Vendor_QandA.pdf

PDF 59 KB Posted

Attached to
Secure Software Development Room Federal contract opportunity
Solicitation number
fa855518r0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Solicitation Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Secure Software Development Room, newest first.
File Type Posted
Q_and_A_18_Jan.pdf PDF
Statement_of_Work_Dated_12_Jan_2018.pdf PDF
FA855518R0001_______0002.pdf PDF
Vendor_Q&A_12_Jan.pdf PDF
Questions_3_Jan_18.pdf PDF
(FOUO)_FA8555-18-R-0001_Questions_18_Dec_2017.pdf PDF
FA855518R0001_______0001.pdf PDF
StatementOfWork(SOW)_Version2.pdf PDF
20171208_Shelter_SOW_RFP_Version.pdf PDF
Attachment_5_Past_Performance_Questionnaire.docx DOCX document
Attachment_4_Consent_Form.docx DOCX document
Attachment_2_Client_Authorization_Letter.docx DOCX document
afmc807_-_SSDR_(final).pdf PDF
(FOUO)FD2399-18-00139_TBD_SP_Solicitation_DD254_(003).pdf PDF
Attachment_3_Transmittal_Letter.docx DOCX document
DD1653_FD2399-18-00139_20_Nov_17.doc DOC document
FA855518R0001.pdf PDF
F3QCAZ7311B104_18-00139-FORM_158.pdf PDF
Attachment_1_FACTS_Sheet.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8555‐18‐R‐0001 – Vendor Questions & Answers

Question Recommendation

1. What is the TEMPEST level for waveguides and

HVAC?

Level 1 (100db) – See RFP Amendment FA8555‐18‐ R‐0001‐0001, SOW Version 2, dated 14 DEC 2017

2. What is the TEMPEST level for power filters and any low voltage filters?

Level 1 (100db) – See RFP Amendment FA8555‐18‐ R‐0001‐0001, SOW Version 2, dated 14 DEC 2017

3. What is the TEMPEST level for all six sides (structure)?

Level 1 (100db) – See RFP Amendment FA8555‐18‐ R‐0001‐0001, SOW Version 2, dated 14 DEC 2017

4. Are STC‐50 steel panels acceptable? Yes, see material equivalent statement in SOW section 4.9.2. Complete constructions still needs to meet Tempest, Level 1 requirements.