FA465915R0003-_Technical_Specifications.pdf
PDF 1 MB Posted
- Attached to
- Maintain Airfield Striping Federal contract opportunity
- Solicitation number
- FA4659-15-R-0003
About this file
FA465915R0003- Technical Specification
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA465915R0003-Amendment_0005.pdf | ||
| FA465915R0003-Amendment_0004.pdf | ||
| FA465915R0003-Amendment_0003.pdf | ||
| FA465915R0003-Amendment_0002.pdf | ||
| FA4659-15-R-0003-0001 _SF_30_Amendment.pdf | ||
| FA4659-15-R-0003-0001 _SF_1442_Conformed_Solicitation.pdf | ||
| FA465915R0003-Climatological_Summary_Data.pdf | ||
| FA465915R0003-Past_and_Present_Performance_Questionnaire.pdf | ||
| FA465915R0003-Schedule_of_Material_Submitals.pdf | ||
| FA465914R0003-Financial_Institution_Reference_Sheet.pdf | ||
| FA465915R0003-Drawings.pdf | ||
| FA465915R0003-SF1442_Solicitation.pdf | ||
| FA465915R0003-Solicitation_Cover_Letter.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAINTAIN AIRFIELD STRIPING
JFSD 201215
SPECIFICATIONS
GRAND FORKS AFB, ND
SPECIFICATIONS TABLE OF CONTENTS
JFSD201215
“MAINTAIN AIRFIELD STRIPING”
Section 01000 Technical Provisions………………………………………...…………….37 pages Section 2400.02 Specification for Pavement Marking……………………………………..7 pages Section 32 17 24.00.10 Pavement Markings……………………………………………….8 pages i
JFSD201215
MAINTAIN AIRFIELD STRIPING
Technical Provisions
Section 01000
1. SCOPE OF WORK:
Work to Be Done: The work consists of furnishing all plant, labor and materials to perform all work 1.1.
in strict accordance with these technical provisions and the project drawings.
Location: The site of the work is Grand Forks Air Force Base, ND. 1.2.
2. PROJECT DESCRIPTION: The work to be performed includes, but is not limited to, the following:
Perform existing pavement marking removal on primarily the airfield by means of water-blasting and 2.1.
sand-blasting. This will include all of the pavement markings on the runway, landing zones and overruns.
Apply reflective and non-reflective airfield marking paint to match the existing pavement markings 2.2.
currently in place on the Main Runway, Parallel Taxiway, Taxiways Bravo, Charlie, Delta, Echo, Foxtrot, and Golf; Bravo and Charlie Ramps, 600 Ramp and 3-Bay Hangar Ramp.
2.3. In accordance with AFI 91-203, apply yellow marking paint to delineate five foot caution zones on both sides of all hangar doors. Include danger signs indicating pinch/crush points. Signs shall state
“DANGER” “HAZARDOUS AREA – STAND CLEAR DURING DOOR OPERATIONS.”
2.4. Provide continuous Foreign Object Debris (FOD) cleanup on both the airfield and haul routes.
Provide daily/regular sweeping for FOD of areas traversed by the contractor and/or in compliance with Base Operations requirements.
2.5. Provide all other basic contract requirements (i.e., submittals, construction schedule, waste disposal plan, etc.) as set forth in these specifications.
All material selections, construction, renovation, repair, and maintenance shall comply with the latest 2.6.
addition of Unified Facilities Criteria UFC 3-600-1, Fire Protection Engineering for Facilities.
Obtain permits, documentation, and apply/execute all other administrative and field requirements for 2.7.
compliance with North Dakota State rules and regulations and the Environmental Protection Agency (EPA) rules and regulations as they apply to Storm Water Pollution Prevention for construction activities.
The contractor shall coordinate with the appropriate facility mangers, Civil Engineering personnel and 2.8.
Security Forces personnel to the extent necessary to provide area access, develop required plans, traffic control, and to permit ongoing mission requirements. This coordination shall be completed and approved by 319 CES and/or the Contracting Officer (CO) ten days prior to the start of on-site work. Preliminary site investigations to prepare required submittals and plans may have to be complete prior to the ten day requirement of user coordination.
All work not specifically addressed in this specification or specifications thereafter shall be installed 2.9.
in strict accordance with the latest publications of the National Electric Code, Uniform Building Code, Uniform Mechanical Code, Uniform Plumbing Code, NFPA 101 Life Safety Code, and Grand Forks AFB
01000 - 1 JFSD 201215
December 2014
Architectural Compatibility Guide. The GFAFB Architectural Compatibility Guide is not included in the specifications package, but will be provided upon request.
International Conference of Building Officials has established the basic building code standards for 2.10.
construction, renovation, repair, and maintenance. These standards, commonly referred to as the International Building Code (IBC), together with the Unified Facilities Criteria UFC 1-200-01 found at http://www.wbdg.org/ccb/DOD/UFC/ufc_1_200_01.pdf (dated 1 July 2013) shall constitute the minimum acceptable levels of construction, function, and safety for all projects.
3. STANDARD TESTS, QUALITY, AND GUARANTEES:
Tests or trials to determine the effectiveness of performance of a completed assembly or fabricated 3.1.
system shall be made by the contractor.
All articles, supplies and equipment, parts, and assemblies thereof, of standard manufacturers or for 3.2.
which design requirements are not prescribed by these specifications shall be guaranteed against any failure in the proper use or operation caused by defective material, workmanship, or design for the full warranty time which is standard with the manufacturer and/or supplier.
The contractor shall provide a minimum one year warranty on all work performed. A copy of the 3.3.
warranty shall be submitted to the Contracting Officer before final inspection of the facility.
4. WORK CLEARANCE REQUEST AND OTHER PERMITS:
Digging Permit: AF Form 103, Base Civil Engineering Work Clearance Request, commonly referred 4.1.
to as a “Digging Permit”. The contractor shall initiate, prepare, and hand carry for signatures an AF Form 103, Work Clearance Request, 14-28 calendar days prior to any work (especially excavation) activities.
Base Civil Engineering will assist the contractor by providing points of contact; however, the responsibility for executing and tracking status of the work clearance request and coordinating utility markings with the Base Civil Engineer shops and/or other utility companies is solely that of the contractor. The contractor shall compose and provide sketches/drawings/ and dimensioning details showing the specific location of the intended area of work (especially excavation) when requesting an AF 103. The contractor shall physically stake, flag, or demarcate (in accordance with base civil engineer work clearance manager) to define the boundaries of all required utility locates at the location of proposed work. The contractor should allow 10-20 days for processing the work clearance request between the various activities that must coordinate on the request. The contractor shall submit to the CO and provide the Construction Representative with a copy of the completed AF Form 103 with all attached record utility drawings, and shall comply with all instructions for hand excavation and other methods of safeguarding the buried utilities prior to on-site work. The contractor shall take caution within the area 3 feet to either side of a utility pre-identified to the contractor. If the contractor damages any utility within this six-foot boundary, the contractor is responsible for restoring the utility to its original working condition. Work to repair the damaged utility will commence immediately and will continue uninterrupted until the utility is restored. If the contractor damages a utility that was not identified or is not within the 6-foot boundary of the utility marking, the contractor shall notify the CO and Construction Representative to determine the method of repair (i.e., in-house or by contract). If the damaged utility requires repair by an outside source or someone not in the contractor’s employ (e.g., someone to repair specialty lines) and the contractor is responsible for the damage; the contractor shall coordinate and schedule such persons making the repairs and shall furnish prompt payment for the work to such persons.
USAF Welding, Cutting, or Brazing Permit: NOT USED. 4.2.
01000 - 2 JFSD 201215
http://www.wbdg.org/ccb/DOD/UFC/ufc_1_200_01.pdf
Demolition and Asbestos Notification: NOT USED. 4.3.
Air Permit: NOT USED. 4.4.
5. UTILITIES COORDINATION: NOT USED.
6. FIRE REGULATIONS: NOT USED.
7. CONTRACTOR USE OF PREMISES:
GENERAL: The government does not guarantee a lot on Grand Forks Air Force Base for contractor 7.1.
use, but there is the possibility for placement in Contractor’s Row.
7.1.1. Storage Area: All contractor storage shall be located in an area located inside the boundary of the project site and shall be properly screened and secured. Indoor storage areas are not guaranteed by the government, and there are no alternate storage areas on base. The contractor may store materials and trailers off base at the contractor’s expense.
7.1.2. A visually acceptable site at Grand Forks Air Force Base is an important construction standard.
Contractor storage sites made available on the work site shall be properly screened from public view, kept clean and secured by the contractor at the contractor’s expense. The contractor shall maintain trailers and portable storage containers in good condition or must remove them when no longer required. The exterior appearance of such items shall be in accordance with base color standards (Light Brown SW6093, Linen White SW6119, Medium Brown SW 6067, and Dark Bronze SW 6006). The contractor is solely responsible for the security of contractor property and general housekeeping of the project area(s). This includes, but is not limited to, vegetation (weed control) and height maintenance to base standards, daily trash and refuse debris collection and containerization, and construction materials stacked, neatly palletized or enclosed in trailers.
7.1.3. The government will provide utilities (water and electricity) for project work areas when available.
The government will NOT modify points of distribution to accommodate contractor project activities. The contractor may modify points of distribution at contractor expense with prior approval from the CO. The government will not provide utilities solely for construction heating purposes. At remote project work areas where no utilities are available, the contractor shall furnish utility services.
7.1.4. When an on-site water source is required and the only reasonable option, the government will furnish water from a fire hydrant or an adjacent facilities point of distribution selected by the Base Civil Engineer with coordination through the Base Fire Dept and the Contracting Officer (CO). The contractor shall provide and install the proper backflow prevention device, valve and hydrant wrench. The contractor shall be liable for any damage caused to government property resulting from improper operation of fire hydrant(s).
7.1.5. Contractor personnel may use existing toilet facilities if available on the premises and approved by the facility occupants/facility manager unless otherwise instructed by the CO or designated representative.
At construction sites where toilet facilities are not readily available, the contractor shall provide chemical sanitary toilets. The contractor shall service the chemical toilets regularly subject to government inspection by the base medical officer. The contractor shall correct all identified sanitary deficiencies within 24 hours of inspection.
7.1.6. Elevators: NOT USED.
01000 - 3 JFSD 201215
7.1.7. Explosive Operated Hand Tools: NOT USED.
7.1.8. Severe Weather: The contractor shall develop and be prepared to implement procedures to evacuate and/or protect people and facilities under the contractor’s control in the event of severe weather. These procedures shall include provisions for securing or repositioning of equipment. The contractor shall notify the CO of any evacuation procedures. Upon receipt of a severe weather warning, the following sequence of actions shall occur.
7.1.8.1. The CO or designated representative will instruct the contractor of the severe weather warning.
7.1.8.2. The contractor shall take immediate action to tie down, remove, protect, or secure contractor materials and equipment to the satisfaction of the Air Force construction representative, providing reasonable assurance that the severe weather will not damage government property. If the contractor fails to secure materials and equipment and it becomes a hazard, Air Force personnel may accomplish the work and potential charges to the contractor may result thereof.
7.1.9. Temporary Closures: To prevent outside intrusion into a work area, at the end of each day the contractor shall close up each and every exterior fence or security barrier (as applicable) resulting from work. Closure(s) shall remain in place when the contractor is not actively working on the site(s), including each and every day, night, weekends, and holidays to sustain in-place security. Temporary closure(s) shall be constructed of same material as originally removed and anchored in place if necessary, or similar construction as approved by the base civil engineer through the CO.
7.1.10. Access Roads: In accordance with Dirt and Dust Control contained herein, and as required (minimum at the end of each day), the contractor shall inspect for and clear all mud, dirt, debris, foreign objects, or spills of any kind from the contractor’s operations (including subcontractors and suppliers) on streets and parking lots used as access to the work or staging areas. The contractor shall ensure all taxiways, runways, parking aprons and hard surfaces in or around the airfield, used to access the work or staging areas, remain clean at all times.
7.1.11. Contractor-Generated Refuse: Prior to completion of the work each day, the contractor shall handle, transport, store, and dispose of all waste materials and rubbish generated by any work under this contract. If the contractor temporarily stores waste material or rubbish in a dumpster controlled by the contractor, the contractor shall secure the dumpster in such a manner that prevents unauthorized use.
Unsecured and unattended dumpsters tend to collect stray refuse from other than contract operations. To avoid this, the contractor shall secure the dumpster during non-working times and post signs (if necessary) on the dumpster(s) noting it as NOT FOR PUBLIC USE. On a regular (minimum weekly) basis, the contractor shall remove and dispose of any waste or excess material resulting from any contract requirement, off base at no expense to the government. The contractor shall dispose of such materials in accordance with applicable federal, state, or local laws, ordinance or regulations. Trucks for hauling refuse and waste materials shall have tight fitting covers to prevent spillage on roadways. The contractor shall use designated haul routes as agreed upon in discussions prior to on-site project work.
7.1.12. Excavations: NOT USED.
7.1.13. Screening: NOT USED.
7.1.14. Covered Chutes: NOT USED.
7.1.15. Contaminated Soils: NOT USED.
01000 - 4 JFSD 201215
7.1.16. Wet Lands: NOT USED.
7.1.17. HAZMAT: The contractor shall handle and store hazardous materials only in areas approved by the agency responsible for the specific material (i.e., fire department, environmental element, etc.), and comply with the contractor’s approved, and the bases Spill Prevention and Countermeasures Plan (319 CES/CEIE: POC). The contractor shall report any spill of oil or hazardous material to the civil engineer service call desk, and take every reasonable precaution to prevent/contain the spillage of oil or other hazardous substances.
7.1.18. Disposals: The contractor shall control the disposal of fuels, oils, bitumens, calcium chloride, acids, or harmful materials, both on and off government premises and shall comply with applicable federal, state, county, and municipal laws concerning pollution of rivers and streams while performing work under this contract. The contractor shall NOT dispose of any waste or residual material on the ground or in any storm sewer or drainage system. The contractor shall take special measures to prevent chemicals, fuels, oils, greases, bituminous materials, herbicides, and insecticides from entering public waters. Do not allow water used in on-site material processing, concrete curing, foundation and concrete clean-up, and other waste waters to re-enter a stream if an increase in the turbidity of the stream could result.
7.1.19. Emissions: The contractor shall limit emissions of organic solvents into the atmosphere. This rule applies to use, clean-up, and disposal of organic, photo chemically reactive, and non-photochemically reactive solvents and materials containing these solvents.
7.1.20. VOC: The contractor shall limit the quantity of volatile organic compounds in exterior paint coatings. This applies to any coatings applied to stationary structures and their appurtenances, pavements, and curbs.
7.1.21. Lead Content: The contractor shall NOT use paints or coatings containing lead in excess of 0.009 percent by weight of total non-volatile content in accordance with Title 16 of the Code of Federal Regulations, Part 1303. Pavement paints or coatings within reach of children in housing, recreation, and public areas shall have zero lead content.
7.1.22. PCBs: The contractor shall deliver all items indicated on the drawings or in the specifications containing PCBs and all oil-cooled transformers removed from service for disposal to a storage area on base as directed by the environmental coordinator through the CO. If equipment labels or catalog data does not specify composition, the contractor shall have all electrical equipment cooling liquid tested by a certified laboratory to determine if PCB is present. Drain and properly contain oil from transformers and flush the system to the required level. Clean, seal, and label all drums. Include an original of the certified report to the environmental coordinator. New electric equipment shall not contain PCBs, shall be certified to this effect, and shall be stamped or labeled “NO PCB”.
7.1.23. Noise Control. The contractor shall comply with all applicable state and local laws, ordinances, and regulations relative to noise control.
7.1.24. Recording and Preserving Historical and Archaeological Finds: NOT USED.
7.1.25. Vehicle Control: The contractor shall NOT park or run vehicles on grass areas for shortcuts and/ or convenience. Only equipment required in direct performance of work will be permitted to enter grass areas. The contractor shall repair or replace any damage done to lawns or shrubs caused by construction equipment or related project activities. Contractor personnel shall load all loose debris on trucks leaving the site in a manner that will prevent dropping materials on streets and conform to local ordinances. Fasten
01000 - 5 JFSD 201215
a suitable cover such as a tarpaulin over the load before entering surrounding streets. The contractor shall promptly clean up any materials that falls from trucks. The use of cell phones is prohibited on Grand Forks AFB while operating a motorized vehicle. Seat belts are required at all time while driving a vehicle. Base speed limits are strictly enforced and violation(s) may result in suspended base driving privileges.
7.1.26. Equipment Condition: Equipment and vehicles used on base shall be safe and in good operating condition. The contracting officer (CO), CM, Base Safety, or designated representative reserves the right to inspect any on-base equipment and reject such equipment if deemed unsafe, in poor operating condition, or inappropriate for the work being performed.
7.1.27. Government Furnished Equipment: As a rule, the government will NOT furnish equipment/materials (GFE/GFM) except for equipment specified in the solicitation/RFP or elsewhere in these specifications. However, the government reserves the right to provide GFE/GFM for use on any contract or delivery order. In such cases, the contract or delivery order shall contain Schedule D, Schedule of Government Furnished Property listing GFE/GFM that pertain to the project. The contractor shall transport all GFE/GFM, if any, from the government storage area to the work site indicated. Once GFE/GFM is released to the contractor for transportation to the project site, the contractor shall assume the risk and responsibility for the loss or damage to GFE/GFM. The contractor shall follow the instructions of the CO or authorized representative regarding the disposition of GFE/GFM not consumed in performance of this contract.
PLANS: 7.2.
7.2.1. Project Site Plan: Prior to starting work, the contractor shall submit an individual Site Plan through the CO to the Construction Manager for approval showing the layout and details of all pertinent attributes used for the project. The base approval authority, normally the Construction Manager and/or Base Civil Engineer, will approve the plan prior to on-site activities. The plan shall include the location of the safety and construction fences, location of all site trailers, equipment and material storage area, construction entrances, trash dumpster locations, temporary sanitary facilities, and worker/construction vehicle parking areas. Overhead site diagrams, and or photographs prior to the start of work may be included with the plan. The CM can provide overhead site photographs to assist the contractor in completion of the project site plan. All areas which may have the potential to tracking of earthen materials shall also be identified.
The contractor shall also indicate if the use of a supplemental or other staging area is desired. At completion of work, the contractor shall remove the temporary facilities and restore the site to the original, pre-work condition.
7.2.2. Dirt and Dust Control Plan: As part of the project site plan, or as an individual plan, the contractor shall identify and submit for approval truck and material haul routes leading from the base entry point to the work site. This plan shall include details for controlling fugitive dust, dirt, debris, and rubbish generated on established base haul route/roadway caused by construction activities. As a minimum, the plan shall identify the contractor’s equipment utilized for cleaning along the haul route and measures to prevent and reduce dirt, dust, and debris from being deposited and dispersed along roadways. The plan shall also include frequency of maintenance/cleaning.
7.2.3. Health & Safety Plan: The contractor shall submit a complete health and safety plan for the proposed work. Plan/Program shall be in compliance with EM 385-1-1, OSHA, 29 CFR 1910, and other occupational health and safety requirements of the contract. Plan shall provide a detail description of procedures to comply with health and safety requirements.
CONTRACTOR’S TEMPORARY FACILITIES: 7.3.
01000 - 6 JFSD 201215
7.3.1. Administrative Field Offices: Contractor's administrative field office shall be in good to new condition, and the exterior color must adhere to base standard color standards as stated previously in this section. Locations, if granted, shall be pre-approved by the CM/Base Civil Engineer through the CO.
Storage of material/debris under the trailers is prohibited. Power and water will be provided by the government in reasonable quantities, and if they are reasonably available within proximity of the approved location. Connections to existing government utilities shall be made by the contractor at no expense to the government. Modification of existing points of distribution from existing government infrastructure shall be approved prior to, and performed by the contractor at no additional expense to the government. Communication lines and service will not be provided by the government. The contractor shall utilize available commercial services as necessary. The duration of such field office presence will be determined by the government upon request of the contractor.
7.3.2. Dumpsters: Dumpsters shall be painted dark bronze SW6006 and equipped with secure covers.
The cover shall be closed at all times, except when being loaded with trash and debris. Locate dumpsters behind the construction fence or out of public view. Empty site dumpsters when they attain 90% of full capacity, or as needed to allow full closure of the covers. All other exterior trash containers shall be dark bronze SW6006 utilized in the construction site area. Locate the trash containers behind the construction fence or out of the public view. Empty trash containers as required to prevent over filling. Large demolition normally requires a large dumpster without lids-these are acceptable but shall not have debris higher than the sides before emptying. Ensure mandated recyclable material (paper, glass, cardboard, etc.) is collected and taken to the recycling center at Building 672.
7.3.3. Temporary Sanitation Facilities: All temporary sewer and sanitation facilities shall be self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the Contracting Officer. The doors shall be self-closing. The exterior of the unit will match the base standards (Ref 7.1.2 this section), unless the facility is behind the construction fence or out of the public view.
7.3.4. Construction Site Maintenance, Safety Fence, and Construction Fence:
7.3.4.1. Site Maintenance: The construction site must be kept neat, clean, and free of debris. Clean-up shall be performed at the end of each work day in conjunction with a complete general clean up at the end of the project. Cut grass (to include weeds) within the construction and storage sites to maintain a maximum height of 4 inch or less. Trim grass around fences and other obstructions where a mower cannot reach. Grass and/or weeds allowed to grow on stockpiled earth are not acceptable at any height.
Contractor identification signs are not required, however if the contractor chooses to erect signs at construction sites, they will be in compliance with base requirements and color scheme and approved by the CM/Base Civil Engineer before being erected.
7.3.4.2. Safety Fence: NOT USED.
7.3.4.3. Construction Fence: NOT USED.
7.3.5. Indoor Barricades: As necessary, the contractor shall furnish, install, and maintain adequate barricades and warning signs to isolate the construction area from other building entrances, and to delineate wet paint areas.
7.3.6. Outdoor Barricades: The contractor shall furnish, install, and maintain adequate barricades, warning signs, and warning lights to isolate outdoor construction areas. The contractor shall identify and barricade all open trenches and excavations at the end of each work day. In the vicinity of traveled ways (pedestrian and vehicular), the contractor shall use flashing barricades with spacing not to exceed 25 feet.
01000 - 7 JFSD 201215
In other areas, the contractor may use unlit barricades, flagging, rope, fences or other suitable means. The contractor shall comply with all pertinent provisions of the Corps of Engineers EM 385-1-1, Safety and Health Requirements Manual, including any revisions.
8. GOVERNMENT FURNISHED SERVICES AND UTILITY AVAILABILITY: All reasonable quantities of utilities (water and electricity) will be made available to the contractor without charge. The Government may not be held responsible for interruptions of utility service and shall not be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.
Water: A centrally-located water filling station for contractors is located at Facility 328. This is the 8.1.
preferred location to fill water trucks/portable tanks. For more information regarding the filling station, contact the designated construction representative.
Refuse Collection: The contractor is responsible for disposing of construction debris and contractor-8.2.
generated refuse at construction sites safely and properly in accordance with this section. The recycle center is for base residents only, contractors shall dispose of recyclables at own expense off-base.
Insect and Rodent Control: If the contractor detects an insect or rodent problem, notify the 8.3.
appropriate facility manager or construction representative for entomology services.
Security Police and Fire Protection: The government will provide security police and fire protection 8.4.
services to the extent necessary to ensure a safe, secure construction site. In return for these services, the contractor shall adhere to the security and fire directives, instructions, and policies of Grand Forks AFB.
Emergency Medical Services: In the event of a severe emergency, the 319th Medical Facility, during 8.5.
hours of operation, will respond and transport, if necessary, a contractor employee to a local hospital. The contractor shall reimburse the government for these services.
9. WORK SEQUENCE:
Commencement of Work: Notice To Proceed (NTP) letters shall be the instruction to commencement 9.1.
of work for said contract. Work shall begin within the number of days specified on the contract.
Project Execution: The work performed under this contract will be adjacent to occupied and 9.2.
unoccupied facilities/areas. The contractor shall perform all work with continuous daily progress. The government will not accept or permit days of no work or periods of inactivity by the contractor except for drying or curing of previous work or as directed by the CO. In some cases, the government will require the contractor to work around building entrances or make accommodations for facility access within the overall work area to facilitate the contractor’s work and safe access/egress from a facility. The contractor shall protect all government facility exterior appurtenances and landscaping within the work area from overspray, debris, and damage. The government will hold the contractor responsible for any damages caused by contractor operations as a result of lack of adequate protection of government property. NOTE:
Once finishes become stained/damaged and cannot be restored, the contractor shall be held responsible to replace such items at no cost to the government. The contractor shall maintain the work site, entry/egress, and vehicular exits free of debris and provide for safe egress at all times. Contractor personnel shall strictly adhere to safety standards (OSHA and AFOSH) and practices at all times during the contract term.
Forced Work Stoppage: In case of emergency, the contractor shall call 911. The CO, base fire chief, 9.3.
and other base-authorized emergency response personnel, or their representative(s), have the authority to order the contractor to terminate work and clear the area of personnel and equipment. The contractor shall comply with such an order with all possible speed. When the previously mentioned authority figures or
01000 - 8 JFSD 201215
representative(s) interrupt the contractor’s operations, the contractor shall immediately notify the contracting officer of the delay.
Interruption of Utility Services: The contractor shall not hold the government responsible for 9.4.
interruptions of utility service. Nor will the government be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service. The contractor, at his own expense, may provide backup power generation and such in the event of base utility outages.
Work in Secure Areas: The contractor shall comply with security regulations imposed by the 9.5.
installation commander and/or the agency responsible for the project location. Rules of entry will be established and directed to the contractor at the preconstruction meeting for associated projects. For specifics, refer to Section 17 for Base Entry Procedures and Airfield Requirements.
10. ADMINISTRATION REQUIREMENTS:
CONTRACTOR PERSONNEL REQUIREMENTS: 10.1.
10.1.1. Subcontractors and Personnel: Furnish a list of key contact personnel of the contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
10.1.2. Supervision: Provide at least one qualifying supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, that individual shall also possess fluent English communication skills. The Contractor shall submit a letter to the CO designating both site supervisor for task delivery orders and a project manager for the duration of contract.
10.1.3. Project Management: The contractor shall have available a project construction manager to respond to the requirements of this contract. The contractor’s project manager shall have sufficient authority to effectively manage the contract from the project location or reasonable proximity. The contractor shall notify the CO and the CE Construction Representative when the project manager plans to be absent and/or unavailable to include duration of such absence.
Records Management Requirements by the Contractor: The contractor shall make available in a 10.2.
timely manner, any permits, reports, or general performance data required in the PWS/SOW. The contractor shall also mark any/all proprietary information in the records submitted to the Air Force/government for Freedom of Information Act purposes. The contractor shall create, handle and maintain records for the Air Force, regardless of medium, (in a pre-agreed medium that can be used by the Air Force ) in accordance with the requirements established in AFRIMS Records Disposition Schedule (RDS), AFI 33-322, Records Management program, AFI 33-364, Records Disposition Procedures and Responsibilities, and AFMAN 33-363, Management of Records. Full text versions of these publications are available for download at http://www.e-publishing.af.mil. The contractor’s records person should attend Records Management Orientation Training conducted by the Base Records Manager. Inquiries as to the specific actions necessary to meet the requirements established in the above-referenced publication may be directed to the GFAFB Records Management Office at (701) 747-6143 or 319th CS/SCXK, Bldg 314, GFAFB, ND, 58205-6436.
PRECONSTRUCTION CONFERENCE: After award of the contract, but prior to commencement 10.3.
of any work at the site, the contractor shall meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, 01000 - 9 JFSD 201215 http://www.e-publishing.af.mil/ preparation of the schedule prices, shop drawings, and other submittals, scheduling, programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
AVAILABILITY OF CADD DRAWING FILES: After award and upon request, the electronic 10.4.
“Computer-Aided Drafting and Design (CADD)” drawings files will be made available to the contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the contractor and without liability or legal exposure to the Government. The contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney’s fees and defense costs, arising out of or resulting from the use of these electronic files. These electronic CADD drawing files are not construction documents. Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files and the corresponding construction documents. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
ELECTRONIC MAIL (E-MAIL) ADDRESS: The contractor shall establish and maintain electronic 10.5.
mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to, contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the contractor of base access conditions when emergency conditions warrant, such as blizzards, terrorist threats, etc. Multiple email address will not be allowed. It is the contractor’s responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office (s). The contractor shall promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.
11. NOTIFICATION TO THE CONSTRUCTION MANAGEMENT OFFICE (CMO) AND PROJECT
COORDINATION: The contractor shall notify the CMO (Designated Construction Representative) at least seven days in advance of starting all work. This shall include, but is not limited to, notification when the initial work shall begin; when work shall resume after stoppage exceeding five work days; and when work shall begin following all specified exclusion periods. The official Notice to Proceed does not constitute sufficient notification to CMO that work shall begin.
The contractor shall coordinate all work schedules with the contracting officer (CO) and with the 11.1.
designated Base Civil Engineer Construction Representative (CR) prior to the start of work. The contractor shall participate in progress meetings as directed by the CO and/or the CR. Attendance at these meetings may include the contractor’s corporate management representative(s) at the CO’s discretion.
01000 - 10 JFSD 201215
Interruption of Activities to Base Personnel: If it becomes necessary to interrupt base activities in 11.2.
buildings and/or areas for construction purposes (except as otherwise described in the contract), the contractor shall request permission, in writing, from the CO five (5) working days in advance. The contractor shall submit written requests for approved street/parking lot closures ten (10) working days prior to closing of the street/parking lot.
Work Near Medical Facilities: NOT USED. 11.3.
Work on Military Family Housing Projects: NOT USED. 11.4.
Contractor Furnished Equipment Data: NOT USED. 11.5.
Work Schedule: Grand Forks Air Force Base standard work hours are 0800 to 1630 hours; Monday 11.6.
through Friday, excluding Federal holidays. Working hours for the contractor will normally align with the base standard hours. If the contractor desires to work during periods other than the base standard work hours, additional Government inspection forces may be required. Therefore, to gain approval to work non-standard hours/days, the contractor shall make a written request to the Contracting Officer a minimum of three working days in advance of the contractor’s intention to work during periods other than standard work hours/days. Additionally, if inspectors are required to perform in excess of normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates may be charged to the contractor. These contract price adjustments may be made as directed by the Contracting Officer.
Requests to work non-standard work times that do not meet the three day notification rule will be highly scrutinized and not normally approved.
12. SUBMITTALS:
Material Submittals: After acknowledgment of Notice to Proceed, the contractor shall submit to the 12.1.
Contracting Officer for approval four hard copies of manufacturer's data, catalog cuts, samples, or other information as required for the items on the Material Submittal Schedule and the Technical Provisions and one electronic copy of the same information. No progress payments will be made until all material submittals are received or other arrangements have been made through the Contracting Officer.
Submittal Preparation: In preparing submittals, it shall be incumbent upon the contractor to clearly 12.2.
and fully demonstrate that proposed materials, systems, or methods meet or exceed all applicable specific requirements of the Technical Provisions. Whenever possible, parameters such as units of measurement, testing protocols and technical vernacular specified in the text will be those employed or referenced by the contractor or his agent in demonstrating compliance. When not possible, the contractor will clearly and fully demonstrate, by written notation, how other parameters, employed or referenced, compare with those specified.
Shop Drawing Submittals: Shop drawings, when required, shall consist of a complete list of 12.3.
equipment and materials, including manufacturer's descriptive and technical literature; performance charts and curves; catalog cuts and installation instructions. Shop drawings shall be prepared to graphically demonstrate proposed layout and anchorage of materials, equipment and appurtenances; and material/equipment relationships to other parts of the work including clearances for maintenance and operation. They shall also contain complete wiring and schematic diagrams; and any other details to graphically demonstrate that a system has been fully coordinated and will properly function as a unit. See Material Submittal Schedule.
12.3.1. Manufacturer’s instructions pertaining to the use or installation of submitted and approved products, materials, or equipment used or installed in the execution of work under this contract form a part
01000 - 11 JFSD 201215
of these specifications as though specifically set forth herein. These instructions apply whether furnished as a normal, usual, or customary practice of the manufacturer or if furnished in response to a requirement stipulated herein. In the event of conflict between the specification of drawings and manufacturers’ instructions, the contractor shall bring such conflict to the attention of the CO for resolution before proceeding with the work involved.
Test Submittals: See Material Submittal Schedule for tests required. 12.4.
Photographs: Photographically document site conditions prior to start of construction operations. 12.5.
Include aerial photographs if applicable and/or available. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer’s Representative. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs, each set on a separate CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
12.5.1. Photography on the airfield requires written approval from the OSS commander. The Government (i.e., someone from 319 CES/CEN) will prepare and staff the letter on behalf of the contractor for the project or a specific delivery order. Photos cannot be taken within the airfield fence or on the airfield until a government photo approval letter is approved by the AF and is in the possession of the contractor while in the act of taking photos on the airfield. If the contractor takes photos on their own accord, without an approved letter in hand; they are subject to Security Forces intervention, confiscation of the camera, and removal from the airfield.
Project Schedule: Prepare for approval a Project Schedule, as specified herein, pursuant to the 12.6.
Contract Clause SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the contractor proposes to perform the work and dates on which the contractor contemplates starting and completing all scheduled activities. Contractor management personnel shall actively participate in Project Schedule development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The schedule must be a forward-planning as well as a project monitoring tool. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the contractor submits the required schedule.
12.6.1. Construction Schedule: In addition to the requirements of paragraph 12.6, prepare and submit to the Contracting Officer for acceptance prior to start of work a construction schedule in the form of a Critical Path Method (CPM), Network Schedule.
12.6.2. Equipment Delivery Schedule:
12.6.2.1. Initial Schedule: Within 30 calendar days after acceptance of the proposed construction schedule, submit for Contracting Officer acceptance a schedule showing procurement plans for materials and equipment. Submit in the format and content as prescribed by the Contracting Officer, and include as a minimum the following information:
01000 - 12 JFSD 201215
12.6.2.1.1. Description
12.6.2.1.2. Date of the purchasing order
12.6.2.1.3. Promised shipping date
12.6.2.1.4. Name of the manufacturer or supplier
12.6.2.1.5. Date delivery is expected
12.6.2.1.6. Date the material or equipment is required, according to the current construction schedule
12.6.2.2. Updated Schedules: Update the construction schedule and equipment delivery schedule at monthly intervals or when the schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation or the delivery dates as directed.
As-Built Drawings: NOT USED. 12.7.
Final As-Built Drawing Preparation: NOT USED. 12.8.
REAL PROPERTY RECORD: NOT USED. 12.9.
Geographic Information System (GIS) and Computer Aided Drafting and Design (CADD): NOT 12.10.
USED.
13. ENVIRONMENT PROTECTION: The contractor shall perform all work in such manner as to prevent the polluting of air, water, or land, and shall follow all applicable federal, state, and local regulations and guidelines. The use of hazardous materials (i.e., lead-based paints, asbestos containing materials and other materials without permission to use) is prohibited. The contractor shall protect against the emission of any hazardous substance(s) that cause or contribute to air pollution and may reasonably be anticipated to endanger health, welfare and the environment.
Publications: The publications listed below form a part of this specification to the extent 13.1.
referenced. The publications are referred to in the text by the basic designation only:
13.1.1. United States Environmental Protection Agency, EPA 832-R-92-005 Storm Water Management for Construction Activities, and the ND State Department of Health Storm Water rules.
13.1.2. Green Procurement Requirements of Section 319002 of Resource Conservation and Recovery Act and Executive Order 13423 Strengthening Federal Environmental Energy and Transportation Management through Environmental Management Systems.
Implementation. After Notice to Proceed and prior to commencement of any work as required 13.2.
under this contract, the contractor shall submit in writing to the CO the required plans (stated herein) for implementing the requirements for environmental protection and pollution control. 319 CES/CEIE (Environmental Compliance) and CM must review and approve all plans submitted by the contractor before site work may begin.
The contractor shall follow North Dakota and EPA guidance 832-R-92-005 Storm Water 13.3.
Management for Construction Activities. Copies are available for review at the Environmental
01000 - 13 JFSD 201215
Compliance Office (319 CES/CEIE), Base Civil Engineering, 525 Tuskegee Airmen Blvd., Grand Forks AFB, ND. ND State Department of Health rules and forms are available at http://www.ndhealth.gov/WQ/Storm/Construction/ConstructionHome.htm.
13.3.1. Prior to on-site work on all projects (as applicable), the contractor shall accomplish the appropriate action from the options listed below. The contractor shall prepare the required documents and applications and submit such to 319 CES/CEIEC. On the Stormwater Permit application (if needed) the contractor shall complete with the exception of the owner information. Once approved, 319 CES/CC or CD will sign as owner and will submit to the North Dakota Dept. Of Health as appropriate. Information regarding the permit can be found at http://www.ndhealth.gov/WQ/Storm/Construction/NDR10per20091001F.pdf
13.3.1.1. If Construction Activity (see permit definitions) area is under 1 acre total; contact 319 CES/CEIEC for a copy of the Grand Forks AFB Storm Water Pollution Prevention Plan (SWPPP) and permit. Any deviations from these documents must have prior approval from this office.
13.3.1.2. Small Site: If…
This is the start of the file's text. The full file is on GovTribe.