ANSWERS TO QUESTIONS FOR FA4819-16-R-5001, AFCEC OPERATIONS SUPPORT RE-COMPETE
QUESTION #3 (Submitted August 5, 2016):
The AFCEC Ops solicitation lists the following information for page limits:
· 20 pages for the Executive Summary in the table on page 46, and under Tab 2 on page 48, it states the narrative limit is 10 pages.
· 30 pages for the technical volume in the table on page 46, but 20 pages is stated on page 48.
· Unlimited pages for the Price Volume in the table on page 47, but states a 10 page limit on page 50
ANSWER:
See Amendment #2 for FA4819-16-R-5001 for corrections. The page counts were aligned with the table.
QUESTION #4 (Submitted August 5, 2015):
On pages 45-47 of Addendum 52.212-1, the instruction format goes from E back to D.
ANSWER:
Corrected see Page 1 of 6 of Amendment #2 for FA4819-16-R-5001
QUESTION #5 (Submitted August 5, 2015):
Will a compliance matrix count towards volume page count?
ANSWER:
Yes!
QUESTION #6 (Submitted August 5, 2015):
Glossary of Abbreviations and Acronyms is in all volumes except past performance. Should these be volume specific or proposal specific?
ANSWER:
Yes! Volume specific. We added a “Glossary of Abbreviations and Acronyms” tab under Past Performance.
See Page 2 of 6 of Amendment #2 for FA4819-16-R-5001
QUESTION #7 (Submitted August 5, 2015):
Should the Representations and Certifications be included in one of the volumes? If so, which one and will they count towards page count? Will a statement of SAM.gov compliance be acceptable?
ANSWER:
Tab 6 has been added in Vol I Executive Summary (Reps and Certs). This will not count towards pages. A copy of the Representations and Certifications is required.
QUESTION #8 (Submitted August 5, 2015):
Will Questionnaires received by proposal due date be acceptable?
ANSWER:
Yes