B1_SCAI_-_Questions_ _Answers_2_-_15_MAY_14.pdf

PDF 40 KB Posted

Attached to
B-1B Self-Contained Attitude Indicator (SCAI)
Solicitation number
FA8107-14-R-0001
Issued by

About this file

Questions Answers 2 - 15 May 14

View the file

Other files

File Type Posted
FA810714R0001_______0005.RTF RTF text file
FA810714R0001_______0005_Appendix_D_Rev_1__Section_L__ITO.pdf PDF
FA810714R0001_______0004.RTF RTF text file
FA810714R0001_______0004_SCAI_SOW_Rev_1_30Jul2014.pdf PDF
FA810714R0001_______0003.RTF RTF text file
FA810714R0001_______0002.RTF RTF text file
FA810714R0001_______0001.RTF RTF text file
FA810714R0001_Appendix_D__Section_L__ITO.pdf PDF
FA810714R0001_Appendix_G__CDRLS.pdf PDF
FA810714R0001_Appendix_A__SOW.pdf PDF
FA810714R0001_Appendix_C__Safety_Specifications.pdf PDF
FA810714R0001_Appendix_E__Section_M__Evaluation_Factors.pdf PDF
FA810714R0001.RTF RTF text file
FA810714R0001_Appendix_B__SRD_Redacted.pdf PDF
FA810714R0001_Appendix_F__Pricing_Matrix.xlsx XLSX spreadsheet
FA810714R0001_ATTACHMENT_A__Warranty_Tracking_Information.pdf PDF
B1_SCAI_-_Questions_ _Answers_2_-_15_APR_14.pdf PDF
SCAI_SOW_Draft-_8_APR_14.pdf PDF
L5306182_(Web _Panel _Instrument_-_Center).pdf PDF
SCAI_DD_254_Draft_-_8_APR_14.pdf PDF
L5306180_(Panel_Assembly_Instrument_-_Center).pdf PDF
L5306181_(Panel _Instrument_-_Center).pdf PDF
LP0320024_(Design_Standard_Cutout).pdf PDF
SCAI_SRD_Draft_-_8_APR_14.pdf PDF
L5159404_(Pitot_and_Static_system_Installation).pdf PDF
SCAI_Pre-RFP_Q A_-_8_APR_14.pdf PDF
SCAI_Pre-Solicitation_Tele-Conference_-_17_Mar_14_FINAL.ppsx PPSX file
SCAI_Pre-Solicitation_Tele-Conference_-_17_Mar_14_FINAL.pdf PDF
Appendix_E_-_Section_M_-_Evaluation_Factors.pdf PDF
Appendix_D_-Section_L-_ITO.pdf PDF
Appendix_A_-_Attachment_1_-_SRD.pdf PDF
Appendix_F_-_Pricing_Matrix.xlsx XLSX spreadsheet
FA810714R0001_DRAFT_No._1.pdf PDF
Appendix_A_-_SOW.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI FA8107-14-R-0001

Questions & Answers

15 MAY 2014

1. Question: Please verify the following:

In 3.6.1 Unit Interface the document has the following requirement:

3.6.1. Unit Interface

The system installation must mate with the following connectors:

. PITOT connector (7/16-20UNF-3B) . STATIC connector (7/16-20UNF-3B) . ES27484T12F35S Electrical Plug (Deviations from the connector specified shall be entertained.)

It shows that the Pitot and Static have the same size connector. Generally, these are of a different size such that they cannot be mis-connected. Are these the correct connector requirements?

Government Response:

The correct pitot/static connections are as follows:

Pitot - 9/16-18UNJF-3B Static - 7/16-20UNJF-3B

The SRD will be changed to reflect this.

2. Question: Will provisions for material and tools, associated with over and above repairs, be added to CLIN 0006 or included on a separate CLIN?

Government Response:

Provisions for materials and tools will be added to CLIN 0006. Exact details are TBD.

3. Question: What is the meaning of “The contractor shall waive any/all data rights of intellectual property with regard to concepts, principles, and/or theory used in the design(s) submitted to the Government? (Reference SOW 1.7 Data Rights)

Government Response:

Government is updating SOW to remove this language from para. 1.7. See final SOW with official RFP for more information. SOW will be updated to reflect specific FAR & DFAR requirements.

4. Question: What is the security level; as a draft DD Form 254 was not provided? (Reference SOW 1.6 Security)

Government Response:

The Government has determined that no DD Form 254 will be required.

5. Question: What is the meaning of “The contractor shall waive any/all data rights of intellectual property with regard to concepts, principles, and/or theory used in the design(s) submitted to the Government? (Reference SOW 1.7 Data Rights)

RFI FA8107-14-R-0001

Questions & Answers

15 MAY 2014

Government Response:

Statement in 1.7 has been removed from the SOW. The SOW is being updated to reflect a more accurate interpretation of FAR data requirements. RFP clauses will reflect government requirements of data rights.

6. Question: What is the certification process for the firmware?

Government Response:

Industry certification of firmware will be acceptable. Proposal should reflect compliance with para 3.1.3 of SCAI SOW.

7. Question: Will there be a need for SSEC as part of the SCAI requirement? Does the aircraft need to be RVSM compliant?

Government Response:

There will be no RVSM requirement. There is no known SSEC requirement; however, a functional system must be provided.

SSEC = Static Source Error Correction RVSM = Reduced Vertical Separation Minimum