Specs. 12.xps
XPS file 170 KB Posted
- Attached to
- RECOVERY--PROJECT NUMBER ZHTV091886DR, Construct Drop Arm Gate 12A Federal contract opportunity
- Solicitation number
- FA8601-10-R-0017
About this file
Specifications 12 - Attachment 2 Section J
Text of this file
Road "T" Security Gate091886D
SECTION 31 00 00
EARTHWORK
08/08
PART 1 GENERAL
1.1 MEASUREMENT PROCEDURES Not Used
1.1.1 [Enter Appropriate Subpart Title Here]
1.1.2 [Enter Appropriate Subpart Title Here]
1.1.3 [Enter Appropriate Subpart Title Here]
1.1.4 [Enter Appropriate Subpart Title Here]
1.1.5 [Enter Appropriate Subpart Title Here]
1.2 PAYMENT PROCEDURES Not Used, except as noted in Rock Excavation.
1.2.1 [Enter Appropriate Subpart Title Here]
1.2.2 Rock Excavation
Payment for rock excavation will be made at the unit price bid for the rock excavation, and will include all necessary drilling and all incidentals necessary to excavate and dispose of the rock. Select granular material, used as backfill replacing rock excavation, will not be paid for separately, but will be included in the unit price for rock excavation.
1.2.3 [Enter Appropriate Subpart Title Here]
1.2.3.1 [Enter Appropriate Subpart Title Here]
1.3 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water, other than minor seepage, will not be encountered.
d. Rock elevations are indicated on the profiles.
e. Material character includes gravels, sands, and clays.
1.4 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 31 00 00 Page 1
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO T 180(2001; R 2004) Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and an 457-mm (18-in) Drop AASHTO T 224(2001; R 2004) Correction for Coarse Particles in the Soil Compaction Test
ASTM INTERNATIONAL (ASTM)
ASTM C 136(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM D 1140(2000; R 2006) Amount of Material in Soils Finer than the No. 200 (75-micrometer) Sieve ASTM D 1556(2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method ASTM D 1557(2007) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3) ASTM D 2167(2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method ASTM D 2487(2006e1) Soils for Engineering Purposes (Unified Soil Classification System) ASTM D 2937(2004) Density of Soil in Place by the Drive-Cylinder Method ASTM D 422(1963; R 2007) Particle-Size Analysis of Soils ASTM D 4318(2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils ASTM D 6938(2007a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
1.5 DEFINITIONS
1.5.1 Satisfactory Materials
Satisfactory materials comprise any materials classified by ASTM D 2487 as
GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, SW-SM, SC, SW-SC,
SP-SM, SP-SC, . Satisfactory materials for grading comprise stones less than 3 inches, except for fill material for pavements and railroads which comprise stones less than 2 inches in any dimension.
SECTION 31 00 00 Page 2
1.5.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.
1.5.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D 2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D 4318, ASTM C 136, ASTM D 422, and ASTM D 1140.
1.5.4 Degree of Compaction
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557 abbreviated as a percent of laboratory maximum density. Since ASTM D 1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224. To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in AASHTO T 180.
1.5.5 Overhaul
Not Used.
1.5.6 Hard/Unyielding Materials
Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 6 inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.5.7 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1 cubic yard in volume.
Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
SECTION 31 00 00 Page 3
1.5.8 Unstable Material
Unstable material are too wet to properly support the utility pipe, conduit, or appurtenant structure.
1.5.9 Select Granular Material
1.5.9.1 General Requirements
Select granular material consist of well graded sand, gravel, crushed gravel, crushed stone, or crushed slag. Material shall be composed of hard, tough, and durable particles, and shall contain not more than 10 percent by weight of material passing a No. 200 sieve and no less than 95 percent by weight passing the 1 inch sieve. The maximum allowable aggregate size shall be 3/4 inch or the maximum size recommended by the pipe manufacturer, whichever is smaller.
1.5.9.2 California Bearing Ratio Values
Not Used.
1.5.10 Initial Backfill Material
Initial backfill consists of select granular material.
1.5.11 Expansive Soils
Not Used.
1.5.12 Nonfrost Susceptible (NFS) Material
Not Used.
1.5.13 Pile Supported Structure
Not Used.
1.6 SYSTEM DESCRIPTION
Not Used.
1.6.1 Classification of Excavation
Finish the specified excavation on a classified basis, in accordance with the following designations and classifications.
1.6.1.1 Common Excavation
Include common excavation with the satisfactory removal and disposal of all materials not classified as rock excavation.
1.6.1.2 Rock Excavation
Include rock excavation excavating, grading, disposing of material classified as rock, and the satisfactory removal and disposal of boulders 1 cubic yard or more in volume; solid rock; rock material that is in ledges, bedded deposits, and unstratified masses, which cannot be removed without systematic drilling and blasting; firmly cemented conglomerate deposits possessing the characteristics of solid rock impossible to remove without SECTION 31 00 00 Page 4 systematic drilling and blasting; and hard materials (see Definitions).
Include the removal of any concrete or masonry structures, except pavements, exceeding 1 cubic yard in volume that may be encountered in the work in this classification. If at any time during excavation, the Contractor encounters material that may be classified as rock excavation, uncover such material and notify the Contracting Officer. Do not proceed with the excavation of this material until the Contracting Officer has classified the materials as common excavation or rock excavation and has taken cross sections as required. Failure on the part of the Contractor to uncover such material, notify the Contracting Officer, and allow ample time for classification and cross sectioning of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Contracting Officer for the areas of work in which such deposits occur.
1.6.2 Blasting
Blasting will not be permitted.
1.6.3 Dewatering Work Plan
Submit procedures for accomplishing dewatering work.
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Shoring; G Dewatering Work Plan; G Submit 15 days prior to starting work.
SD-03 Product Data Utilization of Excavated Materials; G Procedure and location for disposal of unused satisfactory material. Notification of encountering rock in the project.
Advance notice on the opening of excavation . Advance notice on shoulder construction for rigid pavements.
SD-06 Test Reports Testing SD-07 Certificates SECTION 31 00 00 Page 5
Testing
PART 2 PRODUCTS
2.1 REQUIREMENTS FOR OFFSITE SOILS
Provide clean material.
2.2 BURIED WARNING AND IDENTIFICATION TAPE
Provide metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines. Provide tape on rolls, 3 inch minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil.
Warning Tape Color Codes [Red:] [Electric] [Yellow:] [Gas, Oil; Dangerous Materials] [Orange:] [Telephone and Other Communications] [Blue:] [Water Systems] [Green:] [Sewer Systems] [White:] [Steam Systems] [Gray:] [Compressed Air]
2.2.1 Warning Tape for Metallic Piping
Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.2.2 Detectable Warning Tape for Non-Metallic Piping
Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.3 DETECTION WIRE FOR NON-METALLIC PIPING
Insulate a single strand, solid copper detection wire with a minimum of 12
AWG.
2.4 MATERIAL FOR RIP-RAP
Provide material meeting the requirements of ODOT Rock Aggregate Type B, if needed.
SECTION 31 00 00 Page 6
2.4.1 Bedding Material
Provide select granular material consisting of sand, gravel, or crushed rock, well graded, with a maximum particle size of 3/4 inch. Compose material of tough, durable particles. Allow fines passing the No. 200 standard sieve with a plasticity index less than six.
2.4.2 Grout
Provide durable grout composed of cement, water, an air-entraining admixture, and sand mixed in proportions of one part portland cement to two parts of sand, sufficient water to produce a workable mixture, and an amount of admixture which will entrain sufficient air, as determined by the Contracting Officer. Mix grout in a concrete mixer. Allow a sufficient mixing time to produce a mixture having a consistency permitting gravity flow into the interstices of the rip-rap with limited spading and brooming.
2.4.3 Rock
Not Used.
2.5 CAPILLARY WATER BARRIER
Not Used.
2.6 PIPE CASING
2.6.1 Casing Pipe
Not Used.
2.6.2 Wood Supports
Not Used.
PART 3 EXECUTION
3.1 GENERAL EXCAVATION
Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas.
During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times. Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from other approved areas selected by the Contractor as specified.
SECTION 31 00 00 Page 7
3.1.1 Ditches, Gutters, and Channel Changes
Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on the d rawings . Do not excavate ditches and gutters below grades shown.
Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown. Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch.
Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.
3.1.2 Drainage Structures
Make excavations to the lines, grades, and elevations shown, or as directed. Provide trenches and foundation pits of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata. Do not disturb the bottom of the excavation when concrete or masonry is to be placed in an excavated area. Do not excavate to the final grade level until just before the concrete or masonry is to be placed. Where pile foundations are to be used, stop the excavation of each pit at an elevation 1 foot above the base of the footing, as specified, before piles are driven. After the pile driving has been completed, remove loose and displaced material and complete excavation, leaving a smooth, solid, undisturbed surface to receive the concrete or masonry.
3.1.3 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. Construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and or provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.
3.1.4 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least 3 feet below the working level. Operate dewatering system continuously until construction work below existing water levels is SECTION 31 00 00 Page 8 complete. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.
3.1.5 Trench Excavation Requirements
Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls more than 5 feet high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in.
Shore vertical trench walls more than 5 feet high. Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 18 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inch inside diameter, and do not exceed 24 inch plus pipe outside diameter for sizes larger than 24 inch inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government.
3.1.5.1 Bottom Preparation
Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of 3 inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.
3.1.5.2 Removal of Unyielding Material
Where unyielding material is encountered in the bottom of the trench, remove such material 6 inch below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION.
3.1.5.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND COMPACTION. When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.
3.1.5.4 Excavation for Appurtenances
Provide excavation for manholes, catch-basins, inlets, or similar structures sufficient to leave at least 12 inch clear between the outer structure surfaces and the face of the excavation or support members of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations. Clean rock of loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata.
Specify removal of unstable material. When concrete or masonry is to be SECTION 31 00 00 Page 9 placed in an excavated area, take special care not to disturb the bottom of the excavation. Do not excavate to the final grade level until just before the concrete or masonry is to be placed.
3.1.5.5 Jacking, Boring, and Tunneling
Unless otherwise indicated, provide excavation by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.
3.1.6 Underground Utilities
The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. Excavation made with power-driven equipment is not permitted within 5 feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
3.1.7 Structural Excavation
Ensure that footing subgrades have been inspected and approved by the Contracting Officer prior to concrete placement.
3.2 OPENING AND DRAINAGE OF EXCAVATION
Except as otherwise permitted, excavation areas providing adequate drainage. Transport overburden and other spoil material to designated spoil areas or otherwise dispose of as directed. Ensure that excavation of any area, or dumping of spoil material results in minimum detrimental effects on natural environmental conditions.
3.3 SHORING
3.3.1 General Requirements
Finish shoring, including sheet piling, and install as necessary to protect workmen, banks, adjacent paving, structures, and utilities. Remove shoring, bracing, and sheeting as excavations are backfilled, in a manner to prevent caving.
3.3.2 Geotechnical Engineer
Hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer is responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions.
The Geotechnical Engineer is responsible for updating the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and submit an updated plan if necessary. Submit a monthly written report, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Contracting SECTION 31 00 00 Page 10
Officer is responsible for arranging meetings with the Geotechnical Engineer at any time throughout the contract duration.
3.4 GRADING AREAS
Do not haul satisfactory material excavated in one grading area to another grading area except when so directed in writing. Place and grade stockpiles of satisfactory and unsatisfactory and wasted materials as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations;
separately stockpile excavated satisfactory and unsatisfactory materials.
Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. If the Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources.
3.5 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE
Do not excavate to final grade until just before concrete is to be placed.
Only use excavation methods that will leave the foundation rock in a solid and unshattered condition. Roughen the level surfaces, and cut the sloped surfaces, as indicated, into rough steps or benches to provide a satisfactory bond. Protect shales from slaking and all surfaces from erosion resulting from ponding or water flow.
3.6 GROUND SURFACE PREPARATION
3.6.1 General Requirements
Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inch before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inch, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inch and compact it as specified for the adjacent fill.
3.6.2 Frozen Material
Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used].
3.7 UTILIZATION OF EXCAVATED MATERIALS
Dispose unsatisfactory materials removing from excavations into designated waste disposal or spoil areas. Use satisfactory material removed from excavations, insofar as practicable, in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar purposes. Do not waste any satisfactory excavated material without SECTION 31 00 00 Page 11 specific written authorization. Dispose of satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Clear and grub newly designated waste areas on Government-controlled land before disposal of waste material thereon. Stockpile and use coarse rock from excavations for constructing slopes or embankments adjacent to streams, or sides and bottoms of channels and for protecting against erosion. Do not dispose excavated material to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way.
3.8 BURIED TAPE AND DETECTION WIRE
3.8.1 Buried Warning and Identification Tape
Provide buried utility lines with utility identification tape. Bury tape 12 inch below finished grade; under pavements and slabs, bury tape 6 inch below top of subgrade.
3.8.2 Buried Detection Wire
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inch above the top of pipe. Extend the wire continuously and unbroken, from manhole to manhole. Terminate the ends of the wire inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. Furnish insulated wire over it's entire length. Install wires at manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, terminate the wire in the valve pit at the pump station end of the pipe.
3.9 BACKFILLING AND COMPACTION
Place backfill adjacent to any and all types of structures, and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Prepare ground surface on which backfill is to be placed as specified in paragraph GROUND SURFACE PREPARATION. Provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.9.1 Trench Backfill
Backfill trenches to the grade shown. Leave the joints and couplings uncovered during the pressure test.
3.9.1.1 Replacement of Unyielding Material
Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material.
3.9.1.2 Replacement of Unstable Material
Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding 6 inch loose thickness.
SECTION 31 00 00 Page 12
3.9.1.3 Bedding and Initial Backfill
Provide initial backfill material and compact it with approved tampers to a height of at least one foot above the utility pipe or conduit. Bring up the backfill evenly on both sides of the pipe for the full length of the pipe. Take care to ensure thorough compaction of the fill under the haunches of the pipe. Except as specified more stringently in the individual piping sections, bedding support for utilities shall consist of a minimum of 4 inches or 1/4 the diameter of the utility, whichever is greater, of select granular material. Bedding shall be continued upward for the full width of the trench to 12 inches above the top of the utility (combined bedding and cover). All materials shall be compacted to 95 percent of ASTM D 1557 maximum density.
3.9.1.4 Final Backfill
Fill the remainder of the trench, except for special materials for roadways, railroads and airfields, with satisfactory material. Place backfill material and compact as follows:
a. Roadways, Railroads, and Airfields: Place backfill up to the required elevation as specified. Do not permit water flooding or jetting methods of compaction.
b. Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas: Deposit backfill in layers of a maximum of 12 inch loose thickness, and compact it to 85 percent maximum density for cohesive soils and 90 percent maximum density for cohesionless soils. Do not permit compaction by water flooding or jetting. Apply this requirement to all other areas not specifically designated above.
3.9.2 Backfill for Appurtenances
After the manhole, catchbasin, inlet, or similar structure has been constructed and the concrete has been allowed to cure for 3 days, place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress.
3.10 SPECIAL REQUIREMENTS
Special requirements for both excavation and backfill relating to the specific utilities are as follows:
3.10.1 Gas Distribution
Excavate trenches to a depth that will provide a minimum 18 inch of cover in rock excavation and a minimum 24 inch of cover in other excavation.
3.10.2 Water Lines
Excavate trenches to a depth that provides a minimum cover of 4 feet from the existing ground surface, or from the indicated finished grade, whichever is lower, to the top of the pipe.
SECTION 31 00 00 Page 13
3.10.3 Heat Distribution System
Free initial backfill material of stones larger than 1/4 inch in any dimension.
3.10.4 Electrical Distribution System
Provide a minimum cover of 24 inch from the finished grade to direct burial cable and conduit or duct line, unless otherwise indicated.
3.10.5 Sewage Absorption Trenches or Pits
3.10.5.1 Porous Fill
Not Used.
3.10.5.2 Cover
Not Used.
3.10.6 Pipeline Casing
Not Used.
3.10.6.1 Bore Holes
Not Used.
3.10.6.2 Cleaning
Not Used.
3.10.6.3 End Seals
Not Used
3.10.7 Rip-Rap Construction
Construct rip-rap on filter fabric in the areas indicated. Trim and dress indicated areas to conform to cross sections, lines and grades shown within a tolerance of 0.1 foot.
3.10.7.1 Bedding Placement
Spread filter fabric, and place bedding material uniformly to a thickness of at least 4 inch on prepared subgrade. Finish bedding to present even surface free from mounds and windrows.
3.10.7.2 Stone Placement
Place rock for rip-rap on prepared bedding material to produce a well graded mass with the minimum practicable percentage of voids in conformance with lines and grades indicated. Distribute larger rock fragments, with dimensions extending the full depth of the rip-rap throughout the entire mass and eliminate "pockets" of small rock fragments. Rearrange individual pieces by mechanical equipment or by hand as necessary to obtain the distribution of fragment sizes specified above.
SECTION 31 00 00 Page 14
3.10.7.3 Grouting
Not Used.
3.11 EMBANKMENTS
3.11.1 Earth Embankments
Construct earth embankments from satisfactory materials free of organic or frozen material and rocks with any dimension greater than 2 inches. Place the material in successive horizontal layers of loose material not more than 12 inch in depth. Spread each layer uniformly on a soil surface that has been moistened or aerated as necessary, and scarified or otherwise broken up so that the fill will bond with the surface on which it is placed.
After spreading, plow, disk, or otherwise brake up each layer; moisten or aerate as necessary; thoroughly mix; and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials. Compaction requirements for the upper portion of earth embankments forming subgrade for pavements are identical with those requirements specified in paragraph SUBGRADE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.11.2 Rock Embankments
Not Used.
3.12 SUBGRADE PREPARATION
3.12.1 Proof Rolling
Finish proof rolling on an exposed subgrade free of surface water (wet conditions resulting from rainfall) which would promote degradation of an otherwise acceptable subgrade.
3.12.2 Construction
Shape subgrade to line, grade, and cross section, and compact as specified. Include plowing, disking, and any moistening or aerating required to obtain specified compaction for this operation. Remove soft or otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed. Excavate rock encountered in the cut section to a depth of 6 inch below finished grade for the subgrade. Bring up low areas resulting from removal of unsatisfactory material or excavation of rock to required grade with satisfactory materials, and shape the entire subgrade to line, grade, and cross section and compact as specified.
3.12.3 Compaction
Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.12.3.1 Subgrade for Pavements
Compact subgrade for pavements to at least 95 percentage laboratory maximum density for the depth below the surface of the pavement shown.
SECTION 31 00 00 Page 15
3.12.3.2 Subgrade for Shoulders
Compact subgrade for shoulders to at least95 percentage laboratory maximum density for the depth below the surface of shoulder shown.
3.12.3.3 Subgrade for Airfield Pavements
Not Used.
3.13 SHOULDER CONSTRUCTION
Construct shoulders of satisfactory excavated material or as otherwise shown or specified. Construct shoulders immediately after adjacent paving is complete. In the case of rigid pavements, do not construct shoulders until permission of the Contracting Officer has been obtained. Compact the entire shoulder area to at least the percentage of maximum density as specified in paragraph SUBGRADE PREPARATION above, for specific ranges of depth below the surface of the shoulder. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Finish shoulder construction in proper sequence in such a manner that adjacent ditches will be drained effectively and that no damage of any kind is done to the adjacent completed pavement. Align the completed shoulders true to grade and shaped to drain in conformity with the cross section shown.
3.14 FINISHING
Finish the surface of excavations, embankments, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph SUBGRADE PREPARATION. Finish gutters and ditches in a manner that will result in effective drainage. Finish the surface of areas to be turfed from settlement or washing to a smoothness suitable for the application of turfing materials. Repair graded, topsoiled, or backfilled areas prior to acceptance of the work, and re-established grades to the required elevations and slopes.
3.14.1 Subgrade and Embankments
During construction, keep embankments and excavations shaped and drained.
Maintain ditches and drains along subgrade to drain effectively at all times. Do no disturb the finished subgrade by traffic or other operation.
Protect and maintain the finsihed subgrade in a satisfactory condition until ballast, subbase, base, or pavement is placed. Do not permit the storage or stockpiling of materials on the finished subgrade. Do not lay subbase, base course, ballast, or pavement until the subgrade has been checked and approved, and in no case place subbase, base, surfacing, pavement, or ballast on a muddy, spongy, or frozen subgrade.
3.14.2 Capillary Water Barrier
Not Used.
3.14.3 Grading Around Structures
Construct areas within 5 feet outside of each building and structure line true-to-grade, shape to drain, and maintain free of trash and debris until SECTION 31 00 00 Page 16 final inspection has been completed and the work has been accepted.
3.15 TESTING
Perform testing by a validated commercial testing laboratory. If the Contractor elects to establish testing facilities, do not permit work requiring testing until the Contractor's facilities have been inspected, validated and approved by the Contracting Officer. Determine field in-place density in accordance with ASTM D 1556 ASTM D 2167 ASTM D 6938.
When ASTM D 6938 is used, check the calibration curves and adjust using only the sand cone method as described in ASTM D 1556. ASTM D 6938 results in a wet unit weight of soil in determining the moisture content of the soil when using this method. Check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D 6938; check the calibration of both the density and moisture gauges at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer. ASTM D 2937, use the Drive Cylinder Method only for soft, fine-grained, cohesive soils.
When test results indicate, as determined by the Contracting Officer, that compaction is not as specified, remove the material, replace and recompact to meet specification requirements. Perform tests on recompacted areas to determine conformance with specification requirements. Appoint a registered professional civil engineer to certify inspections and test results. These certifications shall state that the tests and observations were performed by or under the direct supervision of the engineer and that the results are representative of the materials or conditions being certified by the tests. The following number of tests, if performed at the appropriate time, will be the minimum acceptable for each type operation.
3.15.1 Fill and Backfill Material Gradation
One test per 200 cubic yards stockpiled or in-place source material.
Determine gradation of fill and backfill material in accordance with
ASTM C 136 ASTM D 422 ASTM D 1140.
3.15.2 In-Place Densities
a. One test per 3,000 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by other than hand-operated machines.
b. One test per 3,000 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by hand-operated machines.
c. One test per 300 linear feet, or fraction thereof, of each lift of embankment or backfill for [roads] [airfields].
d. One test per 300 linear feet, or fraction thereof, of each lift of embankment or backfill for railroads.
3.15.3 Check Tests on In-Place Densities
If ASTM D 6938 is used, check in-place densities by ASTM D 1556 as follows:
a. One check test per lift for each 9,000 square feet, or fraction thereof, of each lift of fill or backfill compacted by other than hand-operated machines.
b. One check test per lift for each 9,000 square feet, of fill or SECTION 31 00 00 Page 17 backfill areas compacted by hand-operated machines.
c. One check test per lift for each 900 linear feet, or fraction thereof, of embankment or backfill for [roads] [airfields].
d. One check test per lift for each 900 linear feet, or fraction thereof, of embankment or backfill for railroads.
3.15.4 Moisture Contents
In the stockpile, excavation, or borrow areas, perform a minimum of two tests per day per type of material or source of material being placed during stable weather conditions. During unstable weather, perform tests as dictated by local conditions and approved by the Contracting Officer.
3.15.5 Optimum Moisture and Laboratory Maximum Density
Perform tests for each type material or source of material to determine the optimum moisture and laboratory maximum density values. One representative test per 200 cubic yards of fill and backfill, or when any change in material occurs which may affect the optimum moisture content or laboratory maximum density.
3.15.6 Tolerance Tests for Subgrades
Perform continuous checks on the degree of finish specified in paragraph SUBGRADE PREPARATION during construction of the subgrades.
3.15.7 Displacement of Sewers
After other required tests have been performed and the trench backfill compacted to the finished grade surface, inspect the pipe to determine whether significant displacement has occurred. Conduct this inspection in the presence of the Contracting Officer. Inspect pipe sizes larger than 36 inch, while inspecting smaller diameter pipe by shining a light or laser between manholes or manhole locations, or by the use of television cameras passed through the pipe. If, in the judgement of the Contracting Officer, the interior of the pipe shows poor alignment or any other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government.
3.16 DISPOSITION OF SURPLUS MATERIAL
Surplus material or other soil material not required or suitable for filling or backfilling, and brush, refuse, stumps, roots, and timber shall be removed from Government property.
-- End of Section -- SECTION 31 00 00 Page 18
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 091886DR Add 1.doc | DOC document | |
| VPP Safety Health Plan.doc | DOC document | |
| Amendment 5.doc | DOC document | |
| Question 5.doc | DOC document | |
| Amendment 4.doc | DOC document | |
| Question 4.docx | DOCX document | |
| Amendment 3.doc | DOC document | |
| Question 3.doc | DOC document | |
| Question 2.doc | DOC document | |
| Wage Decision 2.docx | DOCX document | |
| Amendment 2.doc | DOC document | |
| Question 1.docx | DOCX document | |
| Sign In Sheet - Site Visit.pdf | ||
| Drawings.pdf | ||
| Amendment 1.doc | DOC document | |
| Specifications.pdf | ||
| Drawings.pdf | ||
| Specs. 4.xps | XPS file | |
| Statement of Objectives.pdf | ||
| Specs. 7.xps | XPS file | |
| Specs. 5.xps | XPS file | |
| Specs. 6.xps | XPS file | |
| Specs. 10.xps | XPS file | |
| Specs. 8.xps | XPS file | |
| Specs. 1.xps | XPS file | |
| Specs. 3.xps | XPS file | |
| Specs. 11.xps | XPS file | |
| Specs. 2.xps | XPS file | |
| Specs. 9.xps | XPS file | |
| Solicitation.doc | DOC document | |
| Wage Decision.docx | DOCX document |
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .