Questions_and_Answers_-_Pre-Bid.docx

DOCX document 14 KB Posted

Attached to
Construct Concrete Slab and Erect LAMS Shelter Federal contract opportunity
Solicitation number
FA5575-15-B-0001
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Questions and Answers Part 1

View the file

Other files for this federal contract opportunity

Other files attached to Construct Concrete Slab and Erect LAMS Shelter, newest first.
File Type Posted
Questions_and_Answers_-_Pre-Bid_(REVISED).docx DOCX document
Attachment_6_-_Past_Performance_Reference_List.doc DOC document
Amendment_001.doc DOC document
Amendment_1_Drawing_-_Slab_Dimension.pdf PDF
Amendment_1_Drawing_-_Anchor_Footing_Options.pdf PDF
Attachment_5_-_Cost_Breakdown.xlsx XLSX spreadsheet
Attachment_2_-_Spanish_Specifications.pdf PDF
Attachment_4_-_Submittal_Schedule.xlsx XLSX spreadsheet
Attachment_3_-_Project_Drawings.pdf PDF
FA5575-15-B-0001 _Solicitation.pdf PDF
Attachment_1_-_English_Specifications.pdf PDF
FA5575-15-B-0001 _Synopsis.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5575-15-B-0001, QUESTIONS AND ANSWERS

1. -In the Cost_Breakdown's Line#11 calls to construct high concrete wall ring. This high concrete all ring is missing in the drawing SB-101. We understand that details for this concrete wall ring have to be provided. FROM SEMI – 18 MARCH 2015

CE RESPONSE (18 MARCH 2015): The answer to the contractor question is detailed in the second one with the reference "5 Concrete Anchor at Ring Wall".

The ring wall, is to be constructed inside the edge to edge dimensions referred in the first attachments.

*DRAWINGS TO BE INCLUDED IN AMENDMENT 0001.