Atch 2 to Amendment No. 0002.pdf

PDF 212 KB Posted

Attached to
Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC), Misawa Air Base, Japan
Solicitation number
FA5205-10-R-0008
Issued by

About this file

Attachment 2 to Amendment No. 0002 - Addendum No. 1 to IDIQ MACC dated 25 Aug 10 1 page with revised pages of General Provisions 5 pages.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM No.1

TO

MACC GENERAL PROVISIONS

RFP No. FA5205-10-R-0008

IDIQ MACC

25 Aug 2010

The General Provisions is amended to provide the following changes:

1. Project Table of Contents. Page numbers of Division 01 01 00 are changed from “PAGE 1 – PAGE

19” to “PAGE 1 – PAGE 20”.

2. Division 01 01 00, Statement of Work. Add the following paragraphs in the end of this division at page 20.

“6.12. Disposal

Except as specified elsewhere in this General Provisions or the Statement of Work for individual project, all residue and scrap generated by the contractor during the performance shall be disposed of outside the confines of Misawa Air Base IAW all applicable Japanese Laws at no additional cost to the government.

6.13. Hazardous Waste

All hazardous waste will be managed, segregated, stored, transported, and disposed of in accordance with the Misawa AB Hazardous Waste Management Plan. All hazardous wastes must be disposed of through the Defense Reutilization and Marketing Office (DRMO), Misawa AB branch.”

3. Appendix 1, Project Flowchart. Add Project Flowchart.

4. The General Provisions dated 24 May 10, cover page and table of contents (page 1 and 2) are replaced with the General Provisions dated 25 Aug 10, and page 20 of Division 01 01 00 is added.

Attachment:

The MACC General Provision Revised 25 Aug 10, Page 1, 2, Division 01 01 00 Page 20 & Appendix 1, 4 pages.

RFP NO. FA5205-10-R-0008

Contract NO.

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

GENERAL PROVISIONS

FOR

DEPARTMENT OF U.S. AIR FORCE

IN MISAWA, JAPAN

Date: Aug 25, 2010

DEPARTMENT OF THE AIR FORCE

MISAWA AIR BASE, JAPAN

35TH CIVIL ENGINEER SQUADRON

APO AP 96319-5022

Attachment 1

PROJECT TABLE OF CONTENTS

DIVISION/SECTION TITLE PAGE NO.

DIVISION 01 GENERAL REQUIREMENTS

01 01 00 Statement of Work PAGE 1 – PAGE 20

01 11 00 Design After Award PAGE 1 – PAGE 13

01 78 00 Closeout Submittals PAGE 1 – PAGE 2

Appendix 1: Project Flowchart

ABBREVIATIONS:

AAS – Atomic Absorption Spectrum

CES – Civil Engineering Squadron.

CID – Comprehensive Interior Design

CO – Contracting officer.

COR – Contracting Officer’s Representative.

CQC – Contractor Quality Control

DB – Design Build

DBB – Design Bid Build.

GFE – Government Furnished Equipment

GFM – Government Furnished Material

HM – Hazardous Material

HMBP – Heavy Metal-Based Paint

IDG – Installation Design Guide

JEGS – Japan Environmental Governing Standards

JIS – Japanese Industrial Standards MACC – Multiple Award Construction Contract

QAPP – Quality Assurance Program Plan

RFP – Request for Proposal

TO – Task Order

Revised 25 Aug 10 per Addendum No. 1

SECTION 01 01 00 PAGE 20

6.12. Disposal

Except as specified elsewhere in this General Provisions or the Statement of Work for individual project, all residue and scrap generated by the contractor during the performance shall be disposed of outside the confines of Misawa Air Base IAW all applicable Japanese Laws at no additional cost to the government.

6.13. Hazardous Waste

All hazardous waste will be managed, segregated, stored, transported, and disposed of in accordance with the Misawa AB Hazardous Waste Management Plan. All hazardous wastes must be disposed of through the Defense Reutilization and Marketing Office (DRMO), Misawa AB branch.

END OF SECTION

Added 25 Aug 10 per Addendum No. 1

Only Construction

OPR Ktr 100% Design Ktr 0% Design

Routine Urgent Routing Urgent

CES Project Identification Project Identification

CONS TO RFP w/ SOW TO RFP w/ 100% Design pkg

3 2 3 2 CONS Joint Site Visit / Meeting Joint Site Visit / Meeting

28 14 35 21 KTR Proposals w/ Concept Proposal

10 7 14 7 GOVT Gov't Evaluation Gov't Evaluation

7 5 7 5 GOVT Discussion (if required) Discussion (if required)

4 2 4 2 CONS Source Selection Source Selection

14 14 14 14 CONS CRC/SJA/HQ PACAF Review CRC/SJA/HQ PACAF Review

66 44 77 51 CONS 100% DB TO Award "Only Const" TO Award

7 5 7 5 KTR Pre-performance Conference ▼

30 21 35 21 KTR 35% Submittal ▼ ▼ ▼

21 14 21 21 GOVT Gov't Review/Approval ▼ ▼ ▼

30 14 35 21 KTR 65% Submittal ▼ ▼ ▼

21 7 25 14 GOVT Gov't Review/Approval ▼ ▼ ▼

30 14 35 14 KTR 95% Submittal ▼ ▼

14 7 14 10 GOVT Gov't Review/Approval ▼ ▼

14 7 14 10 KTR 100% / Final Submittal ▼

14 7 14 10 GOVT Gov't Review/Approval ▼

181 96 200 126 GOVT Acceptance of Final Design ▼

30 30 30 30 KTR Performance Bond Performance Bond

7 7 7 7 GOVT Pre-Construction Conference/NTP Pre-Construction Conference/NTP

KTR Construction Work Construction Work

5 5 5 5 GOVT Final Acceptance Final Acceptance

30 30 30 30 GOVT Final Payment Final Payment

30 30 30 30 GOVT/KTR Past Performance Evaluation Past Performance Evaluation

Closeout Closeout

Multiple Award Construction Contract (MACC)

PROJECT FLOWCHART

Non-complex Complex

Design-BuildTypical Numbers of Days (CD)

Ktr Partial Design

Discussion (if required)

Partial DB TO Award

CRC/SJA/HQ PACAF Review

Source Selection

Post Award

Project Identification

TO RFP w/ Partial Design pkg

Joint Site Visit / Meeting

Proposal

Gov't Evaluation

PR Acceptance by CONS

Acceptance of Final Design

Gov't Review/Approval

100% / Final Submittal

65% Submittal

Past Performance Evaluation

Final Payment

Final Acceptance

Construction Work

Performance Bond

Pre-Construction Conference/NTP

Pre-performance Conference

Closeout

95% Submittal

Gov't Review

Gov't Review

Appendix 1 to MACC General Provisions Added 25 Aug 10 per Addendum No. 1