FA8903-12-R-0031
Attachment 2
FA8903-12-R-0050
Attachment L-6
Contract Line Item Number (CLIN) Structures/
Milestone Payment Schedules (MPS)/Integrated Master Schedules (IMS) Guidance This guidance is being provided to communicate Air Force expectations for the development of CLIN/Sub-CLIN Structures and the correlation with the subsequent development of the MPS and the IMS. This guidance is not intended to remove Contractor flexibility. The examples provided are for illustration purposes only and are not intended to be inclusive of all acceptable approaches.
When annual Congressional appropriations provide the basis for sourcing these contracts, special consideration must be given to ensure compliance with funding rules concerning period of availability, bona fide need and purpose as they relate to each year of funding applied. This will ensure milestones are developed that support fiscally responsible use of funds. To ensure compliance when establishing milestones, any contingent events that affect the beginning date of any milestone must be considered. Key to proper use of funds in this context is non-severability. A non-severable deliverable is defined as a deliverable item that represents a single end product or undertaking, entire in its nature, that cannot be feasibly subdivided into discrete elements or phases without losing its identity. Milestones must have a clear delineation of final deliverables, as distinct non-severable options to be fully funded in the fiscal year in which the award of the Sub-CLIN is made, even though the performance may extend into future fiscal years. There is no administrative reservation of funds whatsoever until a determination is made to exercise a separate and non-severable Sub-CLIN. Each non-severable Sub-CLIN will be funded in its entirety with funds current at the time the Sub-CLIN is exercised, and any need for prior year funds in the future will be clearly tied back to the specific non-severable Sub-CLIN and associated well defined requirement(s) and associated deliverable(s).
CLIN AND SUB-CLIN STRUCTURE:
CLINs are identified in the WERC09 contract. Sub-CLINs provide a means for funding economically or programmatically viable stages by identifying the items or activities to be acquired as non-severable contract deliverables (performance objectives). The performance period for the Sub-CLIN may be for more than one, but not more than five fiscal years. Sub-CLINs shall provide a firm fixed price for separately identifiable contract deliverables (performance objectives). Each Sub-CLIN shall have its own performance objective expressly stated. Sub-CLINs should identify remediation objectives or activities that relate directly to, and are an integral part of, the CLIN. For example:
· Achieve [performance objective] for [site number(s)]
Sub-CLIN prices and completion dates must not exceed the value or completion date of the CLIN. Sub-CLINs cannot be partially exercised and must be fully funded when exercised in order to avoid violations of the Anti-Deficiency Act. The use of Sub-CLINs provides the Air Force with the flexibility to match options to be exercised with available funding as the amount of available program funding is sometimes unpredictable. The Air Force may restructure the Sub-CLINs with the Apparent Successful Offeror based upon the submitted MPS.
Sub-CLINs shall consist of numeric digits and alpha characters. Once a Sub-CLIN number has been assigned, it shall not be assigned to another Sub-CLIN in the same task order. Under the WERC09 contract the numeric digits for the CLIN on Performance-Based Remediation (PBR) task orders shall be 0009. Only 24 alpha characters shall be used in the second position before selecting a different alpha character for the first position. Alpha characters I and O should be avoided due to the potential for confusion with numeric digits 1 or 0. The Sub-CLINs must use AA, AB, AC, through AZ before beginning BA, BB, and BC. For example, if the CLIN number is 0009, the first three Sub-CLIN items would be 0009AA, 0009AB, and 0009AC.
MILESTONE PAYMENT SCHEDULE:
The Contractor shall propose milestone payments as part of the MPS in its proposal. The Air Force intends to use the Contractor’s proposed MPS to restructure Sub-CLINs, if necessary, to align with projected available funding prior to award. The MPS shall also be included as part of the Project Management Plan (PMP). The MPS is not included in the task order and is not considered final with award of the task order. Changes made to the MPS prior to award are used to finalize the Sub-CLINs, therefore, award of the task order does not equate to final acceptance of the MPS. The MPS will be negotiated during development of the PMP and may require additional changes.
Milestone payments shall be based on the completion of a definable and measurable step considered integral and necessary to the achievement of the performance objective/Sub-CLIN. Completion of milestones shall demonstrate payment is appropriate. Milestone payments shall include the approval requirements in accordance with the performance standards in Table 1 of the Statement of Objectives (SOO) and the requirements of the regulatory structure. Terms of acceptance of milestone payments will be negotiated during development of the PMP.
A consolidation of completed milestone payments is to be submitted monthly, however milestone payments shall not represent a “progress” payment or a “monthly” payment for level of effort expended. In addition, milestone payments shall not include management or overhead type costs (program/project management, monthly reporting, mobilization/demobilization, etc.) that do not provide measurable project advancement. For any performance objective, a milestone payment shall be for completion of a definable and measurable point considered integral and necessary to completion of the performance objective. For example, if the performance objective is to achieve Remedy-in-Place (RIP) and the work required to achieve RIP includes Feasibility Study (FS), Proposed Plan (PP), Record of Decision (ROD), Remedial Design (RD), and Remedial Action (RA), then potential interim milestone payments could be:
· Air Force approval of Draft FS;
· Air Force and Regulator approval of Final FS;
· Air Force approval of Draft PP;
· Air Force and Regulator approval of Final PP;
· Air Force approval of Draft ROD;
· Air Force and Regulator approval of Final ROD;
· Air Force approval of Draft Remedial Action Work Plan (RAWP)/RD;
· Air Force and Regulator approval of Final RAWP/RD;
· Air Force approval of Remedial Action Completion Report (RACR);
· Air Force and Regulator approval of Final RACR signifying achievement of RIP.
Contractor proposed milestone payments for Air Force approval of draft documents require sufficient funds to remain associated with the final document to ensure completion of the performance objective. Milestone payments shall not exceed 80% of the total payment for that Sub-CLIN prior to achievement of the final deliverable (performance objective). The Sub-CLIN’s final deliverable may include the combination of the draft and final versions. The final Sub-CLIN milestone for each site must be a minimum of 20% of the total Sub-CLIN cost. Air Force acceptance of Contractor proposed draft milestones, or the proposed percentage of the milestone payment as compared to the total payment for that Sub-CLIN, is discretionary and negotiated on a case-by-case basis between the Air Force and selected Offeror. These negotiations may occur prior to award and/or during development of the PMP.
The Air Force will use performance indicators and performance models in addition to the PMP to establish and execute a Surveillance Plan. The Surveillance Plan will highlight key quality control activities or events. The Contracting Officer’s Representative (COR) will use the Surveillance Plan to determine when Air Force (COR and/or Contracting Officer (CO)) surveillance activities can be conducted to assess progress toward and/or completion of milestone payments.
INTEGRATED MASTER SCHEDULE:
The Contractor shall prepare and submit an activity-based IMS that is consistent with the MPS. The Contractor must include and identify all performance milestones at the appropriate level of detail and logically sequenced to support and manage achievement of the proposed performance objectives. The IMS shall identify completion of the performance objectives in the time designated and shall include identification of any critical path items. The IMS shall include incorporation of Air Force and Regulatory review periods for deliverables while meeting or exceeding any applicable agreements or regulatory schedule requirements.
Sites associated with each milestone/task must be noted in the schedules using the Site IDs and referencing all site aliases noted in Table 1 of the SOO. The schedule shall be provided in hardcopy and electronic format consistent/compatible with Air Force software, currently Microsoft( Project, Microsoft( Excel, and in Adobe Acrobat portable document file (.pdf). Updated and revised schedules shall be submitted with monthly status reports with changes clearly identified by the Contractor.
An example illustrating the progression of CLIN/Sub-CLIN Structure to MPS and IMS follows:
EXAMPLE CLIN/SUB-CLIN STRUCTURE
(Air Force approval required prior to Task Order Award)
| CLIN/SUB-CLIN |
| CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/SUB-CLIN AMOUNT |
| PROJECTED EXERCISE DATE OR RATIONALE |
| 0009 |
| ENVIRONMENTAL REMEDIATION FFP (in accordance with the SOO) |
| $0 |
| 0009AA |
| Preliminary Project Management Plan (PMP) |
| $25,000 |
| At Award |
| 0009AB |
| Final Project Management Plan (PMP) |
| $25,000 |
| Approx 4.5 years from 0009AA or upon CO determination of bona fide need |
| 0009AC |
| CG025 Management Unit: Achieve RIP |
| $200,000 |
| At Award |
| Total |
| $250,000 |
EXAMPLE MILESTONE PAYMENT SCHEDULE
(Negotiated between the Air Force and the selected Offeror and approved by the Air Force)
| CLIN/SUB-CLIN |
| CLIN/SUB-CLIN/MILESTONE PAYMENT DESCRIPTION |
| CLIN/SUB-CLIN AMOUNT |
| MILESTONE PAYMENT AMOUNT |
| MILESTONE PERCENT |
| 0009 |
| ENVIRONMENTAL REMEDIATION FFP (in accordance with the SOO) |
| $0 |
| 0009AA |
| Preliminary Project Management Plan (PMP) |
| $25,000 |
| $25,000 |
| 0009AB |
| Final Project Management Plan (PMP) |
| $25,000 |
| $25,000 |
| 0009AC |
| CG025 Management Unit: Achieve RC |
| $200,000 |
Air Force Approval of Draft FS
| $30,000 |
| 15% |
Air Force and Regulatory Approval of Final FS
| $20,000 |
| 25% |
Air Force Approval of Draft ROD
| $6,000 |
| 28% |
Air Force and Regulatory Approval of Final ROD
| $4,000 |
| 30% |
Air Force Approval of Draft Remedial Action Work Plan/Remedial Design
| $62,000 |
| 61% |
Air Force and Regulatory Approval of Final Remedial Action Work Plan/Remedial Design
| $38,000 |
| 80% |
Air Force Approval of Draft RACR
| $30,000 |
| 95% |
Air Force and Regulatory Approval of Final RACR signifying achievement of RIP
| $10,000 |
| 100% |
| Total |
| $250,000 |
| $250,000 |
Note: Payment milestone ranges could be as low as 60%; but shall not exceed 80% of the total payment for the CLIN/Sub-CLIN prior to achievement of the final deliverable. In the example above, 80% of $200,000 = $160,000; therefore, RACR (draft + final) = $40,000 or 20% of the Sub-CLIN 0009AC. Air Force approval of the "Draft" is defined as Contractor resolution of Air Force comments on the Draft deliverable.
EXAMPLE Integrated Master Schedule (Air Force approval required as part of the PMP)
| Activity ID# |
| ACTIVITY DESCRIPTION |
| DURATION |
| START |
| FINISH |
| 0009 |
| Task Order Award |
| 1 day |
| 1 OCT 10 |
| 1 OCT 10 |
| 0009AA0001 |
| Kick Off Meeting |
| 1 day |
| 15 OCT 10 |
| 15 OCT 10 |
| 0009AA0002 |
| Prepare Preliminary PMP |
| 30 days |
| 1 OCT 10 |
| 31 OCT 10 |
| 0009AA0003QA |
| Air Force Review of Draft Preliminary PMP |
| 30 days |
| 1 NOV 10 |
| 1 DEC 10 |
| 0009AA0004PM |
| Air Force Approval of Final Preliminary PMP |
| 1 day |
| 1 DEC 10 |
| 1 DEC 10 |
Note: Air Force surveillance activities precede all milestone payments.
CLIN
SUB-CLIN
CLIN/SUB-CLIN DESCRIPTION
**PROJECTED DATE OF EXERCISE
CLIN/SUB-CLIN AMOUNT
Project Management Plan (PMP)
$0
0001AA
Preliminary Project Management Plan in accordance with Table 1 of the SOO
At Award
0001AB
Final Project Management Plan in accordance with Table 1 of the SOO
Approx 4.5 years from 0001AA or upon CO determination of bona fide need
JB Charleston - Air
LF002 - SWMU 69, LANDFILL NO 4
0002AA
LF002 - SWMU 69, Landfill No. 4: Achieve RIP within 4 years of NTP.
At Award
0002AB
LF002 - SWMU 69, Landfill No. 4: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0002AA or upon CO determination of bona fide need
0002AC
LF002 - SWMU 69, Landfill No. 4: Implement the elements of the approved optimized exit strategy in an Implementation Completion Report that fall within the POP.
Approx. 2 years from 0002AB or upon CO determination of bona fide need
0002AD
LF002 - SWMU 69, Landfill No. 4: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0002AC or upon CO determination of bona fide need
FT003 - SWMU 55, FIRE PROTECTION TRAINING AREA 3
0003AA
FT003 - SWMU 55, Fire Protection Training Area 3: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0003AB
FT003 - SWMU 55, Fire Protection Training Area 3: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0003AA or upon CO determination of bona fide need
0003AC
FT003 - SWMU 55, Fire Protection Training Area 3: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0003AB or upon CO determination of bona fide need
0003AD
FT003 - SWMU 55, Fire Protection Training Area 3: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0003AC or upon CO determination of bona fide need
LF004 - SWMU 66, LANDFILL NO 1
0004AA
LF004 - SWMU 66, Landfill No. 1: Achieve RIP within 4 years of NTP.
At Award
0004AB
LF004 - SWMU 66, Landfill No. 1: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0004AA or upon CO determination of bona fide need
0004AC
LF004 - SWMU 66, Landfill No. 1: Implement the elements of the approved optimized exit strategy in an Implementation Completion Report that fall within the POP.
Approx. 2 years from 0004AB or upon CO determination of bona fide need
0004AD
LF004 - SWMU 66, Landfill No. 1: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0004AC or upon CO determination of bona fide need
LF006 - SMWU 68, LANDFILL NO 3
0005AA
LF006 - SWMU 68, Landfill No. 3: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0005AB
LF006 - SWMU 68, Landfill No. 3: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0005AA or upon CO determination of bona fide need
0005AC
LF006 - SWMU 68, Landfill No. 3: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0005AB or upon CO determination of bona fide need
0005AD
LF006 - SWMU 68, Landfill No. 3: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0005AC or upon CO determination of bona fide need
LF017 - SWMU 67, LANDFILL NO 2
0006AA
LF017 - SWMU 67, Landfill No. 2: Achieve Decision Document (DD)
At Award
0006AB
LF017 - SWMU 67, Landfill No. 2: Achieve RIP within 8 years of NTP of Sub-CLIN 0006AA.
Upon Completion of 0006AA or upon CO determination of bona fide need
0006AC
LF017 - SWMU 67, Landfill No. 2: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0006AB or upon CO determination of bona fide need
0006AD
LF017 - SWMU 67, Landfill No. 2: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0006AC or upon CO determination of bona fide need
OT011 - SWMU 60, HARDFILL AREA 3
0007AA
OT011 - SWMU 60, Hardfill Area 3: Achieve RIP within 4 years of NTP.
At Award
0007AB
OT011 - SWMU 60, Hardfill Area 3: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Preliminary OES Implementation Completion Report that fall within the POP.
Upon Completion of 0007AA or upon CO determination of bona fide need
0007AC
OT011 - SWMU 60, Hardfill Area 3: Implement the elements of the approved optimized exit strategy in an Implementation Completion Report that fall within the POP.
Approx. 2 years from 0007AB or upon CO determination of bona fide need
0007AD
OT011 - SWMU 60, Hardfill Area 3: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0007AC or upon CO determination of bona fide need
OT012 - SWMU 58, HARDFILL AREA 1
0008AA
OT012 - SWMU 58, Hardfill Area 1: Achieve RIP within 4 years of NTP.
At Award
0008AB
OT012 - SWMU 58, Hardfill Area 1: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Preliminary OES Implementation Completion Report that fall within the POP.
Upon Completion of 0008AA or upon CO determination of bona fide need
0008AC
OT012 - SWMU 58, Hardfill Area 1: Implement the elements of the approved optimized exit strategy in an Implementation Completion Report that fall within the POP.
Approx. 2 years from 0008AB or upon CO determination of bona fide need
0008AD
OT012 - SWMU 58, Hardfill Area 1: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0008AC or upon CO determination of bona fide need
ST013 - AOC I, BASE GASOLINE STATION LEAK
0009AA
ST013 - AOC I, Base Gasoline Station Leak: Mobilize and develop an optimized exit strategy to achieve SC per Table 1 of the SOO and implement the elements of the approved strategy that fall within the POP.
At Award
0009AB
ST013 - AOC I, Base Gasoline Station Leak: Achieve SC within 7 years of NTP of Sub-CLIN 0009AA.
Upon Completion of 0009AA or upon CO determination of bona fide need
OT016 - ENTOMOLOGY SHOP (PRESENT) (Represents ZONE 2)
0010AA
OT016 - Entomology Shop (Present): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0010AB
OT016 - Entomology Shop (Present): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0010AA or upon CO determination of bona fide need
0010AC
OT016 - Entomology Shop (Present): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0010AB or upon CO determination of bona fide need
0010AD
OT016 - Entomology Shop (Present): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0010AC or upon CO determination of bona fide need
ST027 - SWMU 145, BUILDING 575 JP-4 TANK LEAK
0011AA
ST027 - SWMU 145, Building 575 JP-4 Tank Leak: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0011AB
ST027 - SWMU 145, Building 575 JP-4 Tank Leak: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0011AA or upon CO determination of bona fide need
0011AC
ST027 - SWMU 145, Building 575 JP-4 Tank Leak: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0011AB or upon CO determination of bona fide need
0011AD
ST027 - SWMU 145, Building 575 JP-4 Tank Leak: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0011AC or upon CO determination of bona fide need
SS041 - SWMU 146, FUEL HYDRANT SYSTEM LEAK
0012AA
SS041 - SWMU 146, Fuel Hydrant System Leak (SWMU 146): Properly Abandon bioventing system and monitoring wells within 2 years of NTP
2Q FY14
SS043 - AOC R, TAXIWAY E JP-4 PIPELINE LEAK
0013AA
SS043 - AOC R, Taxiway E JP-4 Pipeline Leak: Mobilize and develop an optimized exit strategy to achieve SC per Table 1 of the SOO and implement the elements of the approved strategy that fall within the POP.
2Q FY14
0013AB
SS043 - AOC R, Taxiway E JP-4 Pipeline Leak: Achieve SC within 7 years from NTP of Sub-CLIN 0013AA.
Upon Completion of 0013AA or upon CO determination of bona fide need
TU047 - SWMU 127, BUILDING 1595
0014AA
TU047 - SWMU 127, Bldg 1595: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0014AB
TU047 - SWMU 127, Bldg 1595: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0014AA or upon CO determination of bona fide need
0014AC
TU047 - SWMU 127, Bldg 1595: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0014AB or upon CO determination of bona fide need
0014AD
TU047 - SWMU 127, Bldg 1595: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0014AC or upon CO determination of bona fide need
TU048 - BUILDING 401
0015AA
TU048 - Bldg 401: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0015AB
TU048 - Bldg 401: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0015AA or upon CO determination of bona fide need
0015AC
TU048 - Bldg 401: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0015AB or upon CO determination of bona fide need
0015AD
TU048 - Bldg 401: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0015AC or upon CO determination of bona fide need
SA501 - SWMU 28, AH-1 WASTE ACCUMULATION AREA
0016AA
SA501 - SWMU 28, AH-1 Waste Accumulation Area: Achieve RCRA Facility Investigation (RFI)
At Award
0016AB
SA501 - SWMU 28, AH-1 Waste Accumulation Area: Achieve RIP within 8 years of NTP from Sub-CLIN 0016AA.
Upon Completion of 0016AA or upon CO determination of bona fide need
0016AC
SA501 - SWMU 28, AH-1 Waste Accumulation Area: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0016AB or upon CO determination of bona fide need
0016AD
SA501 - SWMU 28, AH-1 Waste Accumulation Area: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0016AC or upon CO determination of bona fide need
OW507 - SWMU 82, B-210 OIL/WATER SEPERATOR (OWS)
0017AA
OW507 - SWMU 82, B-210 OWS: Achieve RCRA Facility Investigation (RFI)
At Award
0017AB
OW507 - SWMU 82, B-210 OWS: Achieve RIP within 8 years of NTP from Sub-CLIN 0017AA.
Upon Completion of 0017AA or upon CO determination of bona fide need
0017AC
OW507 - SWMU 82, B-210 OWS: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0017AB or upon CO determination of bona fide need
0017AD
OW507 - SWMU 82, B-210 OWS: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0017AC or upon CO determination of bona fide need
OW508 - SWMU 83, B-239 OWS
0018AA
OW508 - SWMU 83, B-239 OWS:Achieve RCRA Facility Investigation (RFI)
At Award
0018AB
OW508 - SWMU 83, B-239 OWS: Achieve RIP within 8 years of NTP from Sub-CLIN 0018AA.
Upon Completion of 0018AA or upon CO determination of bona fide need
0018AC
OW508 - SWMU 83, B-239 OWS: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0018AB or upon CO determination of bona fide need
0018AD
OW508 - SWMU 83, B-239 OWS: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0018AC or upon CO determination of bona fide need
OW509 - SWMU 84, B-370 OWS
0019AA
OW509 - SWMU 84, B-370 OWS: Achieve RCRA Facility Investigation (RFI)
At Award
0019AB
OW509 - SWMU 84, B-370 OWS: Achieve SC within 7 years of NTP from Sub-CLIN 019AA.
Upon Completion of 0019AA or upon CO determination of bona fide need
TU522 - SWMU 101, B-210 SAND TRAP
0020AA
TU522 - SWMU 101, B-210 Sand Trap: Achieve RCRA Facility Investigation (RFI)
At Award
0020AB
TU522 - SWMU 101, B-210 Sand Trap: Achieve RIP within 8 years of NTP from Sub-CLIN 0020AA.
Upon Completion of 0020AA or upon CO determination of bona fide need
0020AC
TU522 - SWMU 101, B-210 Sand Trap: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0020AB or upon CO determination of bona fide need
0020AD
TU522 - SWMU 101, B-210 Sand Trap: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0020AC or upon CO determination of bona fide need
TU527 - SWMU 109, B-239 HOLDING TANK (1)
0021AA
TU527 - SWMU 109, B-239 Holding Tank (1): Achieve RCRA Facility Investigation (RFI)
At Award
0021AB
TU527 - SWMU 109, B-239 Holding Tank (1): Achieve RIP within 8 years of NTP from Sub-CLIN 021AA.
Upon Completion of 0021AA or upon CO determination of bona fide need
0021AC
TU527 - SWMU 109, B-239 Holding Tank (1): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0021AB or upon CO determination of bona fide need
0021AD
TU527 - SWMU 109, B-239 Holding Tank (1): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0021AC or upon CO determination of bona fide need
TU528 - SWMU 110, B-239 HOLDING TANK (2)
0022AA
TU528 - SWMU 110, B-239 Holding Tank (2): Achieve RCRA Facility Investigation (RFI)
At Award
0022AB
TU528 - SWMU 110, B-239 Holding Tank (2): Achieve RIP within 8 years of NTP from Sub-CLIN 022AA.
Upon Completion of 0022AA or upon CO determination of bona fide need
0022AC
TU528 - SWMU 110, B-239 Holding Tank (2): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0022AB or upon CO determination of bona fide need
0022AD
TU528 - SWMU 110, B-239 Holding Tank (2): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0022AC or upon CO determination of bona fide need
RW532 - SWMU 118, B-371 WASH RACK
0023AA
RW532 - SWMU 118, B-371 Wash Rack: Achieve RCRA Facility Investigation (RFI)
At Award
0023AB
RW532 - SWMU 118, B-371 Wash Rack: Achieve RIP within 8 years of NTP from Sub-CLIN 0023AA.
Upon Completion of 0023AA or upon CO determination of bona fide need
0023AC
RW532 - SWMU 118, B-371 Wash Rack: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0023AB or upon CO determination of bona fide need
0023AD
RW532 - SWMU 118, B-371 Wash Rack: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0023AC or upon CO determination of bona fide need
TU538 - SWMU 147, B-672 UST
0024AA
TU538 - SWMU 147, B-672 UST: Achieve RCRA Facility Investigation (RFI)
At Award
0024AB
TU538 - SWMU 147, B-672 UST: Achieve RIP within 8 years of NTP from Sub-CLIN 024AA.
Upon Completion of 0024AA or upon CO determination of bona fide need
0023AC
TU538 - SWMU 147, B-672 UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0024AB or upon CO determination of bona fide need
0023AD
TU538 - SWMU 147, B-672 UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0024AC or upon CO determination of bona fide need
DD540 - AOC P, FLIGHTLINE DRAINAGE DITCH
0025AA
DD540 - AOC P, Flightline Drainage Ditch: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0025AB
DD540 - AOC P, Flightline Drainage Ditch: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0025AA or upon CO determination of bona fide need
0025AC
DD540 - AOC P, Flightline Drainage Ditch: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0025AB or upon CO determination of bona fide need
0025AD
DD540 - AOC P, Flightline Drainage Ditch: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0025AC or upon CO determination of bona fide need
TU542 - AOC V, SHOPETTE UST AND DISTRIBUTION LINES
0026AA
TU542 - Shopette UST and Distribution Lines (AOC V): Properly Abandon bioventing system and monitoring wells within 2 years of NTP
At Award
0026AB
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 1)
2Q FY14
0026AC
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 2)
Approx. 1 year from 0026AB or upon CO determination of bona fide need
0026AD
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 3)
Approx. 1 year from 0026AC or upon CO determination of bona fide need
0026AE
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 4)
Approx. 1 year from 0026AD or upon CO determination of bona fide need
0026AF
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 5)
Approx. 1 year from 0026AE or upon CO determination of bona fide need
0026AG
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 6)
Approx. 1 year from 0026AF or upon CO determination of bona fide need
0026AH
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 7)
Approx. 1 year from 0026AG or upon CO determination of bona fide need
0026AJ
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 8)
Approx. 1 year from 0026AH or upon CO determination of bona fide need
0026AK
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 9)
Approx. 1 year from 0026AJ or upon CO determination of bona fide need
0026AL
TU542 - AOC V, Shopette UST and Distribution Lines: Perform Remedial Action – Operations (RA-O) (Year 10)
Approx. 1 year from 0026AK or upon CO determination of bona fide need
TU543 - SWMU 108, B-58 UST
0027AA
TU543 - SWMU 108, B-58 UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0027AB
TU543 - SWMU 108, B-58 UST: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0027AA or upon CO determination of bona fide need
0027AC
TU543 - SWMU 108, B-58 UST: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0027AB or upon CO determination of bona fide need
0027AD
TU543 - SWMU 108, B-58 UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0027AC or upon CO determination of bona fide need
TU544 - AOC T, B-129 UST
0028AA
TU544 - AOC T, B-129 UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0028AB
TU544 - AOC T, B-129 UST: Implement the elements of the approved optimized exit strategy in an Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0028AA or upon CO determination of bona fide need
0028AC
TU544 - AOC T, B-129 UST: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0028AB or upon CO determination of bona fide need
0028AD
TU544 - AOC T, B-129 UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0028AC or upon CO determination of bona fide need
TU545 - AOC U, B-1800 UST
0029AA
TU545 - AOC U, B-1800 UST: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
2Q FY14
0029AB
TU545 - AOC U, B-1800 UST: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0029AA or upon CO determination of bona fide need
0029AC
TU545 - AOC U, B-1800 UST: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0029AB or upon CO determination of bona fide need
0029AD
TU545 - AOC U, B-1800 UST: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0029AC or upon CO determination of bona fide need
TS836 - AOC W, SKEET RANGE 1
0030AA
TS836 - AOC W, Skeet Range 1: Achieve RI within 2 years of NTP.
At Award
TS837 - AOC X, SKEET RANGE 2
0031AA
TS837 - AOC X, Skeet Range 2: Achieve RI within 2 years of NTP.
At Award
TS838 - AOC Y, SUSPECTED SKEET RANGE
0032AA
TS838- AOC Y, Suspected Skeet Range 2: Achieve RI within 2 years of NTP.
At Award
ZZ049 - WATER TOWER 1
0033AA
ZZ049 - Water Tower 1: Achieve RCRA Facility Assessment Report (RFA) within 2 years from NTP
3Q FY15
ZZ050 - WATER TOWER 2
0034AA
ZZ050 - Water Tower 2: Achieve RCRA RFA within 2 years from NTP
3Q FY15
ZZ051 - WATER TOWER 3
0035AA
ZZ051 - Water Tower 3: Achieve RCRA RFA within 2 years from NTP
3Q FY15
RW052 - SWMU 123, BUILDING 548 WASH RACK
0036AA
RW052 - SWMU 123, Bldg 548 Wash Rack: Achieve RIP within 8 years of NTP.
3Q FY15
0036AB
RW052 - SWMU 123, Bldg 548 Wash Rack: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
Upon Completion of 0036AA or upon CO determination of bona fide need
0036AC
RW052 - SWMU 123, Bldg 548 Wash Rack: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 1 year from 0036AB or upon CO determination of bona fide need
Seymour Johnson AFB
LF006 - LANDFILL NO. 4 (LF-6)
0037AA
LF006 - Landfill No. 4 (LF-6): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY15
0037AB
LF006 - Landfill No. 4 (LF-6): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0037AA or upon CO determination of bona fide need
0037AC
LF006 - Landfill No. 4 (LF-6): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0037AB or upon CO determination of bona fide need
0037AD
LF006 - Landfill No. 4 (LF-6): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0037AC or upon CO determination of bona fide need
FT007 - FIRE TRAINING AREA #3
0038AA
FT007 - Fire Training Area #3: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY15
0038AB
FT007 - Fire Training Area #3: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0038AA or upon CO determination of bona fide need
0038AC
FT007 - Fire Training Area #3: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0038AB or upon CO determination of bona fide need
0038AD
FT007 - Fire Training Area #3: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0038AC or upon CO determination of bona fide need
LF008 - LANDFILL NO. 1 (LF-8)
0039AA
LF008 - Landfill No. 1 (LF-8): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY15
0039AB
LF008 - Landfill No. 1 (LF-8): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0039AA or upon CO determination of bona fide need
0039AC
LF008 - Landfill No. 1 (LF-8): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0039AB or upon CO determination of bona fide need
0039AD
LF008 - Landfill No. 1 (LF-8): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0039AC or upon CO determination of bona fide need
SS009 - DPDO HAZARDOUS WASTE (SS-09)
0040AA
SS009 - DPDO Hazardous Waste (SS-09): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
At Award
0040AB
SS009 - DPDO Hazardous Waste (SS-09): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0040AA or upon CO determination of bona fide need
0040AC
SS009 - DPDO Hazardous Waste (SS-09): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0040AB or upon CO determination of bona fide need
0040AD
SS009 - DPDO Hazardous Waste (SS-09): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0040AC or upon CO determination of bona fide need
LF015 - LANDFILL NO. 2 (LF-15)
0041AA
LF015 - Landfill No. 2 (LF-15): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY15
0041AB
LF015 - Landfill No. 2 (LF-15): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0041AA or upon CO determination of bona fide need
0041AC
LF015 - Landfill No. 2 (LF-15): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0041AB or upon CO determination of bona fide need
0041AD
LF015 - Landfill No. 2 (LF-15): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0041AC or upon CO determination of bona fide need
LF016 - LANDFILL NO. 3 (LF-16)
0042AA
LF016 - Landfill No. 3 (LF-16): Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY15
0042AB
LF016 - Landfill No. 3 (LF-16): Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0042AA or upon CO determination of bona fide need
0042AC
LF016 - Landfill No. 3 (LF-16): Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0042AB or upon CO determination of bona fide need
0042AD
LF016 - Landfill No. 3 (LF-16): Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0042AC or upon CO determination of bona fide need
OT021 - OLD ENTOMOLOGY SHOP
0043AA
OT021 - Old Entomology Shop: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY17
0043AB
OT021 - Old Entomology Shop: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0043AA or upon CO determination of bona fide need
0043AC
OT021 - Old Entomology Shop: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0043AB or upon CO determination of bona fide need
0043AD
OT021 - Old Entomology Shop: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0043AC or upon CO determination of bona fide need
OT029 - RADAR TOWER SITE
0044AA
OT029 - Radar Tower Site: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY16
0044AB
OT029 - Radar Tower Site: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0044AA or upon CO determination of bona fide need
0044AC
OT029 - Radar Tower Site: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0044AB or upon CO determination of bona fide need
0044AD
OT029 - Radar Tower Site: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0044AC or upon CO determination of bona fide need
SA501 - SWMUs 86, 87, AOC A
0045AA
SA501 - SWMUs 86, 87, AOC A: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY17
0045AB
SA501 - SWMUs 86, 87, AOC A: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0045AA or upon CO determination of bona fide need
0045AC
SA501 - SWMUs 86, 87, AOC A: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0045AB or upon CO determination of bona fide need
0045AD
SA501 - SWMUs 86, 87, AOC A: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0045AC or upon CO determination of bona fide need
OW508 - SWMU 64
0046AA
OW508 - SWMU 64: Mobilize and develop an optimized exit strategy to achieve SC and implement the elements of the approved strategy in an OES Implementation Plan that fall within the POP.
1Q FY17
0046AB
OW508 - SWMU 64: Implement the elements of the approved optimized exit strategy in a Preliminary Implementation Completion Report that fall within the POP.
Approx. 2 years from 0046AA or upon CO determination of bona fide need
0046AC
OW508 - SWMU 64: Implement the elements of the approved optimized exit strategy in a Final Implementation Completion Report that fall within the POP.
Approx. 2 years from 0046AB or upon CO determination of bona fide need
0046AD
OW508 - SWMU 64: Finalize an optimized exit strategy to achieve SC and implement the elements of the approved strategy in a Final OES Effectiveness Report that fall within the POP.
Approx. 2 years from 0046AC or upon CO determination of bona fide need
OW515 - BUILDING 2121A PROPULSION SHOP
0047AA
OW515 - Bldg. 2121A Propulsion Shop: Achieve Remedial Investigation (RI) within 2 years of NTP.
3Q FY15
OW525 - BUILDING 3104 AUTO HOBBY SHOP
0048AA
OW525 - Bldg. 3104 Auto Hobby Shop: Achieve RI within 2 years of NTP.
3Q FY15
OW541 - BUILDING 4533A AGE MAINTENANCE (NORTH SIDE)
0049AA
OW541 - Bldg. 4533A AGE Maintenance (north side): Achieve RI within 2 years of NTP.
3Q FY15
OW542 - BUILDING 4533B AGE MAINTENANCE (NEXT TO SIDEWALK)
0050AA
OW542 - Bldg. 4533B AGE Maintenance (next to sidewalk): Achieve RI within 2 years of NTP.
3Q FY15
OW544 - BUILDING 4535B AVIONICS MAINTENANCE
0051AA
OW544 - Bldg. 4535B Avionics Maintenance: Achieve RI within 2 years of NTP.
3Q FY15
OW545 - BUILDING 4537 AIRCRAFT MAINTENANCE (BEHIND HANGER NORTH SIDE)
0052AA
OW545 - Bldg. 4537 Aircraft Maintenance (behind hanger north side): Achieve RI within 2 years of NTP.
3Q FY15
OW566 - BUILDING 4909 KC-135 MAINTENANCE RAMP SIDE
0053AA
OW566 - Bldg. 4909 KC-135 Maintenance Ramp Side: Achieve RI within 2 years of NTP.
3Q FY15
*Projected Dates of Exercise are the anticipated award dates for the SubCLINs, but will be subject to the availability of funding and to the bona fide need rule. Note that prior to contract award, the Government may negotiate the SubCLINS based on the Offeror's proposal.