SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 14-May-2015 01:00 PM to 20-May-2015 10:00 AM.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Attachment 1 |
| Technical Specifications |
| 82 |
| 01-MAR-2015 |
| Attachment 2 |
| Drawings Bldg 821 |
| 9 |
| 04-MAR-2015 |
| Attachment 3 |
| Drawings Bldg 617 |
| 13 |
| 01-FEB-2015 |
| Attachment 4 |
| Wage Determination MN36 |
| 8 |
| 27-MAR-2015 |
| Attachment 5 |
| Financial Reference Sheet |
| 1 |
| 02-APR-2015 |
| Attachment 6 |
| Bid Bond Form SF24 |
| 2 |
| 01-OCT-1998 |
to:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Attachment 1 |
| Technical Specifications |
| 82 |
| 01-MAR-2015 |
| Attachment 2 |
| Drawings Bldg 821 |
| 9 |
| 04-MAR-2015 |
| Attachment 3 |
| REV. DRAWINGS, ROOF BLDG 617 |
| 13 |
| 05-MAY-2015 |
| Attachment 4 |
| Wage Determination MN36 |
| 8 |
| 27-MAR-2015 |
| Attachment 5 |
| Financial Reference Sheet |
| 1 |
| 02-APR-2015 |
| Attachment 6 |
| Bid Bond Form SF24 |
| 2 |
| 01-OCT-1998 |
| Attachment 7 |
| ADDENDUM #01 |
| 2 |
| 05-MAY-2015 |
(End of Summary of Changes)