Bid/Proposal Form
View the file
Other files for this federal contract opportunity
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Galveston Post Office and Federal Courthouse Elevator Modernization Construction Cost Summary by System XX/XX/XXXX
CONVERT OLD WATER
CSI Category
Total Cost/SF Total Cost/SF Total Cost/SF
1 General Conditions (see below)
2 Sitework
3 Concrete
4 Masonry
5 Metals
6 Wood & Plastics
7 Thermal & Moisture
8 Doors & Windows
9 Finishes
10 Specialties
11 Equipment
12 Furnishings
13 Special Construction
14 Conveying
15 Mechanical
16 Electrical
17 Special Systems
Subtotal Subcontractors Cost
General Conditions
General Contractor Fee (Profit) Bond
Total Construction Cost
Prepared by Page of
Construction Cost Summary by System
Element Total
1 General Conditions (Incl. Below)
2 Sitework
3 Concrete
4 Masonry
5 Metals
6 Wood & Plastics
7 Thermal & Moisture
8 Doors & Windows
9 Finishes
10 Specialties
11 Equipment
12 Furnishings
13 Special Construction
14 Conveying
15 Mechanical
16 Electrical
17 Special Systems
Subtotal
General Conditions %
Subtotal
General Contractor Fee (Profit) %
Subtotal
Bonds & Insurance %
TOTAL ESTIMATED CONSTRUCTION COST
PROJECT SUMMARY - Galveston P.O. & Courthouse Elevator Modernization
Prepared by Page of
Detailed Construction Cost by Elements
DETAIL ELEMENTS - Galveston P.O. & Courthouse Elevator Modernization
Element Quantity Unit Unit Cost Total
2 Sitework
Total - Sitework $
3 Concrete
Total - Concrete $
4 Masonry
Total - Masonry $
5 Metals
Total - Metals $
6 Wood & Plastics
Prepared by Page of
Total - Wood & Plastics $
7 Thermal & Moisture
Total - Thermal & Moisture $
8 Doors & Windows
Total - Doors & Windows $
9 Finishes
Total - Finishes $
Detailed Construction Cost by Elements
DETAIL ELEMENTS - Galveston P.O. & Courthouse Elevator Modernization
Element Quantity Unit Unit Cost Total
Prepared by Page of
10 Specialisties
Total - Specialties $
11 Equipment
Total - Equipment $
14 Conveying
Total - Conveying $
15 Mechanical
Total - Mechanical $
16 Electrical
Total - Electrical $