Prime Cover sheet
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | Sheet | 1 of 19 | ||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Final Estimate IGE | D:\Projects\….\032-33_FinalEst.xls | |||||||||
| Item | Description | % | Material | Labor | Total | Total Cost | Option Bid Summary | |||
| No. | SUMMARY SHEET | Cost | Cost | Cost | ||||||
| 1 | General Construction Subcontractors | |||||||||
| 2 | ||||||||||
| 3 | Mechanical Subcontractor | |||||||||
| 4 | Electrical Subcontractor | |||||||||
| 5 | Fire Alarm Subcontractor | |||||||||
| 6 | Option Bid #1 | |||||||||
| 7 | Subtotal | |||||||||
| 8 | Prime Mark Up on Subcontractors | |||||||||
| 9 | Total Subcontractors | |||||||||
| 10 | ||||||||||
| 11 | General Conditions | |||||||||
| 12 | ||||||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | Subtotal | |||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | Prime Overhead and Profit | |||||||||
| 20 | Subtotal | |||||||||
| 21 | Total Including Subcontractors | |||||||||
| 22 | Escalation to midpoint of construction | |||||||||
| 23 | Subtotal | |||||||||
| 24 | Bond | |||||||||
| 25 | Subtotal | |||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| 28 | ||||||||||
| 29 | ||||||||||
| 30 | ||||||||||
| 31 | ||||||||||
| 32 |
&CSolicitation No. FA7012-10-R-0020 Attachment No. 7
General Conditions
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 2 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Conditions - 2008 Means Prices | Prices by | Daihl | |||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | superintentdant/cqc, full time | 52 | WK | |||||||
| 2 | project manager, 1/4 time | 52 | WK | |||||||
| 3 | Security processing | 1 | Job | |||||||
| 4 | field office expenses | 12 | MO | |||||||
| 5 | office supplies | 12 | MO | |||||||
| 6 | telephone bills | 12 | MO | |||||||
| 7 | dumpster, 30 cy, 1 dump per week | 52 | WK | |||||||
| 8 | daily cleanup (2 hour/day) in occupied areas | 540 | MH | |||||||
| 9 | mobilization/demobilization | 160 | MH | |||||||
| 10 | plastic sheets, 6 mil, fire retardent | 1,500 | SF | |||||||
| 11 | Crane, flatbed mounted, 3-ton capacity | 6 | day | |||||||
| 12 | ||||||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 1 Summary
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | ||||||||
| Bolling AFB | Sheet | 3 of 19 | |||||||||
| Washington, D.C. | Dated | ||||||||||
| Estimate Valid to | |||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | |||||||||
| Checked by | |||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | ||||||||||
| Item | Description | % | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||||
| 1 | Interior Architectural Construction | ||||||||||
| 2 | Interior Architectural Equipment | ||||||||||
| 3 | Staff Toilet Architectural Construction | ||||||||||
| 4 | Exterior & Supplemental Architectural Components | ||||||||||
| 5 | Site Work | ||||||||||
| 6 | |||||||||||
| 7 | |||||||||||
| 8 | |||||||||||
| 9 | |||||||||||
| 10 | |||||||||||
| 11 | |||||||||||
| 12 | |||||||||||
| 13 | |||||||||||
| 14 | |||||||||||
| 15 | |||||||||||
| 16 | |||||||||||
| 17 | |||||||||||
| 18 | |||||||||||
| 19 | Subtotal | ||||||||||
| 20 | |||||||||||
| 21 | |||||||||||
| 22 | |||||||||||
| 23 | |||||||||||
| 24 | |||||||||||
| 25 | Subcontractor Overhead | ||||||||||
| 26 | Subtotal | ||||||||||
| 27 | Subcontractor Profit | ||||||||||
| Sheet Total |
Sub No 1 Sheet 1
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 4 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | General Construction | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||
| 1 | Demo Exist. Guest Rm. Carpet | 21,188 | SF | |||||||
| 2 | Demo Exist. Guest Rm. Quarry Tile | 1116 | SF | |||||||
| 3 | Demo Exist. Guest Rm. Ceramic Tile Fl. | 2604 | SF | |||||||
| 4 | Demo Exist. Guest Rm. Gyp. Bd. Chase | 1984 | SF | |||||||
| 5 | ||||||||||
| 6 | Demo Exist. Guest Rm. Wet Walls (Gyp.,Studs & CT) | 16,709 | SF | |||||||
| 7 | Demo Exist. Guest Rm. Interior Walls (Gyp. & Studs) - no wet walls | 36,010 | SF | |||||||
| 8 | Demo Exist. Guest Rm. Exterior Walls (Gyp. & Studs) Int. face only | 10,912 | SF | |||||||
| 9 | Demo Exist. Guest Rm. Toilet Doors & Frames | 62 | EA | |||||||
| 10 | ||||||||||
| 11 | Carpet w/ Pad - Guest Room | 2,354 | SY | |||||||
| 12 | Quarry Tile - Guest Room | 1,116 | SF | |||||||
| 13 | Ceramic Tile Floor - Guest Room | 2,604 | SF | |||||||
| 14 | Ceramic Tile Wall - Guest Room | 11284 | SF | |||||||
| 15 | Gyp. Bd. Chase - Guest Room | 1,984 | SF | |||||||
| 16 | Wall Paint - Textured Acrylic Coating | 48,800 | SF | |||||||
| 17 | Wall Paint Accent - Textured Acrylic Coating | 8,432 | SF | |||||||
| 18 | Ceiling Paint | 6,074 | SF | |||||||
| 19 | Ceiling Patching for Exist. Wall Demo | 1,984 | SF | |||||||
| 20 | ||||||||||
| 21 | New Gyp. Bd. & Mtl. Stud Wet Walls - Guest Rm. | 16,709 | SF | |||||||
| 22 | New Gyp. Bd. & Mtl. Stud Interior Walls - Guest Rm. (no wet walls) | 36,010 | SF | |||||||
| 23 | New Gyp Bd & Mtl Stud Ext Walls w/ Insul - Guest Rm - Int face only | 10,912 | SF | |||||||
| 24 | ||||||||||
| 25 | SCWD, Frame & Hardware (2'-0" x 6'-8") | 62 | EA | |||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 1 Sheet 2
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 5 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | General Construction | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||
| 1 | Guest Rooms | |||||||||
| 2 | Demo Exist. Vanity | 155 | LF | |||||||
| 3 | Demo Exist. Wet Bar & Upper Cabinet | 310 | LF | |||||||
| 4 | Demo Exist. Shower Assembly | 62 | EA | |||||||
| 5 | ||||||||||
| 6 | ||||||||||
| 7 | Vanity Base | 60 | EA | |||||||
| 8 | Vanity Counter | 60 | LF | |||||||
| 9 | Vanity Sink & Cut-Out | 60 | EA | |||||||
| 10 | Wet Bar Base Cabinet | 60 | EA | |||||||
| 11 | Wet Bar Upper Cabinet | 60 | EA | |||||||
| 12 | Wet Bar Counter - Solid Surface | 155 | LF | |||||||
| 13 | Mirror | 124 | EA | |||||||
| 14 | Toilet Paper Dispenser | 60 | EA | |||||||
| 15 | Towel Bar - 24" | 60 | EA | |||||||
| 16 | Towel Loop | 60 | EA | |||||||
| 17 | Robe Hook | 60 | EA | |||||||
| 18 | ||||||||||
| 19 | Clg. Access Door - 24" x 24" Stainless (bathroom) - Fire Rated | 22 | EA | |||||||
| 20 | Clg. Access Door - 24" x 24" Stainless (bathroom) - Non-Fire Rated | 41 | EA | |||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 1 Sheet 3
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 6 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | General Construction | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||
| 1 | Staff Toilet | |||||||||
| 2 | Demo Exist. Ceramic Tile Fl. | 88 | SF | |||||||
| 3 | Demo Exist. Ceramic Tile Wall | 495 | SF | |||||||
| 4 | Demo Exist. Toilet Partitions | 4 | EA | |||||||
| 5 | ||||||||||
| 6 | ||||||||||
| 7 | Conc. Floor Slab Patching | 88 | SF | |||||||
| 8 | Epoxy Floor Coating | 88 | SF | |||||||
| 9 | Ceramic Tile Wall | 495 | SF | |||||||
| 10 | Toilet Partitions | 4 | EA | |||||||
| 11 | Toilet Paper Dispenser | 2 | EA | |||||||
| 12 | Mirror | 2 | EA | |||||||
| 13 | Paper Towel Dispenser | 2 | EA | |||||||
| 14 | Soap Dispenser | 2 | EA | |||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 1 Sheet 4
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 7 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | General Construction | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||
| 1 | Sawcutting Exist Masonry | 48 | LF | |||||||
| 2 | Demo Exist Face Masonry | 72 | SF | |||||||
| 3 | Light Gauge Mtl. Framing @ New Opening | 4 | EA | |||||||
| 4 | ||||||||||
| 5 | Steel Lintels - 5' | 4 | EA | |||||||
| 6 | 3' x 4' Alum. Fixed Blade Louver | 48 | SF | |||||||
| 7 | ||||||||||
| 8 | Access Ladder - Aluminum w/ Cage | 32 | VLF | |||||||
| 9 | Access Door - 24" x 36" | 2 | EA | |||||||
| 10 | ||||||||||
| 11 | Guard Railing - mechanical platform | 20 | LF | |||||||
| 12 | Steel beam for platform | 20 | LF | |||||||
| 13 | Platform grating | 60 | SF | |||||||
| 14 | ||||||||||
| 15 | Steel framing for relocated AHU (2) | 80 | LF | |||||||
| 16 | ||||||||||
| 17 | Caulk Removal, Grout Infill | 9 | EA | |||||||
| 18 | ||||||||||
| 19 | T/O Shaft Enclosures | 22 | EA | |||||||
| 20 | ||||||||||
| 21 | Threaded rod hangers for relocated AHU | 60 | LF | |||||||
| 22 | ||||||||||
| 23 | Anchorage assemblies for platform/AHU framing | 12 | EA | |||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 1 Sheet 5
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 8 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | General Construction Subcontractors | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | General Construction | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||
| 1 | Demo, concrete sidewalk | 3,800 | SF | |||||||
| 2 | Demo, gravel bed | 3,800 | SF | |||||||
| 3 | Dumpster | 6 | EA | |||||||
| 4 | Debris haul/disposal | 2,400 | CF | |||||||
| 5 | New cleanouts | 7 | EA | |||||||
| 6 | Tie-ins/pipe fittings | 7 | EA | |||||||
| 7 | Excavate | 2,400 | CF | |||||||
| 8 | Backfill | 1,200 | CF | |||||||
| 9 | New slab subbase | 3,800 | SF | |||||||
| 10 | New concrete sidewalk | 7,600 | SF | |||||||
| 11 | Sodding | 4,200 | SF | |||||||
| 12 | Remove/store/transplant shrubs | 40 | EA | |||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 3 Summary
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | ||||||||
| Bolling AFB | Sheet | 9 of 19 | |||||||||
| Washington, D.C. | Dated | ||||||||||
| Estimate Valid to | |||||||||||
| Trade/Division | Mechanical Subcontractor | Prices by | Anastasi | ||||||||
| Checked by | Anastasi | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | ||||||||||
| Item | Description | % | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||||
| 1 | Mechanical Sheet 1 | ||||||||||
| 2 | Mechanical Sheet 2 | ||||||||||
| 3 | Mechanical Sheet 3 | ||||||||||
| 4 | Plumbing Sheet 1 | ||||||||||
| 5 | |||||||||||
| 6 | |||||||||||
| 7 | |||||||||||
| 8 | |||||||||||
| 9 | |||||||||||
| 10 | |||||||||||
| 11 | |||||||||||
| 12 | |||||||||||
| 13 | |||||||||||
| 14 | |||||||||||
| 15 | |||||||||||
| 16 | |||||||||||
| 17 | |||||||||||
| 18 | |||||||||||
| 19 | Subtotal | ||||||||||
| 20 | |||||||||||
| 21 | |||||||||||
| 22 | |||||||||||
| 23 | |||||||||||
| 24 | |||||||||||
| 25 | Subcontractor Overhead | 10% | |||||||||
| 26 | Subtotal | ||||||||||
| 27 | Subcontractor Profit | 10% | |||||||||
| Sheet Total |
Sub No 3 Sheet 1
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 10 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Mechanical Subcontractor | Prices by | Daihl | |||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Replace MAU-1, Northeast Attic | |||||||||
| 2 | Demolition | 48 | MH | |||||||
| 3 | AHU-1, 2,850 CFM, coils, CAV | 1 | EA | |||||||
| 4 | Exhaust Fan, Inline centrifugal, 2,050 CFM | 1 | EA | |||||||
| 5 | Ductwork, galvanized steel | 600 | lbs | |||||||
| 6 | Insulation: 1-1/2", 1-1/2 lb board | 400 | SF | |||||||
| 7 | Air devices | 126 | EA | |||||||
| 8 | Controls | 24 | Pts. | |||||||
| 9 | Testing and Balancing | 60 | MH | |||||||
| 10 | ||||||||||
| 11 | Replace MAU-2, Southwest Attic | |||||||||
| 12 | Demolition | 48 | MH | |||||||
| 13 | AHU-2, 2,200 CFM, coils, CAV | 1 | EA | |||||||
| 14 | Exhaust Fan, Inline centrifugal, 1,350 CFM | 1 | EA | |||||||
| 15 | Ductwork, galvanized steel | 600 | lbs | |||||||
| 16 | Insulation: 1-1/2", 1-1/2 lb board | 400 | SF | |||||||
| 17 | Air devices | 78 | EA | |||||||
| 18 | Controls | 24 | Pts. | |||||||
| 19 | Testing and Balancing | 40 | MH | |||||||
| 20 | ||||||||||
| 21 | Fan Coil Units, 4-Pipe, Pre-Piped w/ valves and accessories (C-125) | 134 | EA | |||||||
| 22 | Piping | 3/4" to 1" Dia, Type L | 2,787 | LF | ||||||
| 23 | Control Valves | 268 | EA | |||||||
| 24 | ||||||||||
| 25 | Ductwork Risers, galvanized steel | 7,280 | lbs | |||||||
| 26 | Insulation: 1-1/2", 1-1/2 lb board | 4,160 | SF | |||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 3 Sheet 2
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 11 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Mechanical Subcontractor | Subs | Prices by | Daihl | ||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Piping | 4" Black Steel, insulated FG, glass cloth | 65 | LF | ||||||
| 2 | Piping | 3" Black Steel, insulated FG, glass cloth | 260 | LF | ||||||
| 3 | Piping | 2-1/2" Black Steel, insulated FG, glass cloth | 360 | LF | ||||||
| 4 | Piping | 2" Black Steel, insulated FG, glass cloth | 195 | LF | ||||||
| 5 | Piping | 1" to 1-1/2" Dia, Type L, insulated FG | 325 | LF | ||||||
| 6 | Piping | 3/4" Dia, Type L, insulated FG | 1,850 | LF | ||||||
| 7 | 4" Valves and Accessories (Class 125) | 6 | EA | |||||||
| 8 | 3" Valves and Accessories (Class 125) | 10 | EA | |||||||
| 9 | 2-1/2" Valves and Accessories (Class 125) | 10 | EA | |||||||
| 10 | 1-1/4" to 1-1/2" Valves and Accessories (Class 125) | 20 | EA | |||||||
| 11 | 3/4" Valves and Accessories (Class 125) | 125 | EA | |||||||
| 12 | ||||||||||
| 13 | Piping | 1-1/4", Condensate drain | 680 | LF | ||||||
| 14 | ||||||||||
| 15 | Piping | 2-1/2" Dia, Sched 80, Insulated FG, Glass Cloth, HTHW | 60 | LF | ||||||
| 16 | Piping | 2" Dia, Sched 80, Insulated FG, Glass Cloth, HTHW | 30 | LF | ||||||
| 17 | Piping | 1-1/2" Dia, Sched 80, Insulated FG, Glass Cloth, HTHW | 25 | LF | ||||||
| 18 | 2-1/2" Valve, Gate (Class 300) | 2 | EA | |||||||
| 19 | 2" Valves and Accessories (Class 300) | 6 | EA | |||||||
| 20 | 1-1/2" Valves and Accessories (Class 300) | 6 | EA | |||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 3 Sheet 3
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 12 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Mechanical Subcontractor | Subs | Prices by | Daihl | ||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Unit Heater, 60-MBH, Horizontal, heating only | 4 | EA | |||||||
| 2 | Controls, UHs | 9 | Pts | |||||||
| 3 | ||||||||||
| 4 | Heat Exchanger, HTHW-to-HWR, Class 600, Dbl.-Wall | 1 | EA | |||||||
| 5 | Expansion Tank | 1 | EA | |||||||
| 6 | Air Separator, 2" | 1 | EA | |||||||
| 7 | Testing and Balancing | 30 | MH | |||||||
| 8 | Controls | 10 | Pts | |||||||
| 9 | Pump, End suction, centrifugal, 7.5 hp | 1 | EA | |||||||
| 10 | Pump, End suction, centrifugal, 5 hp | 2 | EA | |||||||
| 11 | Equipment Insulation | 1 | Job | |||||||
| 12 | ||||||||||
| 13 | Reinsulate Piping Mains In Attic, 3", FG Insulated | 300 | LF | |||||||
| 14 | Reinsulate Piping Mains In Attic, 2-1/2", FG Insulated | 550 | LF | |||||||
| 15 | Reinsulate Piping Mains In Attic, 2", FG Insulated | 1,000 | LF | |||||||
| 16 | Reinsulate Piping Mains In Attic, 1-1/2", FG Insulated | 150 | LF | |||||||
| 17 | Reinsulate Piping Mains In Attic, 1-1/4", FG Insulated | 200 | LF | |||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 3 Sheet 4
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 13 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Mechanical Subcontractor | Prices by | Daihl | |||||||
| Plumbing | Checked by | |||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Demolition, Mechanical room, Plumbing equipment | 40 | MH | |||||||
| 2 | Demolition, Water closet assemblies | 155 | EA | |||||||
| 3 | ||||||||||
| 4 | Water Closet, Floor Mounted, two piece, power assist, incl. pipe,etc | 61 | EA | |||||||
| 5 | Lavatory w/ Trim, Vanity Top, includes pipe and valves | 122 | EA | |||||||
| 6 | Fiberglass, one piece, Three Walls, 36" Square, inc. pipe and valves | 61 | EA | |||||||
| 7 | ||||||||||
| 8 | ||||||||||
| 9 | Domestic Water Heater, Gas-Fired, condensing type, PVC Intake/Exh | 1 | EA | |||||||
| 10 | Storage Tank, 80 gallon | 1 | EA | |||||||
| 11 | Expansion Tank, 5 gallon | 1 | EA | |||||||
| 12 | Domestic Water Hot Water Generator, 50 GPM Recovery | 1 | EA | |||||||
| 13 | Circulating Pump, bronze, fractional horsepower | 2 | EA | |||||||
| 14 | ||||||||||
| 15 | Piping | 3" Galvanized Steel, insulated FG, glass cloth | 50 | LF | ||||||
| 16 | Piping | 2" Galvanized, insulated FG, glass cloth | 125 | LF | ||||||
| 17 | Piping | 1" to 1-1/2" Dia, Type L, glass cloth, insulated FG | 98 | LF | ||||||
| 18 | Piping | 3/4" Dia, Type L, glass cloth, insulated FG | 130 | LF | ||||||
| 19 | 3" Valves and Accessories (Class 125) | 2 | EA | |||||||
| 20 | 2" Valves and Accessories (Class 125) | 12 | EA | |||||||
| 21 | 1-1/4" to 1-1/2" Valves and Accessories (Class 125) | 10 | EA | |||||||
| 22 | 3/4" Valves and Accessories (Class 125) | 10 | EA | |||||||
| 23 | ||||||||||
| 24 | Fire Protection Modifications - Mechanical Room | |||||||||
| 25 | Demolition | 750 | SF | |||||||
| 26 | Sprinkler Piping Modifications | 1,200 | SF | |||||||
| 27 | Drain and Refill | 40 | MH | |||||||
| Sheet Total |
Sub No 4 Summary
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | ||||||||
| Bolling AFB | Sheet | 14 of 19 | |||||||||
| Washington, D.C. | Dated | ||||||||||
| Estimate Valid to | |||||||||||
| Trade/Division | Electrical Subcontractor | Prices by | |||||||||
| Checked by | |||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | ||||||||||
| Item | Description | % | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||||
| 1 | Electrical Sheet 1 | ||||||||||
| 2 | Electrical Sheet 2 | ||||||||||
| 3 | |||||||||||
| 4 | |||||||||||
| 5 | |||||||||||
| 6 | |||||||||||
| 7 | |||||||||||
| 8 | |||||||||||
| 9 | |||||||||||
| 10 | |||||||||||
| 11 | |||||||||||
| 12 | |||||||||||
| 13 | |||||||||||
| 14 | |||||||||||
| 15 | |||||||||||
| 16 | |||||||||||
| 17 | |||||||||||
| 18 | |||||||||||
| 19 | Subtotal | ||||||||||
| 20 | |||||||||||
| 21 | |||||||||||
| 22 | |||||||||||
| 23 | |||||||||||
| 24 | |||||||||||
| 25 | Subcontractor Overhead | 10% | |||||||||
| 26 | Subtotal | ||||||||||
| 27 | Subcontractor Profit | 10% | |||||||||
| Sheet Total |
Sub No 4 Sheet 1
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 15 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Electrical Subcontractor | Prices by | Bolt | |||||||
| Checked by | Bolt | |||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Demolition | 160 | HR | |||||||
| 2 | Tag, Protect and Retain Wiring/Cabling | 160 | HR | |||||||
| 3 | Ceiling Mounted Lighting Fixtures (bathroom downlights) | 64 | EA | |||||||
| 4 | Wall Mounted Lighting Fixtures (bathroom sinks) | 62 | EA | |||||||
| 5 | Ceiling Mounted Lighting Fixtures (wet bar downlight) | 60 | EA | |||||||
| 6 | Industrial Deep-V Lighting Fixtures | 5 | EA | |||||||
| 7 | First Floor Bathroom Strip Lighting Fixtures | 2 | EA | |||||||
| 8 | Outdoor Stair Lighting Fixtures | 15 | EA | |||||||
| 9 | Outdoor Exit Lights | 9 | EA | |||||||
| 10 | Outdoor Walkway Lights | 96 | EA | |||||||
| 11 | 2x2 Recessed Parabolics | 46 | EA | |||||||
| 12 | Jelly Jar Lighting Fixtures | 14 | EA | |||||||
| 13 | Light Switches | 330 | EA | |||||||
| 14 | Battery Inverter System | 1 | EA | |||||||
| 15 | Receptacles, 20A, Duplex, Recess Mounted | 496 | EA | |||||||
| 16 | Receptacles, GFI, 20A Duplex, Recess Mounted | 248 | EA | |||||||
| 17 | Time Clock | 2 | EA | |||||||
| 18 | Emergency Relays | 3 | EA | |||||||
| 19 | Motor Connection, Single Phase | 150 | EA | |||||||
| 20 | Motor Connection, Three Phase | 7 | EA | |||||||
| 21 | Combination Motor Starter & 60A Safety Switch | 1 | EA | |||||||
| 22 | Combination Motor Starter & 30A Safety Switch | 3 | EA | |||||||
| 23 | Wire Trough | 2 | EA | |||||||
| 24 | 3-Pole Motor Rated Switch | 2 | EA | |||||||
| 25 | Thermal Motor Switch | 8 | EA | |||||||
| 26 | 150A c/b for Switchboard | 1 | EA | |||||||
| 27 | Lighting Contactor, 6 Pole Electrically Operated, Electrically Held | 1 | EA | |||||||
| 28 | Lighting Contactor, 10 Pole Electrically Operated, Electrically Held | 1 | EA | |||||||
| 29 | Telecom Cover Plate with Ports/Jacks | 124 | EA | |||||||
| Sheet Total |
Sub No 4 Sheet 2
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 16 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Electrical Subcontractor | Prices by | Bolt | |||||||
| Checked by | Bolt | |||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | #12 THHN conductors | 5,000 | LF | |||||||
| 2 | #10 THHN conductors | 350 | LF | |||||||
| 3 | #8 THHN conductors | 800 | LF | |||||||
| 4 | #3 THHN conductors | 175 | LF | |||||||
| 5 | 3/4" EMT | 2,000 | LF | |||||||
| 6 | 3/4" Rigid | 500 | LF | |||||||
| 7 | 1-1/2" EMT | 50 | LF | |||||||
| 8 | ||||||||||
| 9 | 225A, 208V Panelboard | 1 | EA | |||||||
| 10 | ||||||||||
| 11 | 3 #12 Metal Clad (MC) Cable | 5,000 | LF | |||||||
| 12 | ||||||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Sub No 5 Summary
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | ||||||||
| Bolling AFB | Sheet | 17 of 19 | |||||||||
| Washington, D.C. | Dated | ||||||||||
| Estimate Valid to | |||||||||||
| Trade/Division | Fire Alarm Subcontractor | Prices by | |||||||||
| Checked by | |||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | ||||||||||
| Item | Description | % | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | ||||||
| 1 | Fire Alarm Sheet 1 | ||||||||||
| 2 | |||||||||||
| 3 | |||||||||||
| 4 | |||||||||||
| 5 | |||||||||||
| 6 | |||||||||||
| 7 | |||||||||||
| 8 | |||||||||||
| 9 | |||||||||||
| 10 | |||||||||||
| 11 | |||||||||||
| 12 | |||||||||||
| 13 | |||||||||||
| 14 | |||||||||||
| 15 | |||||||||||
| 16 | |||||||||||
| 17 | |||||||||||
| 18 | |||||||||||
| 19 | Subtotal | ||||||||||
| 20 | |||||||||||
| 21 | |||||||||||
| 22 | |||||||||||
| 23 | |||||||||||
| 24 | |||||||||||
| 25 | Subcontractor Overhead | 10% | |||||||||
| 26 | Subtotal | ||||||||||
| 27 | Subcontractor Profit | 10% | |||||||||
| Sheet Total |
Sub No 5 Sheet 1
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 18 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Fire Alarm Subcontractor | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Demolition | 8 | HR | |||||||
| 2 | ||||||||||
| 3 | Duct Mounted Smoke Detector | 4 | EA | |||||||
| 4 | Addressable Relay | 6 | EA | |||||||
| 5 | ||||||||||
| 6 | Programming and testing | 12 | HR | |||||||
| 7 | ||||||||||
| 8 | FPLP Metal Clad Cable | 2,500 | LF | |||||||
| 9 | 3/4" EMT | 500 | LF | |||||||
| 10 | #16 TSSHPR | 1,100 | LF | |||||||
| 11 | ||||||||||
| 12 | ||||||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| 19 | ||||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | ||||||||||
| 26 | ||||||||||
| 27 | ||||||||||
| Sheet Total |
Option Bid
| Project | Repair HVAC and Infrastructure Mathies Manor, B3621 | Project No. | BXUR 08-0002 | |||||||
| Bolling AFB | 19 of 19 | |||||||||
| Washington, D.C. | Dated | |||||||||
| Estimate Valid to | ||||||||||
| Trade/Division | Design/Built - Office spaces SW Wing first floor | Prices by | ||||||||
| Checked by | ||||||||||
| D:\Projects\….\032-33_FinalEst.xls | Final Estimate IGE | |||||||||
| Item | Description | Quantity | Unit | Material | Labor | Total | ||||
| No. | Unit Cost | Cost | Unit Cost | Cost | Cost | |||||
| 1 | Demolition - Walls & openings | 200 | SF | |||||||
| 2 | ||||||||||
| 3 | New door, door frame, and hardware complete | 8 | EA | |||||||
| 4 | New Gyp. Bd. & Mtl. Stud Wet Walls - bath room | 576 | SF | |||||||
| 5 | New Gyp. Bd. & Mtl. Stud Interior Walls - office Rm. (no wet walls) | 656 | SF | |||||||
| 6 | ||||||||||
| 7 | Wall Paint - Textured Acrylic Coating | 780 | SF | |||||||
| 8 | Wall Paint Accent - Textured Acrylic Coating | 1,500 | SF | |||||||
| 9 | ||||||||||
| 10 | Tiles, bath room fixtures, floor finishes, drop ceiling (under base bid) | |||||||||
| 11 | Sprinkler Piping Modifications Lounge Area | 1,200 | SF | |||||||
| 12 | ||||||||||
| 13 | Lighting rearrange in Lounge area | 8 | HR | |||||||
| 14 | ||||||||||
| 15 | 2x2 Recessed Parabolics | 16 | EA | |||||||
| 16 | ||||||||||
| 17 | Design/Built fee | 1 | Job | |||||||
| 18 | ||||||||||
| 19 | Subtotal | |||||||||
| 20 | ||||||||||
| 21 | ||||||||||
| 22 | ||||||||||
| 23 | ||||||||||
| 24 | ||||||||||
| 25 | Subcontractor Overhead | |||||||||
| 26 | Subtotal | |||||||||
| 27 | Subcontractor Profit | |||||||||
| Sheet Total |
File details come from the government source that posted it. Updated .