About this file

This document is a Revision Narrative from MPS Engineering dated January 27, 2025, related to the Hollins High School Theatre Lights project (MPS Job #24038). The document details specific electrical plan revisions for Addendum #1, including modifications to various electrical plan sheets (E1-E6) and the Specification Section for Theatrical Stage Lighting. Revisions include editing projector receptacle specifications, adding booth lighting network equipment, adjusting lighting patch cable requirements, adding and removing various notes, and updating equipment quantities.

The revision narrative is part of a larger theater lighting renovation project for Pinellas County School Board in Florida, which involves disconnecting existing theatrical lighting systems and installing new lighting, video projection, and audio systems at Clearwater High School and Hollins High School. The project requires a Florida-licensed "EC" or "ES" Electrical Contractor and must comply with State Requirements for Educational Facilities (SREF) within the Florida Building Code. The document is signed by Edward J. Wolanin, Principal Electrical Engineer, and provides contact information for MPS Engineering located in Oldsmar, Florida.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISION NARRATIVE

Date: January 27, 2025 To: Mike McClimon Project: Hollins HS Theatre Lights MPS Job #: 24038

The following revisions have been made to the electrical plans:

Addendum #1

E1

• Edited projector receptacle to a 20 amp breaker

E3

• Added booth lighting network EQ rack and note number 12.

• Revised projector circuit wiring note number 7.

E4

• Removed outlet box specification in “MISC. LIGHTING EQUIPMENT”

• Adjusted “LIGHTING PATCH CABLE REQUIRMENTS”

• Added “Zoom” text to 4 torm pipes

E5

• Edited 7” touchscreen one line

• Removed dimming rack note

• Added flypipe riser diagram

E6

• Added Maintenance contract requirement note

Specification Section – 26_55_61 – Theatrical Stage Lighting

• Revised section 2.08 Equipment Quantities.

If you have any questions regarding the above mentioned, please call for clarification.

Sincerely, Edward J. Wolanin PE Principal Electrical Engineer

File details come from the government source that posted it. Updated .