AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

See Schedule.

POC: Satoshi Nogaw a, Mr.

Commercial Telephone#: 0176-57-2715

DSN# 226-3496

E-mail: satoshi.nogaw a.jp@misaw a.af.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Aug-2010

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA5205-10-R-0008

X 9B. DATED (SEE ITEM 11)

04-Aug-2010

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Aug-2010

CODE

35 CONS/LGC (JAPAN)

DODAAC: FA5205

BLDG. 656, MISAWA AIR BASE

MISAWA-SHI, AOMORI-KEN 033-0012

FA5205 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA5205-10-R-0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

This amendment is issued to amend subject RFP with regard to Attachment 1, 3 and 4, and Section J, to confirm the

Government’s clarifications for the Questions No. 1, 2, 7 and 10 made under the 35 CONS response letter of 24 Aug

10.

(a) Attachment 1, MACC General Provisions. By incorporating attached Addendum No. 1 dated 25 Aug 10 into

Attachment 1, MACC General Provisions, the General Provisions page 1 and 2, and Division 01 01 00 page 20 are replaced with revised ones, and Appendix 1, Project Flowchart is added.

(b) Attachment 3, MACC Seed Project Statement of Work (SOW). By incorporating attached Addendum No. 2 dated 25 Aug 10 into Attachment 3, MACC Seed Project SOW, the SOW page 1 and 3 are replaced with revised ones.

(c) Attachment 4, Price Proposal for MACC Seed Project. By replacing Attachment 4, Price Proposal for MACC

Seed Project with the revised one, "Design Other Cost" is added beneath "Design Fee".

(d) Section J. By replacing page 32 of the RFP with the revised one attached to this amendment, the Exhibit/

Attachment Table of Contents specified in Section J is updated to reflect incorporations of Addendum No. 1 into

Attachment 1 and Addendum No. 2 into Attachment 3, and replacement of Attachment 4, as shown in "From" and

"To" below:

From:

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 MACC General

Provisions

38 24-MAY-2010

Attachment 3 MACC Seed Project

Statement of Work &

Addendum No. 1

45 19-AUG-2010

Attachment 4 Price Proposal for MACC

Seed Project

1 24-MAY-2010

To:

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 MACC General

Provisions & Addendum

No. 1

39 25-AUG-2010

Attachment 3 MACC Seed Project

Statement of Work &

Addenda No. 1 thru 2

46 25-AUG-2010

Attachment 4 Price Proposal for MACC

Seed Project

1 25-AUG-2010

(e) No other change is made under this amendment.

4 Attachments:

1. Revised page 32 of the RFP numbered with FA5205-10-R-0008-0002, 1 page.

2. Addendum No. 1 dtd 25 Aug 10, 1 page, w/ Revised General Provisions, 5 pages.

3. Addendum No. 2 dtd 25 Aug 10, 1 page, w/ Revised SOW, 3 pages.

4. Attachment 4, Price Proposal for MACC Seed Project Revised 25 Aug 10, 1 page.

File details come from the government source that posted it. Updated .