About this file

This directive establishes the Goddard Space Flight Center's policy for preventing counterfeit parts and controlling counterfeit parts that may have entered the supply chain. It applies to all processes where counterfeit parts could be procured or encountered for flight hardware or safety-critical applications. The policy requires projects to establish counterfeit avoidance requirements in documentation like the Mission Assurance Requirements. It provides definitions and assigns responsibilities throughout the organization. Projects must meet the requirements for counterfeit part avoidance plans in procedural documents like 500-PG-4520.2.1 or SAE AS5553 for electrical and electronic parts. Material procurement must follow directives like 541-PG-8072.1.2. The directive also provides procedures for reporting, handling, and disposing of suspect counterfeit parts and notifying the appropriate channels.

View the file

Other files for this federal contract opportunity

Other files attached to NASA Sounding Rocket Operations Contract (NSROC) IV - FINAL Request for Proposal, eLibrary, newest first.
File Type Posted
SRPO Cryogenic Safety Users Guide Revision A Final.pdf PDF
NSROC III NNG16WA70C Attachment M - Contract Historical Data 19-20.pdf PDF
SRPO Technology Roadmap June 2021.pdf PDF
NSROC III List of Ongoing Work - October 2021.pdf PDF
SRPO Annual Report 2016.pdf PDF
Rocket_Report_4th_quarter_2019.pdf PDF
SR User Handbook Final_July 2015.pdf PDF
SRPO Annual Report 2019.pdf PDF
Doing Business with Wallops.pdf PDF
Sounding Rockets_NASA_fact_sheet.pdf PDF
NASA-STD-8719.12A Safety Standard for Explosives, Propellants, and Pyrotechnics.pdf PDF
803-GS-ESP-ES-F10-01 F-10 Explosive Site Plan.pdf PDF
803-PG-8730 1 WFF Met and Cal Lab Quality Manual.pdf PDF
GPR 8710.2.pdf PDF
NPR 8715.3.pdf PDF
NPR 4200.2.pdf PDF
GPD 7150.0.pdf PDF
GPR 1840.1.pdf PDF
GPR 8715.8.pdf PDF
GPR 8715.1.pdf PDF
GPR 8710.7.pdf PDF
GPR 7120.11.pdf PDF
200-PG-8812.1.1 Wallops Facilities Review Committee.pdf PDF
800-PG-8715.5.1A Range Safety Process for Programs and Projects.pdf PDF
GPR 8500.1.pdf PDF
NPR 1040.1 Updated.pdf PDF
NPD 8730.5.pdf PDF
GPR 1820.2.pdf PDF
GPR 1840.2.pdf PDF
GPR 1600.2.pdf PDF
GPR 8800.1.pdf PDF
GPR 8715.12.pdf PDF
GPR 4100.2.pdf PDF
NPD 8700.1 Updated.pdf PDF
800-PG-8715.0.4C_Certification Procedures for OSS at WFF.pdf PDF
NPD 2800.1.pdf PDF
NPR 6000.1.pdf PDF
NPD 2025.1.pdf PDF
800-PG-8710.0.2D Operations in Cold Weather Environments.pdf PDF
GPD 1800.0.pdf PDF
800-PG-7120.4.1 Risk Mgmt.pdf PDF
NPR 5200.1.pdf PDF
NSROC CBA IAMAW 11.01.21 final FULLY EXECUTED.pdf PDF
Rocket_Report_1st_quarter_2019.pdf PDF
Rocket Report 2nd quarter 2021.pdf PDF
Rocket_Report_3rd_quarter_2019.pdf PDF
Rocket Report 4th quarter 2020.pdf PDF
Rocket Report 1st quarter 2021.pdf PDF
SRPO Annual Report 2017.pdf PDF
Rocket Report 1st quarter 2020.pdf PDF
Show all 50

NASA Sounding Rocket Operations Contract (NSROC) IV - FINAL Request for Proposal, eLibrary has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIRECTIVE NO. GPR 4520.4A APPROVED BY Signature: Original Signed By

EFFECTIVE DATE: August 12, 2019 NAME: Eric K. Isaac

EXPIRATION DATE: August 12, 2024 TITLE: Director, Safety and Mission Assurance

CHECK THE GSFC DIRECTIVES MANAGEMENT SYSTEM AT

http://gdms.gsfc.nasa.govTO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE.

(08/16)

Goddard Procedural Requirements (GPR)

COMPLIANCE IS MANDATORY

Responsible Office: 300/Safety and Mission Assurance Directorate

Title: Counterfeit Part Avoidance Program

PREFACE

P.1 PURPOSE

This document establishes the policy at Goddard Space Flight Center (GSFC) for preventing the use of counterfeit items in mission hardware and for closed loop control of counterfeit items that may have entered the GSFC supply chain.

P.2 APPLICABILITY

a. This GPR applies to all processes within GSFC where counterfeit items may be procured or encountered for flight application in missions required to follow NPR 7120.5 or in safety-critical applications. This policy applies to hardware including Electrical, Electronic, and Electromechanical

(EEE) parts and assemblies, and mechanical parts and assemblies. The requirements herein apply to all

Directorates, Divisions, Branches, and Offices who direct the procurement of these items.

b. This GPR applies to projects governed by NPR 7120.8 or otherwise outside of NPR 7120.5 only to the extent specified in paragraph 2.7. Some Class D projects may entail a similar risk posture and hence may pursue a waiver to this GPR for permission to follow the requirements in 2.7.

c. In this directive, all document citations are assumed to be the latest version unless otherwise noted.

d. In this directive, all mandatory actions (i.e., requirements) are denoted by statements containing the term “shall.” The terms “may” or “can” denote discretionary privilege or permission; “should” denotes a good practice and is recommended but not required; “will” denotes expected outcome; and “are/is” denotes descriptive material.

P.3 AUTHORITIES

NPD 8730.2, NASA Parts Policy

P.4 APPLICABLE DOCUMENTS AND FORMS

a. NPD 9800.1, NASA Office of Inspector General Programs

b. NPR 7120.5, NASA Space Flight Program and Project Management Requirements

DIRECTIVE NO. GPR 4520.4A Page 2 of 10

EFFECTIVE DATE: August 12, 2019

EXPIRATION DATE: August 12, 2024

(08/16)

c. NPR 7120.8, NASA Research and Technology Program and Project Management Requirements

d. NPR 8705.4, Risk Classification for NASA Payloads

e. GPR 5100.1, Procurement

f. GPR 5340.3, Preparation and Handling of GIDEP Alerts, GIDEP Safe-Alerts, GIDEP Problem

Advisories, GIDEP Agency Action Notices, and NASA Advisories

g. 500-PG-4520.2.1, Electrical, Electronic and Electromechanical (EEE) Counterfeit Parts Avoidance

Plan (CPAP)

h. 541-PG-8072.1.2, Goddard Space Flight Center Fastener Integrity Requirements

i. 547-PG-8072.1.1, Manufacturing Process

j. 547-WI-8072.1.6, Bath Analysis for the Electroplating Solutions

k. 270-WI-5100.1.2, Procurement

l. SAE AS5553, Counterfeit Electronic Parts; Avoidance, Detection, Mitigation, and Disposition

P.5 CANCELLATION

GPR 4520.4-, Counterfeit Part Avoidance Program

P.6 SAFETY

None

P.7 TRAINING

At the time of writing of this directive, there is no established core training for counterfeit parts prevention that would be cost-effective to require for a large population at GSFC. Most training courses and modules available are specific to identification of counterfeits found in commercial procurements that are made outside of the requirements herein. In general, the employee’s supervisor is best suited to determine whether an individual is likely to encounter counterfeits and whether special training is needed. Those with a general possibility of encountering counterfeits in day-to-day activities should attend some of the periodic online or in-person seminars and colloquia offered to NASA employees.

P.8 RECORDS

Record Title Record Custodian Retention

Counterfeit Form Code 562 Parts, Packaging and Assembly Office

5 years after end of project*

Procurement Records Procurement Agency 5 years after end of project*

OIG Investigation Records with confirmed counterfeit items

NASA OIG NRRS: 9/23(D1):

*PERMANENT*

Transfer To NARA 10

Years After File Is Closed.

DIRECTIVE NO. GPR 4520.4A Page 3 of 10

* NRRS – NASA Records Retention Schedule (NRRS 1441.1)

P.9 MEASUREMENT/VERIFICATION

Internal and external audits verify effectiveness of this program.

PROCEDURES

1.0 Responsibilities

1.1 Center Director:

a. Ensures that GSFC projects and Directorates comply with Agency-level policies and requirements to prevent entry of counterfeit items into NASA inventories and mission hardware.

b. Ensures that GSFC projects and Directorates comply with this counterfeit items avoidance plan.

1.2 Heads of each Directorate:

a. Ensure personnel understand and follow the policies herein and adhere to the requirements that are relevant to the work of the Directorate to avoid procuring counterfeit items, to identify and prevent use of suspect counterfeit items that are received, and to properly report the receipt and disposition of suspect counterfeit items.

1.3 Program/Project Managers:

a. Establish sufficient counterfeit avoidance requirements in accordance with Section 2.0 of this document.

b. Ensure that counterfeit avoidance requirements are imposed on in-house and out-of-house procurements for all applicable items used on mission hardware and safety-critical applications.

1.4 Safety and Mission Assurance (SMA):

a. Ensures that requirements for counterfeit item avoidance for all mission hardware and safety-critical applications are imposed in the Mission Assurance Requirements (MAR) document or other project requirements documentation for purchased hardware, assemblies, and materials.

b. Periodically performs supply chain audits to ensure prime contract and subcontract suppliers of applicable hardware have counterfeit item avoidance plans that comply with the requirements herein.

c. Provides for suspect counterfeit item reporting via the GSFC Government-Industry Data Exchange

Program (GIDEP) system per GPR 5340.3.

d. Ensures that any parts or materials intended for use in mission hardware that are obtained from

GSFC supply stock or from an entity outside of GSFC meet all requirements in this GPR and have all relevant pedigree documentation, prior to integration into hardware.

http://nodis3.gsfc.nasa.gov/

DIRECTIVE NO. GPR 4520.4A Page 4 of 10

(08/16)

e. Provides counterfeit avoidance requirements to procurement personnel to include in procurement procedures and contract language to mitigate the risk of ordering counterfeit items.

f. Ensures that all applicable procured items are inspected upon receipt in accordance with counterfeit requirements. For in-house procurements, these procedures will comply with all applicable published directives and the project requirements. For out-of-house procurements, the procedures will comply with counterfeit item avoidance requirements in the project requirements documentation.

g. Establishes procedures for handling and quarantining items identified as suspect counterfeit parts.

h. Establishes procedures for reporting incidents when suspect counterfeit items are encountered to the appropriate channels, including the Office of the Inspector General (OIG), the project Chief Safety and Mission Assurance Officer (CSO), and the GIDEP Alert Coordinator.

i. Aids Code 210 in enforcing procurement contract terms and conditions for item replacement.

1.5 Engineering:

a. Coordinates with Procurement to ensure that item source selections are not in conflict with Center-established policies and project requirements that are in place to avoid procurements of counterfeit items.

b. Provides information as it becomes available to the Procurement organization about emerging considerations related to selection and procurement that reduce risk of counterfeit items acquisitions.

c. Establishes procedures for performing incoming inspection testing as needed and as applicable, where those tests cannot be performed by the procurement organization, to determine if the delivered items are suspect counterfeit.

d. Establishes procedures for notifying the OIG, Procurement, the project CSO, and the GIDEP Alert

Coordinator when suspect counterfeit items are encountered.

1.6 Employees:

a. Notify the OIG and management (project or line supervision) immediately when suspect counterfeit items are encountered.

2.0 Counterfeit Avoidance Plans

2.1 This counterfeit item avoidance plan uses the following strategies to achieve compliance with the counterfeit control requirements of NPD 8730.2, NASA Parts Policy:

a. Counterfeit control requirements are defined for EEE and finished mechanical parts.

b. Counterfeit control is established for mission hardware by the project in its MAR or other project requirements documentation.

c. Counterfeit control requirements are flowed down to prime contracts and subcontracts used to acquire mission components or systems.

d. GSFC engineering organizations provide technical expertise to Program/Project Managers to develop requirements, procedures, and plans for avoiding acquisition of, or incoming acceptance of, suspect counterfeit parts.

DIRECTIVE NO. GPR 4520.4A Page 5 of 10

(08/16)

e. Procurement organizations comply with Federal Acquisition Requirements (FAR), NASA FAR

Supplement (NFS) requirements, and counterfeit avoidance requirements for applicable item procurements.

f. Procurement organizations ensure that their incoming inspection methods facilitate detection of suspect counterfeit parts.

g. Procedures are followed that ensure proper control, storage, disposition, and reporting of counterfeit items.

h. Procedures are followed that ensure that suspect counterfeit items are brought to the attention of the OIG for disposition.

2.2 Project Parts Engineers (or engineers responsible for part procurement when no formal position on a project exists) shall ensure that no counterfeit parts are introduced to project inventories or manufactured systems that will be used in the mission (i.e., “mission hardware”).

2.3 All GSFC projects shall establish counterfeit item avoidance requirements in the Mission Assurance

Requirements (MAR) or other project requirements documentation for EEE parts and assemblies and finished mechanical parts.

2.4 EEE parts and assembly Counterfeit Prevention

a. The counterfeit parts control plan shall meet the requirements of 500-PG-4520.2.1 or SAE

AS5553. For finished mechanical parts, technical requirements for counterfeit control should be specified by the lead mechanical engineer, with input from the lead materials engineer where applicable.

b. For hardware provided by “out-of-house” suppliers where items are not procured and supplied by

GSFC, requirements shall be flowed down via contract or purchase order to the prime contractor and all sub-tier contractors.

c. For GSFC direct purchases of items for use in manufacturing of applicable hardware internally

(i.e., “in-house”) or for supply to external manufacturers (i.e., government furnished material), applicable PG documents are listed in Appendix C of this document.

2.5 Material Counterfeit Prevention

a. The project engineer responsible for material procurement and usage shall ensure that the acquisition, traceability, receiving inspection, and test requirements for fasteners is per 541-PG-

8072.1.2, Goddard Space Flight Center Fastener Integrity Requirements.

b. The project engineer responsible for material procurement and usage shall ensure that the material certification is documented in accordance with a configuration-controlled plan approved at the division level or project level. Approved directives, such as 541-PG-7120.2.1, Materials &

Processes Engineering Support Guidelines for Goddard Space Flight Center Projects are sufficient to meet the requirements for this plan.

c. The project lead mechanical engineer shall ensure that fabricated parts are dimensionally inspected, including material chemical/physical test reports, in accordance with a configuration-controlled plan approved at the division level or project level. Approved directives, such as 547-PG-8072.1.1, Manufacturing Process, or equivalent are sufficient to meet the requirements for this plan.

DIRECTIVE NO. GPR 4520.4A Page 6 of 10

(08/16)

d. Projects and Divisions, as applicable, shall ensure the integrity of electroplating solutions for in-house applications in accordance with a configuration-controlled plan approved at the division level or project level. Approved directives, such as 547-WI-8072.1.6, Bath Analysis for the

Electroplating Solutions are sufficient to meet the requirements for this plan.

2.6 For counterfeit concerns related to items not covered by this GPR, counterfeit avoidance control requirements shall be established by the program/project as needed to mitigate the risk of procurement and use of counterfeit items in mission hardware, critical ground support equipment, and safety-critical applications, as well as to ensure counterfeits are adequately reported, handled, and dispositioned.

2.7 Projects not governed by NPR 7120.5 shall:

a. Notify the NASA OIG within 48 hours upon the suspicion or discovery of a counterfeit item, and turn over the item(s) to OIG.

b. Store all pedigree documentation for unused parts and materials and provide to future users at

GSFC or to accompany the items if transferred outside of GSFC.

DIRECTIVE NO. GPR 4520.4A Page 7 of 10

Appendix A – Definitions

A.1 Counterfeit Part — A copy or substitute part without legal right or authority to represent itself as declared; or a part whose material, performance, or characteristics are knowingly misrepresented by a supplier at any level in the supply chain. Examples of counterfeit parts may include, but are not limited to: Parts which do not contain the proper internal construction and materials (die, manufacturer, wire bonding, etc.) consistent with the procured part.

a. Part that exhibits appearance of being used, refurbished or reclaimed, but presented as new product.

b. Part that has a different package style or surface plating/finish than the ordered part.

c. Part that has not successfully completed the OEM’s full production and test flow, but is represented as completed product.

d. Part sold as a re-screened part, to a higher quality level than identified, that has not successfully completed re-screening.

e. Part sold with modified part number identification intended to misrepresent the part’s form, fit, function, grade or manufacturing date.

f. Part sold as compliant to a procurement specification, marked as required by the procurement specification but does not satisfy the parametric or quality requirements of the specification.

A.2 EEE Parts – Items such as capacitors, circuit breakers, connectors, crystals and crystal oscillators, diodes, fiber optics accessories, fiber optics cables, fiber optics conductors, fiber optics devices, fiber optics interconnects, filters, fuses, inductors, hybrids/multi-chip modules, microcircuits, relays, resistors, switches, thermistors, transformers, transistors, and wire/cable.

A.3 Finished Mechanical Parts – Items such as fasteners, bearings, studs, pins, rings, shims, piping components, valves, springs, brackets, clamps and spacers.

A.4 Government-Industry Data Exchange Program (GIDEP) – A cooperative program that collects and distributes Alerts, Safe Alerts, Problem Advisories, and Agency Action Notices to participating organizations.

A.5 Suspect Counterfeit Part — is a part in which there is an indication by visual inspection, testing, or other information that it may be misrepresented by the supplier or manufacturer or may not conform to legal, established government or industry-accepted specifications, or national consensus standards; or a part’s documentation.

DIRECTIVE NO. GPR 4520.4A Page 8 of 10

Appendix B – Acronyms

CSO Chief Safety and Mission Assurance Officer

CPAP Counterfeit Parts Avoidance Plan

EEE Electrical, Electronic, and Electromechanical

FAR Federal Acquisition Requirements

GIDEP Government-Industry Data Exchange Program

GPR Goddard Procedural Requirements

GSFC Goddard Space Flight Center

GSE Ground Support Equipment

MAR Mission Assurance Requirements

NPD NASA Policy Directive

NPR NASA Procedural Requirements

NRRS NASA Records Retention Schedule

NFS NASA FAR Supplement

OCM Original Component Manufacturer

OIG Office of the Inspector General

PG Procedural Guidelines

SMA Safety and Mission Assurance

DIRECTIVE NO. GPR 4520.4A Page 9 of 10

Appendix C – GSFC Counterfeit Control Program

The following documents are listed in this Appendix to establish traceability of the GSFC Counterfeit

Control program.

GPR 5100.1 Procurement

GPR 5340.3 Preparation and Handling of GIDEP Alerts, GIDEP Safe-Alerts, GIDEP

Problem Advisories, GIDEP Agency Action Notices, and NASA Advisories

500-PG-4520.2.1 EEE CPAP

541-PG-8072.1.2 Goddard Space Flight Center Fastener Integrity Requirements

547-PG-8072.1.1 Manufacturing Process

270-WI-5100.1.2 Procurement

DIRECTIVE NO. GPR 4520.4A Page 10 of 10

CHANGE HISTORY LOG

Revision Effective Date Description of Changes

Baseline 09/25/14 Initial Release

A 08/12/19

Removed references to Ground Support Equipment (GSE).