Q_and_A__2.docx

DOCX document 14 KB Posted

Attached to
Renovation and Repair Building 238
Solicitation number
FA8201-15-R-RENO
Issued by

About this file

These questions were inadvertently omitted from the original Q A.

View the file

Other files

File Type Posted
FA8201-15-B-0001-0005.pdf PDF
Drawing_Clarification_Document_1_June_2015.docx DOCX document
Bid_Opening_Information.docx DOCX document
Amendment_4.pdf PDF
08_33_13_Rolling_Counter_Doors_-_Hill_AFB.pdf PDF
Amendment_3.pdf PDF
KRSM238_142063_IFC_20150323_Combined_34x22(5-18-15).pdf PDF
QA_Responses_RENO.docx DOCX document
238_Pictures__4.zip ZIP file
238_Pictures__3.zip ZIP file
238_Pictures__2.zip ZIP file
238_Pictures__1.zip ZIP file
Building_238_Amendment_2.pdf PDF
238_Site_Visit_List.docx DOCX document
Building_238_Amendment_1.pdf PDF
FA8201-15-B-0001_Solicitation.zip ZIP file
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

*Aftermarket solutions to measure outside air flow generally do not work with packaged HVAC units due to limited space and geometry causing excessive turbulence. Factory options for outside air flow are sometimes available. Would the government prefer to: 1. Require a factory flow sensor option. 2. Calculate outside air flow from supply and return air flow sensors or 3. Delete this requirement.

PROVIDE AIRFLOW MONITORING

*A discharge damper is not required on this type of unit can it be deleted? If not please explain the purpose.

DAMPER IS REQUIRED FOR THE EMERGENCY SHUTDOWN (ATFP)

*What is the required location of the hot water coil valve? Will it be located inside the unit or outside, above the roof line or below?

LOCATE THE HOT WATER VALVE ABOVE THE ROOF LINE (FOR MAINTENANCE PURPOSES). INSIDE OF THE UNIT WOULD BE PREFERABLE.

*The specifications of this project call for the hot water coils on the RTUs and Vav to be tied in to the building hot water loop. Previous jobs in this building have had heat exchangers installed to separate from the main building water loop due to the problems with the main loop (i.e. leaks, untreated system, etc.). Will a heat exchanger be required for this project?

CONNECT TO THE HOT WATER LOOP AS SHOWN. NO HEAT-EXCHANGERS WERE MENTIONED IN THE RFP.