JA-9_Hangar_Door_Operation_Guideline.pdf

PDF 1 MB Posted

Attached to
Hangar Door Repair Federal contract opportunity
Solicitation number
FA5004-15-R-C003
Issued by
Department of the Air Force Pacific Air Forces

About this file

JA-9 Hangar Door Operation Guideline

View the file

Other files for this federal contract opportunity

Other files attached to Hangar Door Repair, newest first.
File Type Posted
Photos.pdf PDF
Hangar_Door_Site_Visit_Sign_in.pdf PDF
Q__A_Hangar_Door_Project__1.pdf PDF
B1335_LBP_Survey.pdf PDF
FA5004-15-R-C003-0003.pdf PDF
Second_Site_Visit_Information.pdf PDF
FA5004-15-R-C003-0002.pdf PDF
JA-13_Past_Performance_Questionnaire.pdf PDF
FA5004-15-R-C003-0001.pdf PDF
JA-2_Structural_Narrative.pdf PDF
JA-3_Electrical_Narrative.pdf PDF
JA-5_021203_22x34_Drawings_03-28-2014.pdf PDF
JA-13_Past_Performance_Questionnaire.pdf PDF
JA-10_AF_Form_3000.pdf PDF
JA-4_021203_Specifications_03_11_2015_Updated.pdf PDF
JA-15_Financial_Reference_Sheet.pdf PDF
JA-12_AF_Form_3065.pdf PDF
FA5004-15-R-C003_Hangar_Door.pdf PDF
JA-6_Hangar_Door_Wage_Determinations.pdf PDF
JA-1_Architectural_Narrative_3.10.15.pdf PDF
JA-11_AF_Form_3064.pdf PDF
JA-14_Past_Performance_Worksheet.pdf PDF
JA-7_Environmental_Protection_Borrow_Pit_Plan.pdf PDF
JA-8_AF66_2.10.15.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-16 HANGAR DOOR OPERATION GUIDELINE FOR CONTRACTORS

(To Prevent Freezing Water Lines in the Hangar Bays)

Unless provisions are made to create a heated enclosure for hangar bays while hangar doors are open when ambie temperature is below 25º F the following guidelines shall be followed:

Outside Air Temperature Operational Guideline

25º F and Above No operational constraints.

10º F to 24º F Doors shall be open no longer than 15 minutes and doors shall be closed for 30 min. before reopening.

0º F to 9º F Doors shall be open no longer than 15 minutes and doors shall be closed for 40 min. before reopening.

-10º F to -1º F Doors shall be open no longer than 15 minutes and doors shall be closed for 1 hour before reopening.

Above -15º F to -11º F Doors shall be open no longer than 15 minutes and doors shall be closed for 1 1/2 hours before reopening.

-15º F Doors shall be open no longer than 15 minutes and doors shall be closed for 2 hours before reopening.

Below -15º F Doors shall be open no longer than 15 minutes and doors shall be closed for 2 hours minimum before reopening.

Temperature of smallest unprotected domestic water line in area of greatest risk shall be monitored to ensure the hangar door is being closed long enough to prevent water in pipe from becoming fully frozen* during the periods the hangar door is open.

*Note: An accurate temperature probe strapped to the exterior of the pipe and covered with a small piece of insulation will provide a good indication of the temperature of the water within the pipe. An indication that the water in a small pipe has become fully frozen is when that temperature drops below 32º F.

FA5004-15-R-C003

EIELSON AFB, ALASKA

ATTACHMENT JA-9

HANGAR DOOR OPERATION GUIDE

ent

FA5004-15-R-C003

EIELSON AFB, ALASKA

ATTACHMENT JA-9

HANGAR DOOR OPERATION GUIDE