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective until thirty (30) days after written notice thereof to the Contracting Officer. The contractor agrees to insert the substance of this clause, including this paragraph, in all subcontracts hereunder.

ATTENTION OFFEROR: IF THIS PROJECT INVOLVES WORK ON NAVIGABLE WATERS,

LONGSHOREMEN’S AND HARBORWORKER’S COMPENSATION ACT (33 U.S.C. 901) IS

APPLICABLE.

H.7 DRAWINGS AND OTHER DATA TO BECOME PROPERTY OF GOVERNMENT

All designs, drawings, specifications, notes and other works developed in the performance of this contract shall become the sole property of the Government and may be used on any other design or construction without additional compensation to the Contractor. The Government shall be considered the "person for whom the work was prepared" for the purpose of authorship in any copyrightable work under 17 U.S.C.

201(b). With respect thereto, the Contractor agrees not to assert or authorize others to assert any rights nor establish any claim under the design patent or copyright laws.

H.8. SYSTEM FOR AWARD MANAGEMENT SYSTEM

ALL OFFERORS MUST BE REGISTERED IN THE CENTRAL CONTRACTOR

REGISTRATION (CCR) IN SYSTEM FOR AWARD MANAGEMENT (SAM) DATABASE AS

AN ECONOMICALLY DISADVANTAGED WOMEN-OWNED SMALL BUSINESS

(EDWOSB) BY THE PROPOSAL DUE DATE. All Coast Guard vendors must be registered in the CCR through the SAM database PROPOSAL DUE DATE in order to receive payments by Electronic Funds Transfer. For more information or to register online, visit the SAM website:

http://www.sam.gov or call the U. S. Coast Guard Finance Center Customer Service line at

(757) 523-6940 or 1-800-564-5504.

H.9 ENGLISH

All communications, written, and oral between the contractor and the Government in connection with this contract shall be in the English Language, and any system of dimensions (English or Metric) shown shall be consistent with that used in the contract.

H.10 CENTRALIZED INVOICE SUBMITTAL PROCEDURES

The following Centralized Invoice Submittal Procedures are being incorporated into this contract:

(a) Invoices shall be prepared and submitted in accordance with the provision of FAR 52.232-27, “Prompt Payment for Construction Contracts.”

(b) Each invoice shall contain the following information:

(1) Contract or Delivery/Task Order Number

(2) Name of the Contract Specialist or Contracting Officer

(3) Invoice Routing Code (IRC) assigned by the Coast Guard

(4) Annotate on the invoice indicating that the contractor represents a small business for accelerated payment purposes.

(c) The Coast Guard unique Invoice Routing Code (IRC) for this contract or delivery/task order is:

FDCCLANT

(d) Each invoice must be submitted to the designated billing office via one of the following modes, listed in descending order of preference:

(1) FINCEN Website invoice receipt form:

http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm

(2) Fax: (757) 523-6900

(3) Mailed to: Commercial Invoices

U.S. Coast Guard Finance Center 1430A Kristina Way Chesapeake, VA 23326

(e) To facilitate processing, all proper invoices and any supporting information submitted electronically using the FINCEN web based invoice submission capability must be submitted as a single Adobe pdf formatted file, or as otherwise specified in the contract.

http://www.sam.gov/ http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm

(f) Supporting documentation along with a courtesy copy of the invoice may also be e-mailed to the Contract Specialist and/or COR at the addresses cited below:

Dannetta.N.Townsend@uscg.mil Contracting Officer

Jeanine.Y.Wong@uscg.mil Contracting Officer Representative

(g) Original Payrolls and submittals shall be mailed to the Contracting Officer with copies mailed to the Government Construction Inspector cited below:

Contracting Officer: Dannetta Townsend Facilities Design & Construction Center 5505 Robin Hood Rd, Suite K Norfolk, VA 23513

Government Construction Inspector: TBD

(h) In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice shall be deemed to have been received:

(1) On the later of:

(i) For invoices that are mailed or transmitted via facsimile, the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.

(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or

(ii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—

a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date shall substitute for the seventh day after the delivery date; or

b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends shall substitute for the seventh day after the delivery date;

(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or

(3) Web based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.

(4) Payment inquiries and status may be obtained - at the following website:

https://www.fincen.uscg.mil/secure/payment.htm mailto:Dannetta.N.Townsend@uscg.mil mailto:Jeanine.Y.Wong@uscg.mil https://www.fincen.uscg.mil/secure/payment.htm

H.11 WOMEN-OWNED SMALL BUSINESS (WOSB) PROGRAM REPOSITORY

(a) In order for the offeror to be eligible for award, mandatory verification of the offeror’s Economically EDWOSB certification status will be verified by the Contracting Officer through the Women-Owned Small Business Program Repository (https://eweb.sba.gov/gls/dsp_sbabanner.cfm?CFID=14502474&CFTOKEN=f26be6da29a92dd8- DB6391EC-088B-F512-ACE0D85C2696158A&jsessionid=5e305541548898a2bd1a11253a37781b284d) to ensure all required documents have been submitted. The WOSB Program Repository is a document repository maintained by Small Business Administration (SBA) to house the documents submitted by EDWOSBs that would verify the concern’s eligibility, to include copies of Third Party Certifications. The WOSB Program Repository is a secure, web based environment that is accessible to the individual EDWOSBs, the Contracting Officer community and SBA. The Contracting Officer will be able to access the documents prior to contract award to review the submitted documents. An Economically Disadvantage Women-Owned Small Business must:

(1) be certified by a Federal agency, a State government, or a national certifying entity approved by the Small Business Administrator, as a small business concern owned and controlled by one or more women (referred to as a Third Party Certifier); or,

(2) certify to the contracting officer that it is a small business concern owned and controlled by women. The EDWOSB must provide adequate documentation, in accordance with standards established by Small Business Administration, to support such certification.

(b) The following is a list of documents that must be submitted to the WOSB Program Repository prior to submitting an offer on a EDWOSB Requirement.

(1) Third Party Certifications – If the WOSB or EDWOSB has received a Third Party Certification then it must provide the following:

a. a copy of the Third Party Certification to the WOSB Program Repository prior to initial offer.

b. a copy of the joint venture agreement, if applicable to the requirement.

c. a signed copy of the Women-Owned Small Business Program Certification-

EDWOSB.

(2) Self Certification – If the EDWOSB is self-certifying, then it must provide the following:

a. Copies of birth certificates, Naturalization papers, or unexpired passports for owners who are women;

b. Copy of the joint venture agreement, if applicable;

c. For limited liability companies:

1. Articles of organization (also referred to as certificate of organization or articles

2. of formation) and any amendments; and

3. Operating agreement, and any amendments;

d. For corporations:

1. Articles of incorporation and any amendments;

2. By-laws and any amendments;

3. All issued stock certificates, including the front and back copies, signed in accord with the by-laws;

https://eweb.sba.gov/gls/dsp_sbabanner.cfm?CFID=14502474&CFTOKEN=f26be6da29a92dd8-DB6391EC-088B-F512-ACE0D85C2696158A&jsessionid=5e305541548898a2bd1a11253a37781b284d https://eweb.sba.gov/gls/dsp_sbabanner.cfm?CFID=14502474&CFTOKEN=f26be6da29a92dd8-DB6391EC-088B-F512-ACE0D85C2696158A&jsessionid=5e305541548898a2bd1a11253a37781b284d

4. Stock ledger; and

5. Voting agreements, if any;

e. For partnerships, the partnership agreement and any amendments;

f. The assumed/fictitious name (doing business as) certificate(s); and

g. A copy of the WOSB Program Certification – EDWOSB

h. SBA Form 413, Personal Financial Statement for each woman claiming economic disadvantage.

(b) ON THE PROPOSAL DUE DATE AND PRIOR TO SUBMITTING YOUR OFFER, the EDWOSB offeror will log into the WOSB Program General Login System (GLS) and select the Federal Agency (United States Coast Guard) and Contracting Officer (Dannetta N. Townsend) for that requirement from a drop down menu to then authorize that individual to have access to the business’ documents. The EDWOSB will also have to enter the solicitation number: HSCG47-15-3EFK10.

SECTION I

CONTRACT CLAUSES

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):http://farsite.hill.af.mil/vffara.htm and http://www.dhs.gov/interweb/assetlibrary/DHS_HSAR_With_Notice_04-01.pdf and http://www.dhs.gov/interweb/assetlibrary/HSAM-with-Notice-04-01.pdf

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far http://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-regulation-0606.pdf http://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-manual-1206.pdf

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 19) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

52.202-1 DEFINITIONS (NOV 2013)

52.203-3 GRATUITIES (APR 1984)

52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT

(SEPT 2006)

52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR

IMPROPER ACTIVITY (MAY 2014)

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS

(OCT 2010)

52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO

INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)

52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POST CONSUMER FIBER CONTENT

PAPER (MAY 2011)

52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013)

52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT

AWARDS (JUL 2013)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JUL 2013)

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT

(AUG 2013)

http://farsite.hill.af.mil/vffara.htm http://www.dhs.gov/interweb/assetlibrary/DHS_HSAR_With_Notice_04-01.pdf http://www.dhs.gov/interweb/assetlibrary/HSAM-with-Notice-04-01.pdf http://www.acquisition.gov/far http://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-regulation-0606.pdf http://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-manual-1206.pdf

52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING

RESPONSIBILITY MATTERS (JUL 2013)

52.215-2 AUDIT AND RECORDS -NEGOTIATION (OCT 2010)

52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997)

52.215-11 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA

MODIFICATIONS (AUG 2011)

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2014)

52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011)

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)

52.219-29 NOTICE OF SET-ASIDE FOR WOMEN-OWNED SMALL BUSINESS (EDWOSB)

CONCERNS (APR 2012)

52.222-3 CONVICT LABOR (JUNE 2003)

52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT - OVERTIME

COMPENSATION (MAY 2014)

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)

52.222-7 WITHHOLDING OF FUNDS (MAY 2014)

52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)

52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)

52.222-12 CONTRACT TERMINATION-DEBARMENT (MAY 2014)

52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND

RELATED REGULATIONS (MAY 2014)

52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)

52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)

52.222-26 EQUAL OPPORTUNITY (APR 2015)

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION

(APR 2015)

52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUL 2014)

52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES (JUL 2014)

52.222-37 EMPLOYMENT REPORTS VETERANS (SEPT 2010)

52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR

RELATIONS ACT (DEC 2010)

52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015)

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (AUG 2013)

52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2014)

52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND

CONSTRUCTION CONTRACTS (SEPT 2013)

52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)

52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

52.223-12 REFRIGERATION EQUIPMENTS AND AIR CONDITIONERS (MAY1995)

52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (DEC 2007)

52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND

CONSTRUCTION CONTRACTS (MAY 2008)

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE

DRIVING (AUG 2011)

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)

52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)

52.227-2 NOTICES AND ASSISTANCE REGARDING PATENT & COPYRIGHT

INFRINGEMENT (DEC 2007)

52.227-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (DEC 2007)

52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)

52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

52.228-11 PLEDGES OF ASSETS (JAN 2012)

52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)

52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (OCT 2010)

Performance and Payment Bonds are required of the prospective contractor with any contract in excess of $100,000.00. Performance Bond, SF-25 and Payment Bond 25A, are required in an amount equal to 100 percent of the original contract price. Performance and payment bonds placed with a surety or sureties acceptable to the Government and in the amounts indicated shall be submitted within ten (10) calendar days after receipt of award and shall be maintained for the entire contract.

52.229-4 FEDERAL, STATE, AND LOCAL TAXES (STATE AND LOCAL ADJUSTMENTS)

(FEB 2013)

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)

52.232-17 INTEREST (MAY 2014)

52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (MAY 2014)

The due date for making such payments shall be 30 days after receipt of the payment request by the designated billing office.

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER-SYSTEM FOR AWARD

MANAGEMENT (JUL 2013)

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)

52.232-40 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS

SUBCONTRACTORS (DEC 2013)

52.233-1 DISPUTES (MAY 2014)

52.233-3 PROTEST AFTER AWARD (AUG 1996)

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

52.236-8 OTHER CONTRACTS (APR 1984)

52.236-9 PROTECTION OF EXISTINFG VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES AND IMPROVEMENTS…