JA-8_AF66_2.10.15.pdf
PDF 560 KB Posted
- Attached to
- Hangar Door Repair Federal contract opportunity
- Solicitation number
- FA5004-15-R-C003
About this file
JA-8 AF66 2.10.15
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Photos.pdf | ||
| Hangar_Door_Site_Visit_Sign_in.pdf | ||
| Q__A_Hangar_Door_Project__1.pdf | ||
| B1335_LBP_Survey.pdf | ||
| FA5004-15-R-C003-0003.pdf | ||
| Second_Site_Visit_Information.pdf | ||
| FA5004-15-R-C003-0002.pdf | ||
| JA-13_Past_Performance_Questionnaire.pdf | ||
| FA5004-15-R-C003-0001.pdf | ||
| JA-2_Structural_Narrative.pdf | ||
| JA-3_Electrical_Narrative.pdf | ||
| JA-5_021203_22x34_Drawings_03-28-2014.pdf | ||
| JA-13_Past_Performance_Questionnaire.pdf | ||
| JA-10_AF_Form_3000.pdf | ||
| JA-4_021203_Specifications_03_11_2015_Updated.pdf | ||
| JA-15_Financial_Reference_Sheet.pdf | ||
| JA-12_AF_Form_3065.pdf | ||
| FA5004-15-R-C003_Hangar_Door.pdf | ||
| JA-6_Hangar_Door_Wage_Determinations.pdf | ||
| JA-1_Architectural_Narrative_3.10.15.pdf | ||
| JA-11_AF_Form_3064.pdf | ||
| JA-14_Past_Performance_Worksheet.pdf | ||
| JA-9_Hangar_Door_Operation_Guideline.pdf | ||
| JA-7_Environmental_Protection_Borrow_Pit_Plan.pdf |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEMS OR DESCRIPTION
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED
N/A N/A N/A N/A N/A N/A N/A N/A
01 14 00 SAFETY, REGULATIONS AND CODES
Construction Operation and Safety Plan
01 14 00 2.A.1 4 30 days prior to construction start
2 Accident Prevention Plan, 01 14 00 3 30 days prior to construction start
Safety and Health Program
01 14 00 2.A.2 4 30 days prior to construction start
Request for Use of Ionizing Radiation (if required)
01 14 00 2.A.3 4 30 days prior to use
Request for Use of Lasers (if required)
01 14 00 2.A.4 4 30 days prior to use
Request for Use of Radioactive Materials (if required)
01 14 00 2.A.5 4 30 days prior to use
Request for Use of Radio Frequency Radiation (if required)
01 14 00 2.A.6 4 30 days prior to use
Request for Use of Ultraviolet Radiation (if required)
01 14 00 2.A.7 4 30 days prior to use
Phase I Environmental Assessment Certificate for Imported
Borrow Materials
01 14 00 2.A.13 4 30 days prior to work
FAA Form 7460-1 Notice of Proposed Construction or
Alteration 4 45 days prior to work
11 AF Form 103 3 30 days prior to construction start
12 Waste/Borrow Pit Coordination 3 30 days prior to construction start
Environmental Protection Plan
01 14 00 1.19, 2.A.8 3 30 days prior to construction start
14 Hazardous Materials Inventory 01 14 00 2.A.9, 1.20 3 30 days prior to construction start, updated version at final inspection
15 MSDS (for all iems) 01 14 00 2.A.9, 1.20 3 14 days prior to use
16 Hazardous Waste Accumulation Log 01 14 00 2.A.10, 1.21 3 At final inspection
01 33 00 Submittals
Submittal Register
01 33 00 1.3 3 15 days after NTP
01 40 00 Quality Control
Testing Laboratory Information
01 40 00 1.3.A,B,C, D, E 4 15 days after NTP
01 70 00 Contract Close Out
O&M Architectural Materials and Finishes
01 70 00 1.4.A.1 4 30 days prior to final inspection
F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A T
E
L in e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
FA5004-15-R-C003
EIELSON AFB, ALASKA
ATTACHMENT JA-8
AF66 2.10.15
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
O&M Mechanical Equipment
01 70 00 1.4.A.2 4 30 days prior to final inspection
O&M Electrical Equipment
01 70 00 1.4.A.3 4 30 days prior to final inspection
Spare Parts and Maintenance Materials
01 70 00 1.6 4 15 days prior to project close-out
01 73 29 Cutting and Patching
Written Request - Cutting or Alteration
01 73 29 1.2.A 4 14 days prior to cutting/alteration
FA5004-15-R-C003
EIELSON AFB, ALASKA
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
02 41 19 Alteration Project Procedure
Permits and Notification
02 41 19 1.2.A 4
Dump Receipts, Bills of Lading, Handling and Tracking
Records
02 41 19 1.2.B
15 days prior to final inspection
03 30 00 Cast-In-Place Concrete
Steel Reinforcing Bars
03 30 00, 1.3.A, 2.1.B 4 21 days prior to work
Design Mixtures for Each Concrete Mixture
03 30 00 1.3.B 4 21 days prior to work
Steel Reinforcement Shop Drawings
03 30 00 1.3.C 4 21 days prior to work
05 12 00 Structural Steel
Structural-Steel Materials
05 12 00 1.3.A, 2.1 4 21 days prior to ordering
Bolts, Connectors, and Anchors
05 12 00 1.3.A, 2.2 4 21 days prior to work
Primer
05 12 00 1.3.A, 2.3 4 21 days prior to work
Grout
05 12 00 1.3.A, 2.4 4 21 days prior to work
High-Strength Bolts
05 12 00 1.3.A, 2.6.A 4 21 days prior to work
Weld Connections
05 12 00 1.3.A, 2.6.B 4 21 days prior to work
Shop Priming
05 12 00 1.3.A, 2.7 4 21 days prior to work
Hot-Dip Galvanized Finish
05 12 00 1.3.A, 2.8 4 21 days prior to work
Shop Drawings
05 12 00 1.3.B 4 21 days prior to work
Qualification Data for Installer
05 12 00 1.4.A 4 21 days prior to work
Qualification Data for Fabricator
05 12 00 1.4.A 4 21 days prior to work
Qualification Data for Testing Agency
05 12 00 1.4.A 4 21 days prior to work
Welding Certificates
05 12 00 1.4.B 4 21 days prior to work
Mill Test Reports for Structural Steel
05 12 00 1.4.C 4 21 days prior to work
Product Test Reports for Bolts, Nuts, and Washers
05 12 00 1.4.D.1 4 21 days prior to work
Product Test Reports for Direct-Tension Indicators
05 12 00 1.4.D.2 4 21 days prior to work
Product Test Reports for Tension-Control, High-Strength Bolt-
Nut-Washer Assemblies
05 12 00 1.4.D.3 4 21 days prior to work
Product Test Reports for Shop Primers
05 12 00 1.4.D.4 4 21 days prior to work
Product Test Reports for Nonshrink Grout
05 12 00 1.4.D.5 4 21 days prior to work
FA5004-15-R-C003
EIELSON AFB, ALASKA
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
05 50 00 Metal Fabrications
Product Data for Paint Products
05 50 00 1.2.A.1 4 21 days prior to work
Shop Drawings
05 50 00 1.2.B 4 21 days prior to work
Qualification Data for Qualified Professional Engineer
05 50 00 1.3.A 4 21 days prior to work
Mill Certificates
05 50 00 1.3.B 4 21 days prior to work
Welding Certificates
05 50 00 1.3.C 4 21 days prior to work
Paint Compatibility Certificates
05 50 00 1.3.D 4 21 days prior to work
07 42 14 Insulated Metal Wall Panels
Product Data for Assembled Panel Structural Capabilities
07 42 14 1.3.A 4 21 days prior to ordering
Shop Drawings
07 42 14 1.3.B 4 21 days prior to work
Design and Performance Data
07 42 14 1.3.C 4 21 days prior to work
Metal Panel System
07 42 14 2.2.A 4 21 days prior to work
Wall Panels
07 42 14 2.3.A 4 21 days prior to work
07 90 05 Joint Sealers
Product Data for Sealant Chemical Characteristics
07 90 05 1.3.B 4 21 days prior to work
Sealants
07 90 05 2.1.A,B,C 4 21 days prior to work
Accessories
07 90 05 2.2.A,B 4 21 days prior to work
08 11 13 Hollow Metal Doors and Frames
Steel Doors
08 11 13 1.3.A, 2.3 4 21 days prior to ordering
Accessory Materials
08 11 13 1.3.A, 2.4 4 21 days prior to ordering
Finish Materials
08 11 13 1.3.A, 2.5 4 21 days prior to ordering
Shop Drawings
08 11 13 1.3.B 4 21 days prior to work
08 36 18 Replacement of Hangar Door Components and
Operators
Shop Drawings
08 36 18 1.5.A 4 21 days prior to work
Manufacturer's Mill Certificate
08 36 18 1.5.B 4 21 days prior to work
Welders Certificates
08 36 18 1.5.C 4 21 days prior to work
FA5004-15-R-C003
EIELSON AFB, ALASKA
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
Door Manufacturer's Calculations
08 36 18 1.5.D 4 21 days prior to work
08 71 00 Door Hardware
Product Data for Hardware
08 71 00 1.4.B 4 21 days prior to work
Manufacturer's Installation Instructions
08 71 00 1.4.C 4 21 days prior to work
Maintenance Data
08 71 00 1.4.D 4 15 days prior to project close-out
Manufacturer's Warranty
08 71 00 1.4.E 4 21 days prior to work
Door Hardware - Finishes
08 71 00 2.2.C 4 21 days prior to work
Hinges
08 71 00 2.3.A 4 21 days prior to work
Locks and Latches
08 71 00 2.4.A,B,C 4 21 days prior to work
Closers
08 71 00 2.5.A 4 21 days prior to work
Gasketing and Thresholds
08 71 00 2.6.A,B,C 4 21 days prior to work
Protection Plates and Architectural Trim
08 71 00 2.7.A.1 4 21 days prior to work
09 90 00 Painting and Coating
Paint Materials, General
09 90 00 1.3.A, 2.2 4 21 days prior to work
Samples for Selection
09 90 00 1.3.B 4 21 days prior to work
Qualification Data
09 90 00 1.3.C 4 21 days prior to work
26 05 09 Manuals and As-Built Drawings
Operation and Maintenance Manuals
26 05 09 1.2 4 30 days prior to final inspection
As-Built Drawings
26 05 09 1.3 4 15 days prior to project close-out
26 05 19 Wire Conductors and Cable
Insulation Types
26 05 19 2.2 4 21 days prior to work
26 05 33 Raceways
Conduit and Tubing
26 05 33 2.3 4 21 days prior to work
Wireways and Gutters
26 05 33 2.4 4 21 days prior to work
Conduit Bodies
26 05 33 2.5 4 21 days prior to work
FA5004-15-R-C003
EIELSON AFB, ALASKA
OF ITEM, CONTRACT REFERENCE, TYPE
OF
SUBMITTAL
APPROVED DIS-APPROVED F
IN
A L A
P P
R O
V A
L
REMARKS
NOTIFIED
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L
N U
M B
E R
DATE CONTRACTOR
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
O T
H E
R
P L
A N
S
D A
T E
R E
C E
IV
E
D I N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E
N G
IN
E
E R
IN
G
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
M S
D S
TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED =
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N D
A e N u m b e r
C E
R T
IF
IC
A T
IO
N
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S R
E C
O M
M E
N D
A T
IO
N
S
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE SOLICITATION/ CONTRACT NUMBER
Repair Hangar Doors, Building
FTQW 06-1025
26 05 53 Identification
Nameplates
26 05 53 2.1.A 4 21 days prior to work
Wire and Cable Markers
26 05 53 2.1.B 4 21 days prior to work
Receptacle Plate Labels and Utilization Connection Point
Labels
26 05 53 2.1.C 4 21 days prior to work
26 28 15 Disconnects
Disconnect Switches
26 28 15 1.2.A,B 2.1 4 21 days prior to work
Outline Drawings
26 28 15 1.2.C 4 21 days prior to work
26 29 13 Motor Starters
Motor Start Switches
26 29 13 1.3.A,B 2.2 4 21 days prior to work
Magnetic Starters
26 29 13 1.3.A,B 2.3 4 21 days prior to work
Combination Magnetic Starter/Disconnects
26 29 13 1.3.A,B 2.4 4 21 days prior to work
28 31 00 Addressable Fire Alarm System
Fire Alarm Branch Circuit Conductors
28 31 00 2.2. 4 21 days prior to work
Schedule of Material Submittals, MAR 05 (SAF/AQCP) / PREVIOUS FORM IS OBSOLETE
FA5004-15-R-C003
EIELSON AFB, ALASKA