Question Response

1. If non US Flag carrier (foreign flag carrier) would represent a cheaper alternative would such a solution be acceptable?

The potential to waive the US Flag Vessel clause can be visited after award. However, for proposal purposes it should be priced to comply with the US Flag Vessel clause.

2. What is the weight limit for the bridge connecting to the island?

There is no bridge; there’s a tunnel. There’s no known weight limit for the tunnel.

3. Does the crane at the final location have the spreader bars and chains to lift heavy equipment?

The contractor is responsible for providing the spreader bar (see SOW paragraph 3) and any rigging equipment (see SOW paragraph 3.10).

4. Could we hire a local electrician and IT technician that have the necessary clearance level?

Hiring local personnel is sufficient as long as they have the required clearance level.

5. Your SOW mentions IDS but does not indicate ACS. Will you install ACS (e.g. card reader)?

A card reader is currently not planned. Per section 4.10.6 – Doors & Locks the main entrance door should have a lock per FF-L- 2740.