Questions_3_Jan_18.pdf

PDF 81 KB Posted

Attached to
Secure Software Development Room Federal contract opportunity
Solicitation number
fa855518r0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Q&A 3 Jan

View the file

Other files for this federal contract opportunity

Other files attached to Secure Software Development Room, newest first.
File Type Posted
Q_and_A_18_Jan.pdf PDF
FA855518R0001_______0002.pdf PDF
Statement_of_Work_Dated_12_Jan_2018.pdf PDF
Vendor_Q&A_12_Jan.pdf PDF
(FOUO)_FA8555-18-R-0001_Questions_18_Dec_2017.pdf PDF
FA855518R0001_______0001.pdf PDF
Vendor_QandA.pdf PDF
StatementOfWork(SOW)_Version2.pdf PDF
(FOUO)FD2399-18-00139_TBD_SP_Solicitation_DD254_(003).pdf PDF
Attachment_3_Transmittal_Letter.docx DOCX document
Attachment_2_Client_Authorization_Letter.docx DOCX document
afmc807_-_SSDR_(final).pdf PDF
20171208_Shelter_SOW_RFP_Version.pdf PDF
Attachment_5_Past_Performance_Questionnaire.docx DOCX document
Attachment_4_Consent_Form.docx DOCX document
DD1653_FD2399-18-00139_20_Nov_17.doc DOC document
FA855518R0001.pdf PDF
F3QCAZ7311B104_18-00139-FORM_158.pdf PDF
Attachment_1_FACTS_Sheet.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Response

1. If non US Flag carrier (foreign flag carrier) would represent a cheaper alternative would such a solution be acceptable?

The potential to waive the US Flag Vessel clause can be visited after award. However, for proposal purposes it should be priced to comply with the US Flag Vessel clause.

2. What is the weight limit for the bridge connecting to the island?

There is no bridge; there’s a tunnel. There’s no known weight limit for the tunnel.

3. Does the crane at the final location have the spreader bars and chains to lift heavy equipment?

The contractor is responsible for providing the spreader bar (see SOW paragraph 3) and any rigging equipment (see SOW paragraph 3.10).

4. Could we hire a local electrician and IT technician that have the necessary clearance level?

Hiring local personnel is sufficient as long as they have the required clearance level.

5. Your SOW mentions IDS but does not indicate ACS. Will you install ACS (e.g. card reader)?

A card reader is currently not planned. Per section 4.10.6 – Doors & Locks the main entrance door should have a lock per FF-L- 2740.