Amend02 SF30.doc

DOC document 89 KB Posted

Attached to
Construct the New National Dwight D. Eisenhower Memorial in Washington, DC
Solicitation number
GS11P12MKC0005
Issued by

View the file

Other files

File Type Posted
Amend03 SF30.doc DOC document
EMC RFQ amendment 2 changes _r1.docx DOCX document
PreProp Site map.pdf PDF
Amend 01 Revised RFQ.docx DOCX document
PreProp Conf Sign In Sheets.pdf PDF
Final Amend01 SF30.doc DOC document
PreProposal Conference Notification.docx DOCX document
Agreement Eisenhower Memorial.docx DOCX document
EMC Firm Performance Questionaire.docx DOCX document
EMC KEY PERSONNEL PERFORMANCE QUESTIONNAIRE.docx DOCX document
RFQ Eisenhower Memorial.docx DOCX document
RFQ Reps Certs Eisenhower Memorial.docx DOCX document
PreProposal Conference Notification.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION OF SF 30: AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

GS11P10MMC0010, RECOVERY

Amendment No. 1

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE

GS11P12MKC0005

PAGE OF

PAGES

2. AMENDMENT/MODIFICATION NO.

Amendment 02 (RFQ)

3. EFFECTIVE DATE

03/26/2012

REQUISITION/PURCHASE REQ. NO.

PROJECT NO. (If applicable)

6. ISSUED BY
CODE
MK000
7. ADMINISTERED BY (If other than Item 6)
CODE
MK000

GSA, NCR, PBS,

Office of Project Delivery (WPC) 301 7th Street, SW Room 2002 Washington, DC 20407

GSA, NCR, PBS,

Office of Project Delivery (WPC)

301 7th Street, SW Room 2002

Washington, DC 20407

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

9.A. AMENDMENT OF SOLICITATION NO.

(X)
GS11P12MKC0005

To All Prospective Offerors

9B. DATED (SEE ITEM 11)

03/06/2012

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers FORMCHECKBOX is extended, FORMCHECKBOX is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning. copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegraph which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS

IT MODIFIES THE CONTRACT/ORDER NO. DESCRIBED IN ITEM 14.

(x)
A.

THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

c.

THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D.

OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor FORMCHECKBOX is not FORMCHECKBOX is required to sign this document and return ________ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible).

The solicitation is hereby amended as follows:

The following changes, clarifications, additions and supplements are hereby incorporated into this SOLICITATION in their entirety as submitted. Continued on Page 2 of this Amendment

Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) Bonnie Echoles, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED
16B. UNITED STATES OF AMERICA

BY

Bonnie Echoles .

(Signature of Contracting Officer)

16C. DATE SIGNED

03/26/2012

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

GSA Contract No. GS-11P-12-MK-C-0005

Construction Contract for Construction of Dwight D Eisenhower Memorial, Washington, DC

ITEM A:

THE QUALIFICATIONS PROPOSAL RECEIPT is UNCHANGED as follows:

WEDNESDAY, April 4, 2012, by 3:00 PM, EDT. Place of receipt as follows:

GSA, NCR, ROB – Bid Room 301 7th Street, SW, Room 1065 Washington, DC 20407 Phone: (202)708-5961

Due to renovations, the BID ROOM is scheduled to operate on Wednesdays and Fridays, 9:00 AM, EDT to 3:00 PM, EDT. Please be mindful when arranging for the delivery of packages.

ITEM B:

DELETE page 3 and page 24 of the RFQ Construction Contract Volume in their entirety and INSERT the attached, revised page 3 clarifying that a Standard Form 1442 is not to be issued, nor submitted, under this phase and revised page 24 correcting the number of pages allowed for submission, in lieu thereof.

ITEM C:

The attached RFQ Questions LOG is hereby incorporated into and made a part of this RFQ in its entirety as submitted.

ITEM D:

Offerors must acknowledge receipt of all Amendments, giving number and date, on Company Letterhead. This letterhead is not to be included in the not–to-exceed numbered page count of the Technical Proposal (Volume II).

END OF AMENDMENT NO. TWO (2)

Attachments:

RFQ Construction Contract Volume, Page 3 (Rev. 03/23/2012) RFQ Construction Contract Volume, Page 24 (Rev. 03/23/2012)

RFQ Questions LOG (03/23/2012)

RFQ Questions LOG

No
RFP Ref
Question
Answer
1
II.C.2

V.A.2

Do the past performance attachments for the Individuals need to be filled out for a project that is on the resume or can it be by any reference?
The individual’s performance questionnaire references should be submitted for projects that are included in the key person’s resume.
2
II.C.2

V.A.2

Clarify if QA/QC, Underground Utility Coordinator, and/or Artist/Artwork Coordinator are required to be fulltime positions.
The QA/QC Representative and Artist / Artwork Coordinator are full-time positions. The Underground Utility Coordinator position is full-time during the period in which underground utility work is being planned, coordinated, and is ongoing.
3
V.b
On pg 24, number (4), confirm reference to "Final Proposal Revision" is in reference to Stage II of the RFQ/RFP
The "Final Proposal Revision" reference applies to Stage II (the RFP) of the solicitation.
4
V.b
Do the past performance questionnaires, resumes, Representations and Certifications (C301), and GSA Form 527 count towards the 50 page limit?
The past performance questionnaires, Representations and Certifications (C301), and GSA Form 527 do not count towards the page limit. The key personnel resumes do count towards the page limit.
5
V.b
Please reconsider the page limit and increase to 65-75 pages due to the font considerations, double spacing, PPQs for the key personnel and resumes.
The page limitation is revised by Amendment.
6
none
Please supply the SF 1442
Not required for Phase I RFQ.
7
V
Should we include Tab 4 with a statement that the PPQ's will be sent directly to the GSA? The RFP tells us to present in the format as outlined in the RFP.
Yes. Please also indicate the source of the completed questionnaires, the name of the projects, and the names of the key personnel.
8
none
Will the short listed offerors who submit a PLA bid in Stage II of the procurement be given a preference (either in the form of an “evaluation factor” or a percentage credit) over those who submit only a non-PLA bid, as indicated in the current PIB?
To be determined before Stage II.
9
V.b
The page count indicates 50 pages and then 60 pages -- which one is correct?
The 50 page "Technical Proposal" reference applies to Stage I (the RFQ) of the solicitation. The 60 page "Final Proposal Revision" reference applies to Stage II (the RFP) of the solicitation. Please note the page count is revised by Amendment.
10
V.b
For the page count, I understand the cover letter is not included. However, are the following to be included in the page count: a) Title Page; b) Joint Venture Agreement (these can be very long); c) Reps and Certifications; d) GSA Form 527?
The Joint Venture Agreement (if any), Representations and Certifications, and GSA Form 527 do not count towards the page limit. The title page does count against the page limit.
11
V.b
For the double spacing requirement, does that apply to the whole proposal? If so, could an exception be made for the Key Personnel section and any tables/charts?

Tables, graphics, and charts do not need to be double-spaced, but must be readable. The key personnel section must be double spaced.

12
II.C.2

V.A.2

Please clarify if the Past Performance Questionnaires for Key Personnel should be delivered directly to the GSA from the References or if they should be included in the Offeror's proposal. If they are to be included in the Offeror's proposal, do they count toward the 50 page limit?
The Past Performance Questionnaires for Key Personnel and the Firm are to be sent directly from the references to the Contracting Officer at the e-mail address listed on the forms and in Section I.C of the RFQ. They should not be included in the Technical Proposal and do not count against the page limit.
13
II.C.2

V.A.2

Can the Performance Questionnaires be submitted by our clients at a later date, for instance by end of the week (of the due date) i.e., the 6thth of April?
The Past Performance Questionnaires for Key Personnel and the Firm can be submitted directly to the Contracting Officer no later than 6 April 2012.
14
II.C.2

V.A.2

Regarding the Past Performance Questionnaires that are required to be sent directly to the GSA, are they to be sent in hard copy or is a PDF via e-mail, from the Reference directly to you, an acceptable means of submission?
The Past Performance Questionnaires for Key Personnel and the Firm should be sent directly in PDF format from the references to the Contracting Officer at the e-mail address listed on the forms and in Section I.C of the RFQ.

Updated 03/26/2012