Source Selection Information - See FAR 2.101 and 3.104
HQ0034-12-R-0002
Construction Management Technical Support Services Attachment 4 J-B1 Amendment 01 01-13-2012 Pricing Submission Worksheet
CLIN Summary
| CLIN |
| Supplies/Service |
| Full Time Equivalent Level |
| Quantity= |
12 months x FTE
| Unit |
| Unit Price |
| Extended Price |
| CLIN 0001 |
| CMTSS PROGRAM PRINCIPAL |
| 1 |
| 12 |
| month |
| CLIN 0002 |
| SENIOR ANALYST |
| 1 |
| 12 |
| month |
| CLIN 0003 |
| PROJECT MANAGER |
| 4 |
| 48 |
| month |
| CLIN 0004 |
| ESTIMATORS |
| 3 |
| 36 |
| month |
| CLIN 0005 |
| QA INSPECTORS * |
| 7 |
| 84 |
| month |
CLIN 0006
month
| CLIN 0007 |
| OFFICE ENGINEERS |
| 3 |
| 36 |
| month |
| CLIN 0008 |
| SCHEDULERS |
| 2 |
| 24 |
| month |
| CLIN 0009 |
| CONSTRUCTION MANAGERS |
| 7 |
| 84 |
| month |
| CLIN 0010 |
| DESIGN COORDINATORS |
| 6 |
| 72 |
| month |
CLIN 0011
| ASST DESIGN COORDINATOR |
| 1 |
| CLIN 0012 |
| TRANSITION SPECIALIST |
| 1 |
| 12 |
| month |
| CLIN 0013 |
| SAFETY INSPECTORS * |
| 4 |
| 48 |
| month |
| CLIN 0014 |
| COMMISSIONING SPECIALIST |
| 1 |
| 12 |
| month |
TOTAL
| CLIN 1001 |
| CMTSS PROGRAM PRINCIPAL |
| 1 |
| 12 |
| month |
| CLIN 1002 |
| SENIOR ANALYST |
| 1 |
| 12 |
| month |
| CLIN 1003 |
| PROJECT MANAGER |
| 4 |
| 48 |
| month |
| CLIN 1004 |
| ESTIMATORS |
| 3 |
| 36 |
| month |
| CLIN 1005 |
| QA INSPECTORS * |
| 7 |
| 84 |
| month |
CLIN 1006
| CLIN 1007 |
| OFFICE ENGINEERS |
| 3 |
| 36 |
| month |
| CLIN 1008 |
| SCHEDULERS |
| 2 |
| 24 |
| month |
| CLIN 1009 |
| CONSTRUCTION MANAGERS |
| 7 |
| 84 |
| month |
| CLIN 1010 |
| DESIGN COORDINATORS |
| 6 |
| 72 |
| month |
CLIN 1011
| ASST DESIGN COORDINATOR |
| 1 |
| CLIN 1012 |
| TRANSITION SPECIALIST |
| 1 |
| 12 |
| month |
| CLIN 1013 |
| SAFETY INSPECTORS * |
| 4 |
| 48 |
| month |
| CLIN 1014 |
| COMMISSIONING SPECIALIST |
| 1 |
| 12 |
| month |
TOTAL
| CLIN 2001 |
| CMTSS PROGRAM PRINCIPAL |
| 1 |
| 12 |
| month |
| CLIN 2002 |
| SENIOR ANALYST |
| 1 |
| 12 |
| month |
| CLIN 2003 |
| PROJECT MANAGER |
| 4 |
| 48 |
| month |
| CLIN 2004 |
| ESTIMATORS |
| 3 |
| 36 |
| month |
| CLIN 2005 |
| QA INSPECTORS * |
| 7 |
| 84 |
| month |
CLIN 2006
| CLIN 2007 |
| OFFICE ENGINEERS |
| 3 |
| 36 |
| month |
| CLIN 2008 |
| SCHEDULERS |
| 2 |
| 24 |
| month |
| CLIN 2009 |
| CONSTRUCTION MANAGERS |
| 7 |
| 84 |
| month |
| CLIN 2010 |
| DESIGN COORDINATORS |
| 6 |
| 72 |
| month |
CLIN 2011
| ASST DESIGN COORDINATOR |
| 1 |
| CLIN 2012 |
| TRANSITION SPECIALIST |
| 1 |
| 12 |
| month |
| CLIN 2013 |
| SAFETY INSPECTORS * |
| 4 |
| 48 |
| month |
| CLIN 2014 |
| COMMISSIONING SPECIALIST |
| 1 |
| 12 |
| month |
TOTAL
| CLIN 3001 |
| CMTSS PROGRAM PRINCIPAL |
| 1 |
| 12 |
| month |
| CLIN 3002 |
| SENIOR ANALYST |
| 1 |
| 12 |
| month |
| CLIN 3003 |
| PROJECT MANAGER |
| 4 |
| 48 |
| month |
| CLIN 3004 |
| ESTIMATORS |
| 3 |
| 36 |
| month |
| CLIN 3005 |
| QA INSPECTORS * |
| 7 |
| 84 |
| month |
CLIN 3006
| CLIN 3007 |
| OFFICE ENGINEERS |
| 3 |
| 36 |
| month |
| CLIN 3008 |
| SCHEDULERS |
| 2 |
| 24 |
| month |
| CLIN 3009 |
| CONSTRUCTION MANAGERS |
| 7 |
| 84 |
| month |
| CLIN 3010 |
| DESIGN COORDINATORS |
| 6 |
| 72 |
| month |
CLIN 3011
| ASST DESIGN COORDINATOR |
| 1 |
| CLIN 3012 |
| TRANSITION SPECIALIST |
| 1 |
| 12 |
| month |
| CLIN 3013 |
| SAFETY INSPECTORS * |
| 4 |
| 48 |
| month |
| CLIN 3014 |
| COMMISSIONING SPECIALIST |
| 1 |
| 12 |
| month |
TOTAL
| CLIN 4001 |
| CMTSS PROGRAM PRINCIPAL |
| 1 |
| 12 |
| month |
| CLIN 4002 |
| SENIOR ANALYST |
| 1 |
| 12 |
| month |
| CLIN 4003 |
| PROJECT MANAGER |
| 4 |
| 48 |
| month |
| CLIN 4004 |
| ESTIMATORS |
| 3 |
| 36 |
| month |
| CLIN 4005 |
| QA INSPECTORS * |
| 7 |
| 84 |
| month |
CLIN 4006
| CLIN 4007 |
| OFFICE ENGINEERS |
| 3 |
| 36 |
| month |
| CLIN 4008 |
| SCHEDULERS |
| 2 |
| 24 |
| month |
| CLIN 4009 |
| CONSTRUCTION MANAGERS |
| 7 |
| 84 |
| month |
| CLIN 4010 |
| DESIGN COORDINATORS |
| 6 |
| 72 |
| month |
CLIN 4011
| ASST DESIGN COORDINATOR |
| 1 |
| CLIN 4012 |
| TRANSITION SPECIALIST |
| 1 |
| 12 |
| month |
| CLIN 4013 |
| SAFETY INSPECTORS * |
| 4 |
| 48 |
| month |
| CLIN 4014 |
| COMMISSIONING SPECIALIST |
| 1 |
| 12 |
| month |
TOTAL
Offeror:
*The contractor will submit pricing to provide 2256 annual hours for CLINS 0005, 1005, 2005, 3005, and 4005 (QA Inspectors). Additionally, the contractor will submit pricing to provide 2256 annual hours for CLINS 0013, 1013, 2013, 3013, and 4013 (Safety Inspectors). All other labor categories will consist of 1880 annual hours. Offerors must include the increased hours of work within Section B (Pricing) of the solicitation.