RFI_Att_4_-_Hydrologic_and_Hydraulic_Report_Redacted.pdf
PDF 6 MB Posted
- Attached to
- Railroad Bridges Federal contract opportunity
- Solicitation number
- FA4686-18-R-0006
About this file
RFI Att 4
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HYDROLOGIC AND HYDRAULIC REPORT
Bridge FAC#221 over Hutchinson Creek
Bridge FAC#222 over Hutchinson Creek (Branch)
Air Combat Command Beale US Air Force Base 9th Civil Engineer Squadron Contract: FA468617C0003 Wheatland Gate Bridges Bridges #221 and #222
Submitted to:
Air Combat Command Beale US Air Force Base 9th Civil Engineer Squadron
May 2017
Wheatland Gate Bridges Replacement Project Bridges FAC#221 and FAC#222 Over Hutchinson Creek on South Beale Road 1
Wheatland Gate Bridge Replacement Project – Hydrologic and Hydraulic Report
TABLE OF CONTENTS
1. STATEMENT OF QUALIFICATIONS
2. EXECUTIVE SUMMARY
3. EXISTING CONDITIONS
3.1 LAND USE
3.2 SOILS
3.3 GROUNDWATER
3.4 TOPOGRAPHY/DRAINAGE PATTERNS
3.5 FLOODING
3.6 EXISTING DRAINAGE FACILITIES
4. PROPOSED DRAINAGE FACILITIES
4.1 ROADWAY AND BRIDGE DECK DRAINAGE
4.1.1 Hydrologic Analysis
4.1.2 Hydraulic Analysis
5. BRIDGE HYDRAULICS
5.1 DESIGN CRITERIA
5.2 HYDRAULIC MODEL
5.2.1 Cross Sections
5.2.2 Manning’s n
5.2.3 Expansion/Contraction Coefficients
5.2.4 Flows
5.3 MODEL RESULTS
5.4 SCOUR ANALYSIS
5.4.1 Geotechnical Data
5.4.2 Hydraulic Data
5.5 SCOUR RESULTS
6. REFERENCES
APPENDIX A: On-Site Drainage Analysis APPENDIX B: Hydrology – Hutchinson Creek APPENDIX C: Hydraulic Analysis – Hutchinson Creek APPENDIX D: Scour Analysis
Over Hutchinson Creek on South Beale Road 1
Wheatland Gate Bridge Replacement Project – Hydrologic and Hydraulic Report
1. STATEMENT OF QUALIFICATIONS
This report has been prepared by or under the supervision of the following Registered Engineer.
The Registered Civil Engineer attests to the technical information contained herein and has judged the qualifications of any technical specialists providing engineering data upon which recommendations, conclusions, and decisions are based.
Ryan Neves, P.E.
May 26, 2017 Date
Over Hutchinson Creek on South Beale Road 2
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
2. EXECUTIVE SUMMARY
The 9th Civil Engineer Squadron, Beale AFB, proposes to replace the Wheatland Gate bridges, FAC#221 and FAC#222, located on South Beale Road in the City of Wheatland, Yuba County (Figure 1). Bridge FAC#221 is a 5-span structure approximately 75’ long. Bridge FAC#222 is a 4-span structure approximately 60’ long. Both existing structures are structurally deficient, internally deteriorating timber bridges founded on shallow concrete spread footings. The project will replace these bridges with single span, precast concrete bridges founded on driven piling with concrete abutments extending below the anticipated scour depths (Figures 4 and 5). The replacement bridges will have improved hydraulic capacity and will be built to current design standards (Caltrans, FHWA and AASHTO).
Improvements will also be made to approximately 150 feet of the existing two-lane South Beale Road approach at each end of each bridge. These improvements include drainage, guardrail, and lane and shoulder width in accordance with current design standards.
This Hydrologic and Hydraulic Report supports the final design of the Wheatland Gate Bridges Replacement Project with an evaluation of the existing and proposed Hutchinson Creek and Hutchinson Creek branch bridges. The report shows that all scour, freeboard, bridge and roadway drainage, as required by Federal Highway Administration (FHWA), is met by the proposed design.
Flow from the Hutchinson Creek watershed is split between the two bridges (Figure 2). Bridge FAC#221 crosses at Hutchinson Creek and Bridge FAC#222 crosses a branch of Hutchinson Creek. Bridge FAC#221 receives the majority of the flow during storm events and Bridges #222 receives overflow from Hutchinson Creek.
Several upstream detention facilities present within the contributing watershed were omitted from the hydrologic analysis to provide a conservative hydraulic analysis of the proposed bridge replacements (Figure 3).
A railroad line runs parallel to and upstream of South Beale Road. This line has two bridges of similar size to the existing FAC#221 and FAC#222. As a conservative measure, the analysis in this report accounts for the future removal of these railroad bridges. Accounting for the removal of the railroad bridges ensures that the proposed replacement bridges will continue to meet the design criteria in the future even if the railroad bridges are replaced by a clear span design or removed entirely.
This project is underlain by Group C soils with moderate-high runoff potential. The on-site runoff will collect along asphalt dikes on either side of the proposed bridges and flow into corrugated metal pipe downdrains sized to accommodate a 10-year storm event. The Federal Emergency Management Agency (FEMA) maps show that the project site is located in an area for which flooding potential is undetermined.
The following tables summarize the hydrologic, hydraulic, and scour results for the two bridges being replaced as part of this project.
Over Hutchinson Creek on South Beale Road 3
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
Table 1: Design Flows
Flow Frequency Bridge #221 Flow (cfs)
Bridge #222 Flow (cfs)
10-Year 2,290 850
50-Year 2,840 1,540
100-Year 3,075 1,745
Table 2: Hydraulic Analysis Results Summary
Bridge Minimum
Soffit Elevation
50-Year
WSEL
100-Year
WSEL
50-Year 100-Year
Freeboard (ft)
Freeboard Required
(ft)
Freeboard (ft)
Freeboard Required
(ft)
221 97.0 93.5 93.9 3.5 2.0 3.1 Clear Soffit
222 96.7 93.3 93.7 3.4 2.0 3.0 Clear Soffit
Table 3: 100-Year Event Estimated Scour Depths
Location Long-Term Bed Change
(ft)
Contraction Scour
(ft)
Local Scour
(ft)
Total Scour Depth
(ft)
Elevation of Total
Maximum Scour
Bridge
Abutment 1 0.0 0.2 6.7 6.9 86.6
Abutment 2 0.0 0.2 6.3 6.5 86.8
Bridge
Abutment 1 0.0 0.6 4.7 5.3 88.2
Abutment 2 0.0 0.2 3.6 3.8 89.7
I 0 2 4 6 8 10
Miles
Source: ESRI 2008;
Beale AFB
Y U B A
B U T T E
N E V A D A
S U T T E R
P L A C E R
S I E R R A
P L U M A S
E L D O R A D O
§̈¦80
§̈¦80
UV49
UV99
UV70
UV20
UV162
UV174
UV113
UV65
UV191
UV49
UV49
UV162
UV70
UV65
UV99
UV20
UV70
UV99
UV49
UV49
UV162
UV99
UV20
UV70
UV70
UV20
UV99
UV65
Plumas National Forest
Lake Oroville State Rec AreaLake Oroville State Rec Area
Auburn State Recreation AreaAuburn State Recreation Area
Malakoff Diggings St Hist ParkMalakoff Diggings St Hist Park
Empire Mine State Hist ParkEmpire Mine State Hist Park Condon ParkCondon Park
Pioneer ParkPioneer Park
V:\
Be ale
AF
B D am
\F1 _V icin ity
_2
9.m xd
FIGURE 1
Project Vicinity
Bridges 221 and 222 Replacement Project Beale Air Force Base, Yuba County, California
PACIFIC
OCEAN
Yuba County
Project Location
Over Hutchinson Creek on South Beale Road 9
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
3. EXISTING CONDITIONS
3.1 Land Use
The area adjacent to South Beale Road consists of undeveloped vegetated floodplain (Figure 6) and isolated service developments such as a truck inspection outpost and a waste water treatment facility. An adjacent railroad track runs parallel to South Beale Road approximately 70 feet to the east.
Table 4: Project Soil Types
Map Unit Symbol Soil Name
Hydrologic Soil Groups Percentage of Total Project Area A B C D
141 Conejo Loam - - 87.9% - 101 Aiken-Horseshoe Complex - - 6.8% - 203 Perkins Loam - - 5.3% -
TOTAL 0% 0% 100% 0%
Figure 6: Project Site Land Use
3.2 Soils
Based on the Natural Resource Conservation Service (NRCS) Web Soil Survey, the primary soil types found at the project site are Conejo Loam, Aiken-Horseshoe Complex, and Perkins Loam.
As shown in Table 4, all three soil types are classified as Hydrologic Soil Group (HSG) C. These soils are characterized having a slow infiltration rate when thoroughly wet. They consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission.
Over Hutchinson Creek on South Beale Road 10
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
3.3 Groundwater
Four exploratory borings were taken, adjacent to each of the proposed abutments at both bridges.
Groundwater was encountered in all borings at depths between 12 and 18 feet. These depths are generally coincident with the observed water elevation in the adjacent creek channels.
3.4 Topography/Drainage Patterns
The project site ranges in elevation from approximately 83 to 97 feet (NGVD 29) and is located in the Central Valley of California. The surrounding topography consists of undeveloped land that slopes generally to the west.
Hutchinson Creek, which is crossed by bridge FAC# 221, receives flow from an upstream, low-head dam as well as other small tributaries located within the watershed. Bridge FAC# 222 provides a crossing for a branch of Hutchinson Creek approximately 1,300 feet south of Hutchinson Creek.
3.5 Flooding
The FEMA Flood Insurance Rate Map (FIRM) for the project area shows that the majority of the project area is located within Zone D, an area where flood hazards are undetermined. Figure 7 shows the FIRM for the project area.
3.6 Existing Drainage Facilities
Within each bridge, storm water flows from the crown of the road and away from the highpoint of each bridge. Runoff sheet flows directly from the roadway onto adjacent land or over the bridge deck via scuppers into Hutchinson Creek and its southern branch.
Figure 7: FEMA Flood Map #06115C0450D
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A Sticky Note Unmarked set by 1538763361A
Over Hutchinson Creek on South Beale Road 11
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
4. PROPOSED DRAINAGE FACILITIES
4.1 Roadway and Bridge Deck Drainage
The proposed roadways will sheet flow from the roadway centerline to asphalt dikes at the edge of the roadway. Concentrated flow along the asphalt dikes will then flow away from the high point of each bridge and flow into 18” downdrains where runoff will outfall onto rock slope protection at the toe of the embankments.
To determine the spread of flow along the dikes and the need for drainage inlets, a hydrologic analysis was conducted for the on-site project areas.
4.1.1 Hydrologic Analysis
The hydrologic design criteria is in accordance with Chapter 7 of the FHWA’s Urban Drainage Design Manual Hydraulic Engineering Circular (HEC) No. 22.
Design Frequency: 10-year storm for roadway
Time of Concentration: Based on the small watershed areas tributary to the downdrains, a 5-minute time of concentration is assumed for all sites.
Peak Discharge – The Rational Method was used to estimate the peak discharge (Q) for the downdrains. The Rational Method is defined by the following formula:
Q = CiA, where
Q = design discharge (in cubic feet per second) C = coefficient of runoff = 0.95 for asphalt i = rainfall intensity for the selected frequency and for a duration equal to the time of concentration (in inches per hour).
A = drainage area (acres)
The rainfall intensities (i) were determined using the NOAA Atlas 14, Volume 6, Version 2. The NOAA intensity data for the project site is included in Appendix A.
4.1.2 Hydraulic Analysis
Chapter 4 of the FHWA’s HEC-22 requires that storm runoff flowing along the bridge/roadway not exceed a half-lane encroachment onto the travel lane during the 10-year storm. In the proposed condition, this is equivalent to 10 feet from the dike. Based on a hydraulic analysis completed using FlowMaster, the spreaded width is less than 6 feet throughout each of the project sites. As a result, deck drains on the bridges or additional inlets are not required to meet the surface flow spread criteria. Downdrains were sized to pass the 10-year flow.
Spreaded width calculations and downdrain calculations as well as roadway drainage exhibits showing surface flow paths are included in Appendix A.
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Over Hutchinson Creek on South Beale Road 12
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
5. BRIDGE HYDRAULICS
South Beale Road currently crosses both Hutchinson Creek and a branch of Hutchinson Creek on 3-span, timber construction truss bridges supported by square timber piers set within the main channels of each crossing. The proposed project will construct two single-span, structurally independent bridges in the place of the existing bridges. The new bridges will match the existing bridges in length and profile but will be supported by concrete abutments set back from the main channels of each crossing so as to provide unobstructed flow for each of the waterways.
The following hydraulic analysis was conducted to verify compliance with freeboard requirements, confirm that the proposed improvements will not cause flooding upstream, and to serve as a basis for the scour analysis.
5.1 Design Criteria
The bridge freeboard requirements applicable to the project, and incorporated into the design, are the FHWA criteria, summarized as follows:
• Bridges should be designed such that the 100-year water surface elevation (WSEL) does not rise more than one foot above existing conditions.
• Bridges should pass the 50-year storm event with a minimum 2 feet of freeboard.
5.2 Hydraulic Model
The steady-state HEC RAS model for the two bridge openings was used as the basis for the Wheatland Bridges Replacement Project hydraulic analysis. The following sections describe how the modeling parameters were addressed in the model.
5.2.1 Cross Sections
The channel geometry for each hydraulic model was developed using a combination of topographic survey data as well as LIDAR data. Channel cross sections were defined perpendicular to the direction of flow. The cross sections for each model are found in Appendix C.
5.2.2 Manning’s n
The existing creeks are unlined, clean, and uniform with grass-vegetated side slopes. Overbank areas are similarly vegetated with few trees or other obstructions. As a result, a Manning’s ‘n’ value of 0.03 was used for both the channel and overbank areas.
5.2.3 Expansion/Contraction Coefficients
The expansion and contraction coefficients were set to 0.3 and 0.1, respectively, along the entire HEC-RAS model limits. These values were selected because they describe a channel with gradual transitions between cross-sections.
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Over Hutchinson Creek on South Beale Road 13
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
At the bridges with abutments that are impacted by the design flows, expansion and contraction coefficients of 0.5 and 0.3, respectively, were selected to represent a more abrupt transition through the bridge.
5.2.4 Flows
At the bridge sites, there is no published flow data available. Flow values for the 10-, 50-, and 100-year flows were determined using the USGS StreamStats web application which has the ability to delineate watersheds and calculate flows based on the USGS regression equations.
Regional regression equations are an extrapolation of data from nearby watersheds with similar hydrologic, physiographic, and climatological characteristics. The StreamStats flow data provides conservative flow values that encompass the entire watershed without taking into account the detention of flow at the existing dams upstream from the bridge and Hutchinson Creek, as well as the natural storage and detention from the general topography of the watershed.
The flow values for the design frequencies at the Hutchinson Creek Bridge are provided in Table 5.
Table 5: Hutchinson Creek Flows at South Beale Road
Flow Frequency Flow (cfs)
10-Year 3,140 50-Year 4,380
100-Year 4,820
These design flows in the main branch of Hutchinson Creek exceed the existing creek capacity.
Under the design flows, the existing banks would overtop and the flow would spread across the floodplain, with a majority of it contributing to the Hutchinson Creek tributary that Bridge #222 crosses over. Because this overtopping occurs upstream of the current hydraulic model limits, separate weir calculations were performed in order to determine the amount of flow that would stay within Hutchinson Creek and that which would exceed the banks and spread across the floodplain. To be conservative, it was assumed that the full flow leaving the main channel of Hutchinson Creek would be tributary to the Bridge #222 shed to the south. The resulting peak flows tributary to each bridge site within the HEC-RAS model were determined to be as shown in Table 6.
Table 6: Design Flows
Flow Frequency Bridge #221 Flow (cfs)
Bridge #222 Flow (cfs)
10-Year 2,290 850 50-Year 2,840 1,540 100-Year 3,075 1,745
Over Hutchinson Creek on South Beale Road 14
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
5.3 Model Results
The design water surface elevations, minimum soffit elevations, and available freeboard for the proposed bridges for the 50-year design storm flow are summarized in Table 7, and a comparison of existing and proposed water surface elevations during the 100-year design storm is provided in Table 8.
The results of the hydraulic analyses show that each bridge will have greater than the required two feet of freeboard during the 50-year condition, in accordance with FHWA standards. In addition, the change in water surface elevation does not exceed 1 foot, meeting FHWA criteria (See Table 7.)
Table 7: Hydraulic Analysis Results Summary
Bridge Minimum
Soffit Elevation
50-Year
WSEL
100-Year
WSEL
50-Year 100-Year
Freeboard (ft)
Freeboard Required
(ft)
Freeboard (ft)
Freeboard Required
(ft) 221 97.0 93.5 93.9 3.5 2.0 3.1 Clear Soffit 222 96.7 93.3 93.7 3.4 2.0 3.0 Clear Soffit
Table 8: 100-Year Water Surface Elevation Summary
Bridge River Station (US of Proposed Bridge)
Existing 100yr
WSEL
Proposed 100yr
WSEL
Change (ft)
221 4060.2 94.2 93.9 -0.3 222 4894 93.9 93.7 -0.2
Detailed hydraulic results from all design storm events, as well as a comparison table including existing and proposed water surface elevations for all non-interpolated sections at each bridge and for each storm event can be found in Appendix C.
5.4 Scour Analysis
To determine the anticipated depth of scour for the proposed bridge design, scour calculations were performed in HEC-RAS based upon the methods outlined in Hydraulic Engineering Circular No. 18 and 20 (FHWA, 1995). The parameters used to calculate scour include geotechnical soil data and hydraulic information.
5.4.1 Geotechnical Data
Geotechnical information at the project site was obtained from the geotechnical borings performed by Consultants in April 2017. Particle sizes for D50 and D90 were obtained from the grain size distribution curves for each of the borings at a depth equivalent to the creek bed.
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Over Hutchinson Creek on South Beale Road 15
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
5.4.2 Hydraulic Data
The hydraulic data used in the scour calculations is based on the 100-year flow from the hydraulic analysis discussed in Section 6.3 and includes flow, velocity, depth, and direction of flow with respect to the bridge and piers.
5.5 Scour Results
Using the geotechnical and hydraulic data described above, the total scour is defined as the summation of long-term, contraction, and local scour. Results of the scour analysis are summarized below and the HEC RAS output is provided in Appendix D.
Long-Term Scour: Review of the channel grade as shown on the original bridge as-builts indicates that there has been little to no long term scour at either bridge over the 65 year life of the existing structures. With no anticipated build out of the undeveloped terrain upstream of the bridges, there is no reason to expect the existing channel inverts to change; therefore long term scour is assumed to be zero.
Contraction Scour: Contraction scour occurs when the flow area of a stream is reduced by a natural contraction or a bridge constricting the flow. The proposed bridge spans increase the hydraulic opening area at each site. Additionally, even when excluding the existing upstream railroad bridges as potential hydraulic obstructions and channel constrictions, the presence of the existing railroad berm itself acts as a natural contraction. The resulting channel contraction at the abutments is less than 1 foot at each bridge.
Local Scour: Scour caused by high flow velocities at the bridge abutments can cause a significant amount of localized scour. The results indicate that local abutment scour ranges from approximately 4 to 7 feet of scour at each of the abutments.
Total Scour: Total scour is the sum of long-term scour, contraction scour, and local scour. The total scour depths at the proposed bridge abutments are shown in Table 9.
Table 9: 100-Year Event Estimated Scour Depths
Location
Long-Term Bed
Change (ft)
Contraction Scour
(ft)
Local Scour
(ft)
Total Scour Depth
(ft)
Elevation of Total
Maximum Scour
Bridge
Abutment 1 0.0 0.2 6.7 6.9 86.6 Abutment 2 0.0 0.2 6.3 6.5 86.8
Bridge
Abutment 1 0.0 0.6 4.7 5.3 88.2 Abutment 2 0.0 0.2 3.6 3.8 89.7
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Over Hutchinson Creek on South Beale Road 16
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
The foundations for the proposed bridges consist of diaphragm abutments that will be constructed beneath the estimated maximum scour depth. Furthermore, the abutments are founded on piles that extend well below the scour depth.
These scour results are considered to be conservative. The 100-year flows used to calculate the scour depths do not account for the reduction of flow provided by upstream attenuation.
Additionally, contraction of the channel occurs at the upstream railroad bridge berm before flows reach the proposed bridge crossings.
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Over Hutchinson Creek on South Beale Road 17
Wheatland Gate Bridges Replacement Project – Hydrologic and Hydraulic Report
6. REFERENCES
Bentley, Inc., November 4, 2009. FlowMaster V8i [4011472].
Bentley, Inc., November 4, 2009. CulvertMaster V3.3 [4011472].
Federal Emergency Management Agency. Flood Insurance Rate Map for Yuba County, California; Map No. 06115C0450D. February 18, 2011.
National Oceanic and Atmosphere Administration. Point Precipitation Frequency Estimates – Atlas 14, Volume 6, Version 2. May 2017
Natural Resource Conservation Service. Web Soil Survey. May 2017
U.S. Department of Transportation, April 2012. Federal Highway Administration. Hydraulic Engineering Circular No. 18, Evaluating Scour at Bridges, Fifth Edition.
U.S. Department of Transportation, September 2009. Federal Highway Administration.
Hydraulic Engineering Circular No. 23, Bridge Scour and Stream Instability Countermeasures:
Experience, Selection, and Design Guidance – Third Edition.
1538763361A
None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
Wheatland Gate Bridge Replacement Project – Hydrologic and Hydraulic Report
APPENDIX A
On-Site Drainage Analysis
Hydrology Calculations ‐BRIDGE 222
WS1 0.95 1560.8 0.036 5.0 2.72 0.09
WS2 0.95 1560.8 0.036 5.0 2.72 0.09
WS3 0.95 4337.5 0.100 5.0 2.72 0.26
WS4 0.95 4337.1 0.100 5.0 2.72 0.26
Hydrology Calculations ‐BRIDGE 221
WS5 0.95 3792.6 0.087 5.0 2.72 0.22
WS6 0.95 3792.8 0.087 5.0 2.72 0.22
WS7 0.95 2291.1 0.053 5.0 2.72 0.14
WS8 0.95 2291.1 0.053 5.0 2.72 0.14
Time of Concentration, Tc (Min= 5 minutes)
Intensity 10 Year (in/hr)
Q ‐ 10 Year (cfs)
Watershed
Watershed Runoff Coefficients for Paved
Area (c=0.95)
Total Sub‐ Watershed Area
(sq. ft.)
Total Sub‐ Watershed Area
(acres)
Watershed Intensity 10 Year (in/hr)
Q ‐ 10 Year (cfs)
Total Sub‐ Watershed Area
(sq. ft.)
Time of Concentration, Tc (Min= 5 minutes)
Watershed Runoff Coefficients for Paved
Area (c=0.95)
Total Sub‐ Watershed Area
(acres)
Bridge 221 ‐ Spread Calculations
Label Solve For Channel Slope
(ft/ft)
Discharge
(ft³/s)
Manning
Coefficient
Flow Area
(ft²)
Depth
(ft)
Velocity
(ft/s)
Road
Cross
Slope
(ft/ft)
Spread
(ft)
WS 5&6 ‐ Q10 Spread 0.0035 0.22 0.016 0.25 0.1 0.89 0.02 4.97
WS 7&8 ‐ Q10 Spread 0.0041 0.14 0.016 0.17 0.08 0.84 0.02 4.08
Bridge 221 ‐ Spread Calculations
Label Solve For Channel Slope
(ft/ft)
Discharge
(ft³/s)
Manning
Coefficient
Flow Area
(ft²)
Depth
(ft)
Velocity
(ft/s)
Road
Cross
Slope
(ft/ft)
Spread
(ft)
WS 1&2 Q10 Spread 0.0035 0.09 0.016 0.13 0.07 0.71 0.02 3.56
WS 3&4 Q10 Spread 0.0035 0.26 0.016 0.28 0.11 0.93 0.02 5.30
Culvert Analysis Report
WS 5&6 Q10
Analysis Component
Storm Event Design Discharge 0.22 cfs
Peak Discharge Method: User-Specified
Design Discharge 0.22 cfs Check Discharge 0.00 cfs
Tailwater Conditions: Constant Tailwater
Tailwater Elevation N/A ft
Name Description Discharge HW Elev. Velocity
Culvert-1 1-12 inch Circular 0.22 cfs 99.29 ft 6.45 ft/s
Weir Not Considered N/A N/A N/A
WS 5&6 Q10
Component:Culvert-1
Culvert Summary
Computed Headwater Elevation 99.29 ft Discharge 0.22 cfs
Inlet Control HW Elev. 99.01 ft Tailwater Elevation N/A ft
Outlet Control HW Elev. 99.29 ft Control Type Entrance Control
Headwater Depth/Height 0.29
Grades
Upstream Invert 99.00 ft Downstream Invert 79.00 ft
Length 40.00 ft Constructed Slope 0.500000 ft/ft
Hydraulic Profile
Profile S2 Depth, Downstream 0.09 ft
Slope Type Steep Normal Depth 0.09 ft
Flow Regime Supercritical Critical Depth 0.19 ft
Velocity Downstream 6.45 ft/s Critical Slope 0.019753 ft/ft
Section
Section Shape Circular Mannings Coefficient 0.024
Section Material CMP Span 1.00 ft
Section Size 12 inch Rise 1.00 ft
Number Sections 1
Outlet Control Properties
Outlet Control HW Elev. 99.29 ft Upstream Velocity Head 0.07 ft
Ke 0.50 Entrance Loss 0.03 ft
Inlet Control Properties
Inlet Control HW Elev. 99.01 ft Flow Control Unsubmerged
Inlet Type Headwall Area Full 0.8 ft²
K 0.00780 HDS 5 Chart 2
M 2.00000 HDS 5 Scale 1
C 0.03790 Equation Form 1
Y 0.69000
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 7&8 Q10
Analysis Component
Storm Event Design Discharge 0.14 cfs
Peak Discharge Method: User-Specified
Design Discharge 0.14 cfs Check Discharge 0.00 cfs
Tailwater Conditions: Constant Tailwater
Tailwater Elevation N/A ft
Name Description Discharge HW Elev. Velocity
Culvert-1 1-12 inch Circular 0.14 cfs 99.23 ft 5.63 ft/s
Weir Not Considered N/A N/A N/A
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 7&8 Q10
Component:Culvert-1
Culvert Summary
Computed Headwater Elevation 99.23 ft Discharge 0.14 cfs
Inlet Control HW Elev. 99.00 ft Tailwater Elevation N/A ft
Outlet Control HW Elev. 99.23 ft Control Type Entrance Control
Headwater Depth/Height 0.23
Grades
Upstream Invert 99.00 ft Downstream Invert 79.00 ft
Length 40.00 ft Constructed Slope 0.500000 ft/ft
Hydraulic Profile
Profile S2 Depth, Downstream 0.07 ft
Slope Type Steep Normal Depth 0.07 ft
Flow Regime Supercritical Critical Depth 0.15 ft
Velocity Downstream 5.63 ft/s Critical Slope 0.020687 ft/ft
Section
Section Shape Circular Mannings Coefficient 0.024
Section Material CMP Span 1.00 ft
Section Size 12 inch Rise 1.00 ft
Number Sections 1
Outlet Control Properties
Outlet Control HW Elev. 99.23 ft Upstream Velocity Head 0.05 ft
Ke 0.50 Entrance Loss 0.03 ft
Inlet Control Properties
Inlet Control HW Elev. 99.00 ft Flow Control Unsubmerged
Inlet Type Headwall Area Full 0.8 ft²
K 0.00780 HDS 5 Chart 2
M 2.00000 HDS 5 Scale 1
C 0.03790 Equation Form 1
Y 0.69000
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 1&2 Q10
Analysis Component
Storm Event Design Discharge 0.09 cfs
Peak Discharge Method: User-Specified
Design Discharge 0.09 cfs Check Discharge 0.00 cfs
Tailwater Conditions: Constant Tailwater
Tailwater Elevation N/A ft
Name Description Discharge HW Elev. Velocity
Culvert-1 1-12 inch Circular 0.09 cfs 99.19 ft 4.92 ft/s
Weir Not Considered N/A N/A N/A
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 1&2 Q10
Component:Culvert-1
Culvert Summary
Computed Headwater Elevation 99.19 ft Discharge 0.09 cfs
Inlet Control HW Elev. 99.00 ft Tailwater Elevation N/A ft
Outlet Control HW Elev. 99.19 ft Control Type Entrance Control
Headwater Depth/Height 0.19
Grades
Upstream Invert 99.00 ft Downstream Invert 79.00 ft
Length 40.00 ft Constructed Slope 0.500000 ft/ft
Hydraulic Profile
Profile S2 Depth, Downstream 0.06 ft
Slope Type Steep Normal Depth 0.06 ft
Flow Regime Supercritical Critical Depth 0.12 ft
Velocity Downstream 4.92 ft/s Critical Slope 0.021682 ft/ft
Section
Section Shape Circular Mannings Coefficient 0.024
Section Material CMP Span 1.00 ft
Section Size 12 inch Rise 1.00 ft
Number Sections 1
Outlet Control Properties
Outlet Control HW Elev. 99.19 ft Upstream Velocity Head 0.04 ft
Ke 0.50 Entrance Loss 0.02 ft
Inlet Control Properties
Inlet Control HW Elev. 99.00 ft Flow Control Unsubmerged
Inlet Type Headwall Area Full 0.8 ft²
K 0.00780 HDS 5 Chart 2
M 2.00000 HDS 5 Scale 1
C 0.03790 Equation Form 1
Y 0.69000
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 3&4 Q10
Analysis Component
Storm Event Design Discharge 0.26 cfs
Peak Discharge Method: User-Specified
Design Discharge 0.26 cfs Check Discharge 0.00 cfs
Tailwater Conditions: Constant Tailwater
Tailwater Elevation N/A ft
Name Description Discharge HW Elev. Velocity
Culvert-1 1-12 inch Circular 0.26 cfs 99.32 ft 6.78 ft/s
Weir Not Considered N/A N/A N/A
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
WS 3&4 Q10
Component:Culvert-1
Culvert Summary
Computed Headwater Elevation 99.32 ft Discharge 0.26 cfs
Inlet Control HW Elev. 99.03 ft Tailwater Elevation N/A ft
Outlet Control HW Elev. 99.32 ft Control Type Entrance Control
Headwater Depth/Height 0.32
Grades
Upstream Invert 99.00 ft Downstream Invert 79.00 ft
Length 40.00 ft Constructed Slope 0.500000 ft/ft
Hydraulic Profile
Profile S2 Depth, Downstream 0.10 ft
Slope Type Steep Normal Depth 0.10 ft
Flow Regime Supercritical Critical Depth 0.21 ft
Velocity Downstream 6.78 ft/s Critical Slope 0.019518 ft/ft
Section
Section Shape Circular Mannings Coefficient 0.024
Section Material CMP Span 1.00 ft
Section Size 12 inch Rise 1.00 ft
Number Sections 1
Outlet Control Properties
Outlet Control HW Elev. 99.32 ft Upstream Velocity Head 0.07 ft
Ke 0.50 Entrance Loss 0.04 ft
Inlet Control Properties
Inlet Control HW Elev. 99.03 ft Flow Control Unsubmerged
Inlet Type Headwall Area Full 0.8 ft²
K 0.00780 HDS 5 Chart 2
M 2.00000 HDS 5 Scale 1
C 0.03790 Equation Form 1
Y 0.69000
1538763361A Sticky Note None set by 1538763361A
1538763361A Sticky Note MigrationNone set by 1538763361A
1538763361A
APPENDIX B
Hydrology - Hutchinson Creek
NOAA Atlas 14, Volume 6, Version 2 Location name: Marysville, California, USA* Latitude: 39.0885°, Longitude: 121.4214°
Elevation: 87.66 ft**
* source: ESRI Maps ** source: USGS
POINT PRECIPITATION FREQUENCY ESTIMATES
Sanja Perica, Sarah Dietz, Sarah Heim, Lillian Hiner, Kazungu Maitaria, Deborah Martin, Sandra Pavlovic, Ishani Roy, Carl Trypaluk, Dale Unruh, Fenglin Yan, Michael Yekta, Tan Zhao, Geoffrey
Bonnin, Daniel Brewer, LiChuan Chen, Tye Parzybok, John Yarchoan
NOAA, National Weather Service, Silver Spring, Maryland
PF_tabular | PF_graphical | Maps_&_aerials
PF tabular PDSbased point precipitation frequency estimates with 90% confidence intervals (in inches/hour)1
Duration Average recurrence interval (years)
1 2 5 10 25 50 100 200 500 1000
5min 1.44 (1.26‑1.68)
1.80 (1.56‑2.10)
2.29 (1.98‑2.69)
2.72 (2.33‑3.22)
3.35 (2.74‑4.13)
3.85 (3.07‑4.88)
4.40 (3.41‑5.76)
5.00 (3.73‑6.78)
5.88 (4.16‑8.39)
6.60 (4.48‑9.83)
10min 1.04 (0.900‑1.21)
1.29 (1.12‑1.51)
1.64 (1.42‑1.93)
1.96 (1.67‑2.31)
2.40 (1.96‑2.96)
2.77 (2.20‑3.50)
3.16 (2.44‑4.13)
3.59 (2.68‑4.86)
4.21 (2.98‑6.01)
4.73 (3.21‑7.05)
15min 0.836 (0.724‑0.972)
1.04 (0.904‑1.21)
1.33 (1.15‑1.55)
1.58 (1.35‑1.86)
1.94 (1.58‑2.38)
2.23 (1.78‑2.82)
2.54 (1.97‑3.33)
2.89 (2.16‑3.92)
3.40 (2.40‑4.84)
3.82 (2.59‑5.68)
30min 0.580 (0.504‑0.674)
0.722 (0.626‑0.840)
0.920 (0.796‑1.08)
1.09 (0.934‑1.29)
1.34 (1.10‑1.65)
1.55 (1.23‑1.96)
1.76 (1.36‑2.31)
2.00 (1.50‑2.72)
2.35 (1.67‑3.36)
2.65 (1.79‑3.94)
60min 0.386 (0.335‑0.449)
0.481 (0.417‑0.560)
0.613 (0.530‑0.717)
0.728 (0.622‑0.860)
0.893 (0.732‑1.10)
1.03 (0.821‑1.30)
1.18 (0.909‑1.54)
1.34 (0.996‑1.81)
1.57 (1.11‑2.24)
1.76 (1.20‑2.63)
2hr 0.284 (0.246‑0.330)
0.336 (0.292‑0.391)
0.410 (0.355‑0.480)
0.476 (0.408‑0.563)
0.574 (0.470‑0.708)
0.656 (0.522‑0.830)
0.744 (0.576‑0.974)
0.844 (0.630‑1.14)
0.992 (0.702‑1.42)
1.12 (0.758‑1.66)
3hr 0.234 (0.204‑0.273)
0.274 (0.237‑0.319)
0.330 (0.285‑0.386)
0.380 (0.325‑0.449)
0.454 (0.372‑0.560)
0.516 (0.412‑0.654)
0.585 (0.453‑0.765)
0.663 (0.495‑0.897)
0.779 (0.551‑1.11)
0.878 (0.596‑1.31)
6hr 0.171 (0.148‑0.199)
0.197 (0.171‑0.230)
0.235 (0.203‑0.275)
0.269 (0.230‑0.317)
0.319 (0.261‑0.393)
0.362 (0.288‑0.458)
0.409 (0.316‑0.535)
0.462 (0.345‑0.626)
0.543 (0.385‑0.775)
0.613 (0.416‑0.913)
12hr 0.112 (0.097‑0.130)
0.139 (0.121‑0.162)
0.175 (0.151‑0.204)
0.205 (0.175‑0.242)
0.246 (0.202‑0.304)
0.279 (0.222‑0.353)
0.313 (0.242‑0.409)
0.349 (0.260‑0.472)
0.399 (0.282‑0.569)
0.438 (0.297‑0.653)
24hr 0.075 (0.066‑0.087)
0.103 (0.091‑0.120)
0.140 (0.122‑0.163)
0.168 (0.146‑0.197)
0.205 (0.172‑0.248)
0.232 (0.192‑0.287)
0.259 (0.209‑0.328)
0.286 (0.225‑0.371)
0.321 (0.243‑0.434)
0.348 (0.254‑0.485)
2day 0.050 (0.044‑0.058)
0.068 (0.059‑0.079)
0.089 (0.078‑0.104)
0.107 (0.092‑0.125)
0.129 (0.109‑0.157)
0.146 (0.120‑0.180)
0.162 (0.131‑0.205)
0.179 (0.140‑0.232)
0.200 (0.151‑0.271)
0.217 (0.159‑0.302)
3day 0.040 (0.035‑0.046)
0.053 (0.046‑0.061)
0.069 (0.060‑0.080)
0.081 (0.071‑0.096)
0.098 (0.083‑0.119)
0.111 (0.091‑0.137)
0.123 (0.099‑0.155)
0.135 (0.106‑0.176)
0.151 (0.114‑0.205)
0.164 (0.120‑0.228)
4day 0.034 (0.029‑0.039)
0.044 (0.038‑0.051)
0.057 (0.050‑0.066)
0.067 (0.058‑0.079)
0.080 (0.067‑0.097)
0.090 (0.074‑0.111)
0.100 (0.081‑0.127)
0.110 (0.086‑0.143)
0.123 (0.093‑0.166)
0.133 (0.097‑0.185)
7day 0.024 (0.021‑0.028)
0.031 (0.027‑0.036)
0.039 (0.034‑0.046)
0.046 (0.040‑0.054)
0.055 (0.046‑0.066)
0.061 (0.050‑0.075)
0.067 (0.054‑0.085)
0.074 (0.058‑0.096)
0.082 (0.062‑0.111)
0.089 (0.065‑0.124)
10day 0.019 (0.017‑0.022)
0.024 (0.021‑0.028)
0.031 (0.027‑0.036)
0.036 (0.031‑0.042)
0.042 (0.036‑0.051)
0.047 (0.039‑0.059)
0.052 (0.042‑0.066)
0.057 (0.045‑0.074)
0.063 (0.048‑0.086)
0.068 (0.050‑0.095)
20day 0.013 (0.011‑0.015)
0.016 (0.014‑0.019)
0.020 (0.018‑0.024)
0.024 (0.021‑0.028)
0.028 (0.023‑0.034)
0.031 (0.025‑0.038)
0.034 (0.027‑0.043)
0.037 (0.029‑0.048)
0.040 (0.031‑0.055)
0.043 (0.032‑0.060)
30day 0.010 (0.009‑0.012)
0.013 (0.011‑0.015)
0.016 (0.014‑0.019)
0.019 (0.016‑0.022)
0.022 (0.019‑0.027)
0.024 (0.020‑0.030)
0.027 (0.021‑0.034)
0.029 (0.023‑0.037)
0.032 (0.024‑0.043)
0.034 (0.025‑0.047)
45day 0.009 (0.008‑0.010)
0.011 (0.009‑0.013)
0.013 (0.012‑0.016)
0.016 (0.013‑0.018)
0.018 (0.015‑0.022)
0.020 (0.016‑0.024)
0.021 (0.017‑0.027)
0.023 (0.018‑0.030)
0.025 (0.019‑0.034)
0.027 (0.020‑0.037)
60day 0.008 (0.007‑0.009)
0.010 (0.008‑0.011)
0.012 (0.010‑0.014)
0.014 (0.012‑0.016)
0.016 (0.013‑0.019)
0.017 (0.014‑0.021)
0.019 (0.015‑0.024)
0.020 (0.016‑0.026)
0.022 (0.016‑0.029)
0.023 (0.017‑0.032)
1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS).
Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values.
Please refer to NOAA Atlas 14 document for more information.
Back to Top
PF graphical http://www.commerce.gov/ http://www.noaa.gov/
Back to Top
Maps & aerials
Small scale terrain
2km
1mi
Large scale terrain
Large scale map
Large scale aerial
Back to Top
US Department of Commerce National Oceanic and Atmospheric Administration
National Weather Service National Water Center
1325 East West Highway Silver Spring, MD 20910
Questions?: HDSC.Questions@noaa.gov
Disclaimer
10km
6mi
40km
30mi
20km
20mi http://www.commerce.gov/ http://www.noaa.gov/ http://www.nws.noaa.gov/ http://www.nws.noaa.gov/oh/ mailto:HDSC.Questions@noaa.gov http://www.nws.noaa.gov/disclaimer.html
APPENDIX C
Hydraulic Analysis – Hutchinson Creek fmartinez Highlight fmartinez Highlight
HEC-RAS Plan: Plan 04 River: Hutchinson Creek Reach: R1 Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
R1 5000 10YR 2290.00 84.00 95.95 89.64 96.15 0.000311 3.62 659.42 141.10 0.21
R1 5000 50YR 2840.00 84.00 96.95 90.31 97.18 0.000325 3.97 748.99 141.10 0.22
R1 5000 100YR 3075.00 84.00 97.34 90.58 97.59 0.000331 4.11 784.41 141.10 0.23
R1 4908.8 10YR 2290.00 85.00 95.71 90.85 96.09 0.000685 5.01 470.39 219.10 0.31
R1 4908.8 50YR 2840.00 85.00 96.66 91.59 97.12 0.000707 5.49 537.36 219.10 0.32
R1 4908.8 100YR 3075.00 85.00 97.04 91.89 97.53 0.000716 5.67 563.79 219.10 0.33
R1 4753.3 10YR 2290.00 83.00 95.68 90.83 95.98 0.000488 4.65 552.41 159.00 0.27
R1 4753.3 50YR 2840.00 83.00 96.65 91.74 96.99 0.000501 5.03 630.04 159.00 0.28
R1 4753.3 100YR 3075.00 83.00 97.03 92.22 97.40 0.000506 5.18 660.68 159.00 0.28
R1 4685.2 10YR 2290.00 82.00 95.66 89.95 95.94 0.000435 4.41 568.30 169.00 0.25
R1 4685.2 50YR 2840.00 82.00 96.63 90.74 96.96 0.000456 4.81 645.77 169.00 0.26
R1 4685.2 100YR 3075.00 82.00 97.01 91.05 97.36 0.000464 4.97 676.36 169.00 0.27
R1 4608.9 10YR 2290.00 83.00 95.54 90.83 95.89 0.000627 4.90 505.81 202.40 0.30
R1 4608.9 50YR 2840.00 83.00 96.51 91.64 96.91 0.000632 5.29 582.96 202.40 0.30
R1 4608.9 100YR 3075.00 83.00 96.89 91.97 97.31 0.000634 5.44 613.42 202.40 0.31
R1 4508.1 10YR 2290.00 82.00 95.55 90.33 95.81 0.000461 4.27 576.36 230.00 0.26
R1 4508.1 50YR 2840.00 82.00 96.52 91.30 96.83 0.000474 4.65 653.67 230.00 0.26
R1 4508.1 100YR 3075.00 82.00 96.90 91.60 97.23 0.000480 4.80 684.18 230.00 0.27
R1 4395.1 10YR 2290.00 82.00 95.55 89.03 95.75 0.000336 3.76 663.38 350.30 0.22
R1 4395.1 50YR 2840.00 82.00 96.52 89.79 96.76 0.000346 4.08 755.90 350.30 0.23
R1 4395.1 100YR 3075.00 82.00 96.91 90.12 97.16 0.000350 4.21 792.45 350.30 0.23
R1 4270.3 10YR 2290.00 82.00 95.45 89.27 95.70 0.000397 4.09 614.30 352.20 0.24
R1 4270.3 50YR 2840.00 82.00 96.43 90.08 96.71 0.000404 4.41 711.61 352.20 0.25
R1 4270.3 100YR 3075.00 82.00 96.81 90.40 97.11 0.000407 4.54 750.09 352.20 0.25
R1 4154.6 10YR 2290.00 84.00 94.82 92.08 95.56 0.001987 6.93 330.90 474.89 0.49
R1 4154.6 50YR 2840.00 84.00 95.68 92.93 96.56 0.001979 7.52 379.83 500.79 0.50
R1 4154.6 100YR 3075.00 84.00 96.02 93.21 96.95 0.001973 7.75 400.71 505.35 0.50
R1 4144.1 10YR 2290.00 85.00 92.72 92.72 94.89 0.008811 11.81 193.88 44.81 1.00
R1 4144.1 50YR 2840.00 85.00 93.49 93.49 95.86 0.008521 12.37 229.68 48.24 1.00
R1 4144.1 100YR 3075.00 85.00 93.78 93.78 96.25 0.008459 12.60 244.10 49.55 1.00
R1 4106.5 10YR 2290.00 84.00 93.01 89.44 93.41 0.000931 5.10 457.14 76.54 0.36
R1 4106.5 50YR 2840.00 84.00 94.08 90.04 94.52 0.000882 5.36 541.24 81.12 0.35
R1 4106.5 100YR 3075.00 84.00 94.42 90.28 94.89 0.000895 5.53 569.35 82.59 0.36
R1 4086.8 10YR 2290.00 85.00 93.17 93.23 0.000204 2.55 1302.97 385.24 0.17
R1 4086.8 50YR 2840.00 85.00 94.27 94.32 0.000142 2.35 1790.99 482.70 0.15
R1 4086.8 100YR 3075.00 85.00 94.63 94.67 0.000128 2.29 1964.10 482.70 0.14
R1 4060.2 10YR 2290.00 83.00 92.80 89.71 93.19 0.001162 5.03 455.67 86.21 0.39
R1 4060.2 50YR 2840.00 83.00 93.86 90.32 94.27 0.001043 5.16 550.33 92.12 0.37
R1 4060.2 100YR 3075.00 83.00 94.19 90.56 94.63 0.001031 5.29 581.51 95.93 0.37
R1 4040.8 Bridge
R1 4015.7 10YR 2290.00 82.00 92.50 92.88 0.000926 4.96 463.33 76.63 0.35
R1 4015.7 50YR 2840.00 82.00 93.50 93.93 0.000890 5.27 541.92 80.14 0.35
R1 4015.7 100YR 3075.00 82.00 93.79 94.26 0.000919 5.48 565.59 81.17 0.36
R1 3990.3 10YR 2290.00 82.00 92.13 92.77 0.001958 6.41 357.44 68.32 0.49
R1 3990.3 50YR 2840.00 82.00 93.19 90.17 93.83 0.001752 6.49 476.16 304.74 0.48
R1 3990.3 100YR 3075.00 82.00 93.67 94.21 0.001414 6.07 625.04 306.29 0.43
R1 3900.3 10YR 2290.00 79.00 92.19 92.57 0.000911 5.00 457.61 69.35 0.34
R1 3900.3 50YR 2840.00 79.00 93.22 93.66 0.000917 5.34 535.33 106.82 0.35
R1 3900.3 100YR 3075.00 79.00 93.63 94.08 0.000884 5.44 591.97 169.80 0.35
R1 3810.1 10YR 2290.00 81.00 92.32 92.45 0.000384 2.89 795.57 170.15 0.22
R1 3810.1 50YR 2840.00 81.00 93.39 93.52 0.000318 2.92 1011.89 217.34 0.21
R1 3810.1 100YR 3075.00 81.00 93.81 93.94 0.000297 2.93 1104.01 219.10 0.20
R1 3710 10YR 2290.00 82.00 92.01 92.36 0.001148 4.76 481.46 98.85 0.38
R1 3710 50YR 2840.00 82.00 93.12 93.45 0.000879 4.68 659.33 210.45 0.34
R1 3710 100YR 3075.00 82.00 93.57 93.88 0.000768 4.56 754.99 211.61 0.32
R1 3647.7 10YR 2290.00 81.00 91.91 92.28 0.001199 4.92 465.10 91.77 0.39
R1 3647.7 50YR 2840.00 81.00 93.02 93.39 0.000966 4.90 614.55 181.84 0.36
Bridge FAC#221 - Existing Condition
HEC-RAS Plan: Plan 04 River: Hutchinson Creek Reach: R1 (Continued) Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
R1 3647.7 100YR 3075.00 81.00 93.48 93.82 0.000861 4.81 697.95 183.52 0.34
R1 3615 10YR 2290.00 79.00 91.91 92.23 0.001022 4.58 499.58 95.26 0.35
R1 3615 50YR 2840.00 79.00 93.03 93.35 0.000819 4.56 673.90 220.91 0.32
R1 3615 100YR 3075.00 79.00 93.49 93.78 0.000716 4.45 776.22 221.81 0.31
R1 3540.8 10YR 2290.00 78.00 91.83 92.17 0.000737 4.68 499.81 98.26 0.31
R1 3540.8 50YR 2840.00 78.00 92.92 93.28 0.000690 4.91 614.36 105.89 0.30
R1 3540.8 100YR 3075.00 78.00 93.35 93.72 0.000671 4.98 660.21 106.34 0.30
R1 3502.7 10YR 2290.00 82.00 89.44 89.44 91.89 0.008859 12.54 182.62 37.48 1.00
R1 3502.7 50YR 2840.00 82.00 90.30 90.30 92.99 0.008644 13.14 216.10 40.44 1.00
R1 3502.7 100YR 3075.00 82.00 90.64 90.64 93.42 0.008559 13.37 230.07 41.61 1.00
R1 3461 10YR 2290.00 81.00 88.28 88.83 91.39 0.012163 14.16 161.77 34.93 1.16
R1 3461 50YR 2840.00 81.00 89.13 89.71 92.50 0.011668 14.74 192.72 37.82 1.15
R1 3461 100YR 3075.00 81.00 89.45 90.05 92.95 0.011577 15.00 205.04 38.91 1.15
R1 3275.4 10YR 2290.00 80.00 88.94 87.28 90.17 0.003609 8.90 257.31 45.11 0.66
R1 3275.4 50YR 2840.00 80.00 89.70 88.09 91.17 0.003901 9.71 292.50 47.52 0.69
R1 3275.4 100YR 3075.00 80.00 89.99 88.41 91.56 0.004024 10.03 306.45 48.44 0.70
R1 2985.4 10YR 2290.00 79.00 87.09 86.46 88.77 0.006374 10.40 220.26 48.05 0.86
R1 2985.4 50YR 2840.00 79.00 88.22 89.83 0.005440 10.17 279.21 56.02 0.80
R1 2985.4 100YR 3075.00 79.00 88.68 90.25 0.005065 10.05 305.94 59.28 0.78
R1 2910.9 10YR 2290.00 79.00 86.64 88.32 0.005678 10.37 220.75 44.01 0.82
R1 2910.9 50YR 2840.00 79.00 87.71 89.42 0.005268 10.50 270.50 50.12 0.80
R1 2910.9 100YR 3075.00 79.00 88.15 89.86 0.005225 10.48 293.35 54.32 0.80
R1 2839.4 10YR 2290.00 78.00 87.16 87.81 0.001626 6.45 355.30 56.99 0.46
R1 2839.4 50YR 2840.00 78.00 88.21 88.93 0.001613 6.81 417.21 61.12 0.46
R1 2839.4 100YR 3075.00 78.00 88.63 89.38 0.001605 6.94 443.11 62.76 0.46
R1 2389 10YR 2290.00 77.00 84.89 83.82 86.52 0.005001 10.24 223.60 40.22 0.77
R1 2389 50YR 2840.00 77.00 85.80 84.67 87.64 0.005002 10.86 261.42 42.76 0.77
R1 2389 100YR 3075.00 77.00 86.17 84.98 88.08 0.005007 11.08 277.49 44.02 0.78
Bridge FAC#221 - Existing Condition
0 500 1000 1500 2000 2500 3000
2339_BealeAFB Plan: Plan 04 5/17/2017 Existing Condition - Bridge #221
Main Channel Distance (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
LOB
ROB
Hutchinson Creek R1
No Data for Plot
0 20 40 60 80 100 120 140 160
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 5000 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
Bank Sta
.03 .03 .03
0 50 100 150 200 250
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4908.8 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4753.3 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 20 40 60 80 100 120 140 160 180
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4685.2 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4608.9 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4508.1 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 50 100 150 200 250 300 350 400
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4395.1 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4270.3 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 100 200 300 400 500 600
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4154.6 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 50 100 150 200 250 300 350
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4144.1 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 100 200 300 400 500 600 700
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4106.5 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
0 100 200 300 400 500
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4086.8 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4060.2 U/S Prop. Bridge Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4040.8 BR Bridge 221 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 4015.7 D/S Prop. Bridge Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3990.3 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
0 50 100 150 200 250 300
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3900.3 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3810.1 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
.03 .03
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3710 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3647.7 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3615 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
0 20 40 60 80 100 120
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3540.8 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
0 50 100 150 200
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3502.7 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Bank Sta
.03 .03 .
0 20 40 60 80 100 120 140
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3461 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 3275.4 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Ineff
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 2985.4 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 2910.9 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
Bank Sta
.03 .03 .
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 2839.4 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
2339_BealeAFB Plan: Plan 04 5/17/2017 River = Hutchinson Creek Reach = R1 RS = 2389 Existing Condition - Bridge #221
Station (ft)
El ev at io n (ft
Legend
WS 100YR
WS 50YR
WS 10YR
Ground
HEC-RAS Plan: Plan 04 River: Hutchinson Creek Reach: R2 Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
R2 5000 10YR 850.00 97.00 97.98 97.98 98.45 0.013701 5.30 154.92 166.47 1.00
R2 5000 50YR 1540.00 97.00 98.43 98.43 99.13 0.012183 6.58 230.01 166.80 1.01
R2 5000 100YR 1745.00 97.00 98.55 98.55 99.31 0.011894 6.88 249.87 166.80 1.01
R2 4976 10YR 850.00 88.00 90.28 91.91 97.03 0.112014 20.84 40.79 28.13 3.05
R2 4976 50YR 1540.00 88.00 91.40 93.25 97.94 0.061332 20.52 75.05 33.36 2.41
R2 4976 100YR 1745.00 88.00 91.71 93.61 98.16 0.053826 20.37 85.66 34.82 2.29
R2 4947 10YR 850.00 89.00 91.03…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.